Notice of Determination

Dec 13, 2020. Canadian Nuclear Laboratories, on behalf of Atomic Energy of Canada (AECL) has determined that the proposed Cask Facility Project at AECL's Chalk River site is not likely to cause significant adverse environmental effects.

Potential environmental effects will be managed through technically and economically feasible mitigation measures and implemented for the following: air, water, and soil. More specifically, wetlands and streams will be protected, all vegetation clearing will be conducted outside of the breeding season and turtle fences will be installed and maintained around the perimeter of the work site.

Therefore, Canadian Nuclear Laboratories, on behalf of Atomic Energy of Canada may carry out the project, exercise any power, perform any duty or function, or provide financial assistance to enable the project to be carried out in whole or in part.

Document Reference Number: 1

Date modified: