Permits

The Government of Canada is committed to ​improving the efficiency and predictability of regulatory processes ​and to expediting decisions on permits and other authorizations so that projects ​can get built faster while ​advancing reconciliation with Indigenous Peoples and maintaining strong environmental protections.

Below is a dashboard for the project displaying progress against the ​target​s set out in the Cabinet Directive on Regulatory and Permitting Efficiency for Clean Growth Projects, and the status of individual authorizations and permits​ needed for the project to start construction.

Permitting for this project started before the Cabinet Directive was released therefore progress is not displayed against the targets in the Directive.


Start date
May 1, 2023
Completed on
August 6, 2024

Status of permits
2 out of 2 completed

Status of permits

The table below is updated on a monthly basis.

Permits Authority Status Application date Decision date
Metal and Diamond Mining Effluent Regulations Schedule 2 Amendment Environment and Climate Change Canada Approved May 5, 2023 July 18, 2024
Fisheries Act Authorization Fisheries and Oceans Canada Approved June 1, 2023 August 6, 2024

For questions or information, please contact:

Permit Coordination
Impact Assessment Agency of Canada
160 Elgin Street, 22nd floor
Ottawa, Ontario K1A 0H3
permit.coordination.permis@iaac-aeic.gc.ca