Rose Inlet Helicopter Landing Pad Replacement
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Canadian Coast Guard, in consultation with Gwaii Haanas National Park Reserve, National Marine Conservation Area Reserve, and Haida Heritage Site (Gwaii Haanas) propose to build a new the helicopter landing pad at the Rose Inlet Marine Communications Mountaintop Site. The Canadian Coast Guard and Gwaii Haanas have been notified of issues with icing of the existing timber helipad leading to potentially unsafe landing/take-off conditions. In addition to this, the proposed helipad will be located further away from the communications tower to improve landing conditions at site. Building the new helicopter landing pad will improve safety for Canadian Coast Guard and Gwaii Haanas personnel accessing the Rose Inlet mountaintop site. Work for the Rose Inlet Helipad replacement project has been separated into two separate phases.
Phase I - Rose Inlet Location Site Preparation and Concrete Footings:
The new 6.0m x 6.0m helicopter pad on concrete columns footings would be built next to the existing helipad. The equipment for this phase would be helicopter long line slung up to site and would consist of handheld power tools and vegetation clearing tools, small diesel powered generator, mini excavator, concrete mixer, cast in place concrete, wood for formwork, health and safety gear and spill response materials. The mini excavator would be delivered via Canadian Coast Guard Sea Truck to Harriet Bay where the excavator would be offloaded onto a manmade rocky outcrop where the helicopter can pick it up and sling it directly to Rose Inlet Marine Communications Mountaintop Site. The area for the footings will be excavated. The rest of the equipment will be slung to site and the activities described in Phase I will occur once the barge arrives in Huston Inlet with the remaining supplies. Activities related to this phase will include helicopter long line slinging, vegetation brushing, excavating soil and gravels (to be contained on site) within the concrete footing locations, rock drilling, formwork, concrete mixing and pouring of helipad footings in the formwork. This equipment would then be slung off site and back to the staging at Huston Inlet. This portion will be carried out by Coast Guard employees. It is anticipated the slinging activities will occur over 4 days with approximately 40 sling loads coming off the barge.
Phase II – Rose inlet Location Helipad Platform Installation:
This phase includes slinging up the new pad components, gravel fill, concrete, handheld power tools and assembling the new pad. The new pad will be a concrete suspended slab, essentially creating a raised gravel pad. It will be assembled on site. This portion would be completed by Coast Guard Employees. Depending on the amount of equipment to be taken off site, and if any equipment was slung back to the staging area from the Phase I portion, helicopter slinging could be used to bring equipment back to the barge. This portion of the project is still under development. Phase II will require approximately 80 sling loads. The existing helipad will be decommissioned and will be removed site. Gravel will be used to level portions of the footprint of the old helipad.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Contacts
Steven ColeMarine Civil Infrastructure
Steven Cole, Project Engineer
Victoria Coast Guard Base 25 Huron Street
Victoria, British Columbia V8V 4V9
Telephone: 250-413-2835
Email: steven.cole@dfo-mpo.gc.ca
-
Location
- Harriet Harbour shore landing excavator drop off Skincuttle Inlet is located on the southeastern end of Moresby Island off of Skincuttle Inlet (British Columbia)
- Huston Inlet is located on the southeastern end of Moresby Island off of Skincuttle Inlet, Gwaii Haanas National Marine Conservation Area Reserve and Haida Heritage Site. (British Columbia)
- Rose Inlet Mountaintop Communications Site is located on southern Moresby Island in Gwaii Haanas National Park Reserve and Haida Heritage Site. (British Columbia)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
Completed -
Start Date
2022-04-19 -
Proponent
Canadian Coast Guard -
Authorities
- Fisheries and Oceans Canada
- Parks Canada Agency
-
Assessment Type
Project on federal lands -
Reference Number
83475
Nearby assessments
...within 200 kilometres-
Rose Inlet Helicopter Landing Pad Replacement and Jedway Barge Helicopter Slinging Operation
Rose Inlet Haida Gwaii -
Haida Gwaii Aids to Navigation Rebuild and Helipad Construction
Scudder Point -
Replacement of Roofing on Operations Station (Ellen Island) and Watchmen Cabin (Hotspring Island)
Gwaii Haanas National Park Reserve, National Marine Conservation Area Reserve, and Haida Heritage Site (Ellen Island) -
Haida Gwaii Aids to Navigation Rebuild and Helipad Construction
Flatrock Island -
The Living Landscapes of SGang Gwaay: strengthening the land and people in a changing climate
Gwaii Haanas National Park Reserve and Haida Heritage Site -
Haida Gwaii Aids to Navigation Rebuild and Helipad Construction
Gowgaia Point -
Replacement of Roofing on Operations Station (Ellen Island) and Watchmen Cabin (Hotspring Island)
Gwaii Haanas National Park Reserve, National Marine Conservation Area Reserve, and Haida Heritage Site (Hotspring Island) -
Parks Canada, Modification to Existing Radiocommunications Tower at Fisheries and Oceans Canada Property 33411, Moresby Island, BC
Parks Canada Fisheries and Oceans Canada Property 33411, Moresby Island, BC -
Nav Canada, Antenna Addition to Radiocommunications Tower on Transport Canada Property Number 19393, Sandspit, BC
Transport Canada Property Number 19393, Sandspit, BC -
Skidegate Watermain Extension for Wastewater Treatment Plant
Skidegate -
Gitga'at Hartley Bay Boardwalk Repair
Hartley Bay -
Canadian Coast Guard Mount Gil Radio Site Upgrade and Radar Installation
Mount Gil, Gil Island -
New Fibre Installation
Dolphin Island -
Mitigation of Risks to Hartley Bay Water Supply Project
Mitigation of Risks to Hartley Bay Water Supply Project -
Canadian Coast Guard Hartley Bay Search and Rescue Residence
Hartley Bay -
Canadian Coast Guard Hartley Bay Search and Rescue Float
Hartley Bay -
New Fibre Installation
Kulkayu 4 -
Gitga'at FNWMS Sewage Treatment & Disposal Upgrade
Hartley Bay -
Gitga'at Hartley Bay Lift Station Repair
Hartley Bay -
All Spirits Gitga'at
Hartley Bay -
Canadian Coast Guard Klemtu Mountain Marine Control Traffic Services Site Upgrade
Klemtu Mountain -
Electrical Utility Upgrades
Kitasoo Xai'Xais Reserve Lands -
Connected Coast Network on Federal Lands - Oona River to Port Hardy
Boat Bluff CCG Lightstation (and 8 other sites) -
Ivory Island Lightstation - Septic System Replacement
Ivory Island Lightstation -
Ivory Island Lightstation Renewable Power Generation System
Ivory Island Lightstation -
Beverage Antenna Boardwalk - Canadian Forces Station (CFS) Leitrim
Masset