Rocky Creek Metallurgical Coal Project

CTI Plus Resources Ltd. is proposing to construct and operate an open-pit metallurgical coal mine located about 47 kilometres southwest of Chetwynd, British Columbia. As proposed, the Rocky Creek Metallurgical Coal Project would produce up to 3.77 million tonnes of coal per year, over a mine life of 18 years. Once mined, the coal would be transported by rail to the west coast of British Columbia for shipment overseas.

 


Latest update

January 16, 2025 — The Impact Assessment Agency of Canada and British Columbia’s Environmental Assessment Office issued the Joint Summary of Issues and Engagement to the proponent on December 23, 2024, for the preparation of the proponent’s response to the Summary of Issues and Detailed Project Description, if required.

At a glance

Planning

Time limit suspension

The time limit for the impact assessment process was suspended on December 23, 2024 at the request of the proponent and the number of days will not advance.

Planning

Suspended 123/180 days

Key documents

Comment periods

Impact Statement

Impact Statement

Not started 0/1095 days
Impact Assessment

Impact Assessment

Not started 0/300 days
Decision Making

Decision Making

Not started 0/30 days
Post Decision

Post Decision phase is an ongoing process

If approved, the project may proceed to construction as federal authorizations and permits are issued, and as conditions and other requirements are met.

Post Decision

Not started

Participate

Contacts

Media Relations
Impact Assessment Agency of Canada
160 Elgin Street, 22nd Floor
Ottawa, Ontario K1A 0H3
Email: media@iaac-aeic.gc.ca

Rocky Creek Metallurgical Coal Project
Impact Assessment Agency of Canada
1800–1138 Melville Street
Vancouver, British Columbia V6E 4S3
Telephone: 604-666-2431
Email: rockycreek@iaac-aeic.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Chetwynd (British Columbia)
  • Nature of Activity

    • Mines and Minerals
  • Assessment Status

    Suspended
  • Start Date

    2024-09-05
  • Proponent

    CTI Plus Resources Ltd.
  • Authorities

    • Impact Assessment Agency of Canada
  • Assessment Type

    Planning Phase for Impact Assessment
  • Reference Number

    88867

Nearby assessments

...within 200 kilometres
Date modified: