Fond Du Lac Environmental Remediation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
An environmental consultant has identified ten plumes of petroleum hydrocarbon impacts on seven sites in the community of Fond du Lac. Impacts in soil and groundwater exceed calculated site specific guidelines that use a scientific approach to evaluate against human and ecological risk. The consultant has proposed to carry out a remedial action plan which includes partially excavating and landfarming impacts where possible and using anaerobic bioremediation to treat the rest of the impacts in place. Excavation and landfarming will account for approx. 5000m3 of impacts and will utilize the formerly established landfarm area north of the community. Anaerobic bioremediation will account for approx. 19,000m3 and will use fertilizer amendment applied within and upstream of impacts. Permeable reactive barriers containing carbon sources will be placed downstream to protect the lake and other receptors from nutrients in the amendments. The estimated timeline to achieve remedial objectives is 5 field seasons, with completion in fall of 2025.
Remedial Action Plan for approx. 25,000m3 of petroleum hydrocarbon contaminated soils/groundwater
- Remedial Excavation: excavate impacted soils using local equipment, haul to landfarm, replace with clean backfill and clean overburden. Excavations occur where impacts are accessible considering subsurface conditions, structures/buildings, and underground utilities. Backfill from local source. Clean overburden will be temporarily stockpiled and returned to the upper layers of excavated area.
- Anaerobic Bioremediation: treat soils that can't be reached/accessed through excavation. Nutrient amendment will be installed in trenches or surficially to promote anaerobic bioremediation of impacts.
- Permeable Reactive Barrier: PRB will be installed downstream of any plumes adjacent to a waterbody (Lake Athabasca, Meech Lake). PRB will consist of a carbon source that will biodegrade the applied nutrients.
- Monitoring and sampling: Groundwater across community will be monitored and sampled twice per year to observe trends. Locations where soil impacts have been observed will be resampled once it is believed remediation has reached its target concentration. Extents of excavations will be sampled to determined if further excavation or treatment is required in each direction.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination for Fond Du Lac Environmental Remediation | - | March 5, 2021 |
1 | Public Comment Period on Intent to Make a Determination | - | February 1, 2021 |
Contacts
ISC-SKENVIndigenous Services Canada
1827 Albert Street
Regina, Saskatchewan S4P 2S9
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
-
Location
- Fond du Lac IR 227 (Saskatchewan)
-
Nature of Activity
- Remediation and conservation
- Soil management
-
Assessment Status
Completed -
Start Date
2021-06-01 -
Proponent
Fond du Lac Denesuline Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
81341
Nearby assessments
...within 200 kilometres-
Fond du Lac First Nation Water Treatment Plant Expansion
Fond du Lac IR 227 -
Sand and Gravel Permit - Fond du Lac Airport Resurfacing project
Fond du Lac IR #227 -
Highway 905 - All Weather Roadway - Stony Rapids to Lake Athabasca near Fond-du-Lac
-
Pelican Lake First Nation Gas Bar Upgrade
Chitek Lake IR 191 -
Highway 905 - All Weather Roadway - Stony Rapids to Lake Athabasca near Fond-du-Lac
Stony Rapids -
Elizabeth Falls Hydroelectric Project
Chicken Indian Reserve No. 224 -
Former Gunnar Mine Site Rehabilitation Project
Gunnar