Gull Bay Roads Rehabilitation

The project will reconstruct approximately a combined total of 10 kilometres of contiguous roads on reserve including improvements or relocation of the entrance to Highway 527. The work includes resurfacing and grading, widening of roadway sections, brush clearing, ditching, sightline improvements, regulatory and warning signs, installation of approximately 43 culverts and drainage modifications.


Latest update

Notice of Determination

2021-06-26 - Infrastructure Canada, Indigenous Services Canada, and Fisheries and Oceans Canada have issued their Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
3 Notice of Determination - Gull Bay Roads Rehabilitation Project - July 15, 2021
2 Gull Bay Roads Rehabilitation Project - May 26, 2021

Contacts

Aboriginal Consultation and Environmental Services
1100 - 180 Kent St
Ottawa, Ontario K1P 0B6
Email: infc.aboriginalconsultenv-consultautochtonesenv.infc@canada.ca


  • Location

    • Neebing (Ontario)
  • Nature of Activity

    • Highways and Roads
  • Assessment Status

    Completed
  • Start Date

    2020-05-29
  • Proponent

    Gull Bay First Nation
  • Authorities

    • Fisheries and Oceans Canada
    • Indigenous Services Canada
    • Infrastructure Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    80744
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

Nearby assessments

...within 200 kilometres
Date modified: