From the Canadian Environmental Assessment Agency to Treasury Metals Inc. re: Commencement of technical review of the response to Information Request #2 (see related document #33)

PDF Version 128 KB

Document Reference Number: 34

Canadian Environmental Assessment Agency
Ontario Region
55 York Street, Suite 600
Toronto, ON, M5J 1R7

Agence canadienne d'évaluation environnementale
Région de l'Ontario
55, rue York, bureau 600
Toronto, ON, M5J 1R7

March 14, 2019

Sent by E-mail

Mark Wheeler
Director – Projects
Treasury Metals Inc.
130 King Street West, Suite 3680
Toronto, ON M5X 1B1

Dear Mr. Wheeler:

SUBJECT: Commencement of technical review of the response to Information Request#2 of the Goliath Gold Project Environmental Impact Statement.

Thank you for submitting the response to Information Request #2 (IR#2) of the Environmental Impact Statement (EIS) for the Goliath Gold Project (the Project) to the Canadian Environmental Assessment Agency (the Agency) on March 6, 2019. The Agency reviewed the response to IR#2 to determine whether the responses provided by Treasury Metals Inc. (the proponent) were complete, contained sufficient details and were consistent with the direction provided in IR#2.

The Agency has concluded that the response to IR#2 sufficiently meets the requirements of IR#2, and hereby advises you that the Agency is resuming the technical review of the response to IR#2. March 15, 2019 marks the first day lapsed on the federal legal timeline, which will be day 184 of 365.

Meeting the requirements of completeness check does not imply that the information provided is adequate to support the environmental assessment. The Agency may issue further information requirements to you based on the results of the technical review of the response to IR#2 conducted by federal reviewers, and on input received from Indigenous groups.

In accordance with subsections 27(6) and 23(2) of the Canadian Environmental Assessment Act, 2012 (CEAA 2012), the period that is taken by a proponent to comply with the information requirements is not included in the calculation of the time limit within which the Minister's decision must be made. For more information on the approach to managing federal environmental assessment timelines, please consult the Agency's "Operational Policy Statement: Information Requests and Timelines, February 2016" at: http://publications.gc.ca/collections/collection_2016/acee-ceaa/En106-147-2016-eng.pdf

Please note that the response to IR#2 will be posted on the Canadian Environmental Assessment Registry Internet Site and shared with Indigenous groups for consultation purposes.

Should you have any questions regarding the completeness check of the response to IR#2, please contact us at 647-262-8046 or via email at ceaa.goliathmine-minegoliath.acee@canada.ca.