Notice of Determination

February 3, 2023 - Infrastructure Canada has determined that the proposed Transmission Main from Chlorine Building to West Link Road Project (the project) is not likely to cause significant adverse environmental effects. Additionnally, it has been confirmed with Parks Canada that the project is not occuring on federal lands and therefore is not subject to an assessment under the Impact Assessment Act. 

This determination was based on a consideration of the following factors:

impacts on rights of Indigenous peoples;
relevant potential environmental effects;
comments received from the public; and
technically and economically feasible mitigation measures.

Mitigation and monitoring measures taken into account for this determination included active and adaptive management measures that would be implemented for the protection of the local environment.  Based on the consideration of these measures, Infrastructure Canada is satisfied that the carrying out of the Project is not likely to cause significant adverse environmental effects.

Therefore, Infrastructure Canada may carry out the Project, exercise any power, perform any duty or function, or provide financial assistance to enable the Project to be carried out in whole or in part.