Permits

The Government of Canada is committed to ​improving the efficiency and predictability of regulatory processes ​and to expediting decisions on permits and other authorizations so that projects ​can get built faster while ​advancing reconciliation with Indigenous Peoples and maintaining strong environmental protections.

Below is a dashboard for the project displaying progress against the ​target​s set out in the Cabinet Directive on Regulatory and Permitting Efficiency for Clean Growth Projects, and the status of individual authorizations and permits​ needed for the project to start construction.


Overview

Timeline

Start date: July 11, 2025 Target completion date: July 11, 2027
In progress 40%
Elapsed To be completed

Total days for process: 730
Total allocated width: 40%


Start date
July 11, 2025
Target completion date
July 11, 2027

Status of permits
0 out of 2 completed

Status of permits

The table below is updated on a monthly basis.

Permits Authority Status Application date Decision date
Canadian Navigable Waters Authorization, Work Approvals Transport Canada In progress July 11, 2025 -
Fisheries Act Authorization Fisheries and Oceans Canada In progress July 22, 2025 -

For questions or information, please contact:

Permit Coordination
Impact Assessment Agency of Canada
160 Elgin Street, 22nd floor
Ottawa, Ontario K1A 0H3
permit.coordination.permis@iaac-aeic.gc.ca
Date modified: