Notice of Determination

North Vancouver, B.C. – May 6, 2020 – The Vancouver Fraser Port Authority has determined that the proposed G3 Terminal Vancouver – Amendment 02 (Extension to Expiry Date and Extended Work Hours) is not likely to cause significant adverse environmental effects.

This determination was based on a consideration of the following factors:

  • Impacts on rights of Indigenous peoples
  • Indigenous knowledge
  • Community knowledge
  • Comments received from the public
  • Technically and economically feasible mitigation measures

Mitigation measures taken into account for this determination are:

  • Activities likely to generate noise are to be concentrated to daytime hours to the extent possible
  • All conditions of Project Permit 15-180 continue to apply during extended work hours and for the duration of the extended permit duration

The Vancouver Fraser Port Authority is satisfied that the carrying out of the project is not likely to cause significant adverse environmental effects.

Therefore, the Vancouver Fraser Port Authority may carry out the project, exercise any power, perform any duty or function, or provide financial assistance to enable the project to be carried out in whole or in part.