Pacific Salmon Strategy Initiative (PSSI): Upper Fraser River Salmon Conservation Hatchery

The construction of a new salmon enhancement facility in the Upper Fraser watershed is a core initiative  of the Pacific Salmon Strategy Initiative (PSSI) which aims to fill a critical infrastructure gap in the region to address conservation and rebuilding priorities for Chinook and Sockeye salmon. The Lheidli T'enneh First Nation is collaborating with DFO on the proposed project and support has continued throughout its development. DFO has engaged with the City of Prince George to accommodate applicable bylaws and permitting requirements, including protection of the riparian zone surrounding the Nechako River. Throughout the construction of the project, a qualified environmental monitor and archaeological monitor will be on site as required to assess potential risks to the environment and monitor the effectiveness of mitigation measures to be implemented across the various phases of the project. 

The total project footprint is approximately 2.15 hectares and is expected to be completed over 3 phases:

Phase 1: Site preparation, Earthworks, and Utilities

Includes site vegetation clearing and stripping of overburden material within the development area to establish a suitable grade and foundation for the next phase. Approximately 0.8 hectares within the project area will be cleared of vegetation, followed by the removal of 5,300 m3 overburden material. Some material will be stockpiled onsite while the remaining material will be disposed of at an appropriate facility. Approximately 30,000 m3 of engineered fill material will be transported on location to support site grading, fill and compaction activities, as well as to elevate the site footprint to meet the City of Prince George Flood Plain Regulation. The site will be graded to achieve temporary construction access, site road/pathways and site drainage. Planned building areas will be prepared for installation of building slabs, footings and/or foundations. Underground utility services, including water supply lines, domestic and fire protection waterlines, and sanitary and storm water piping, and electrical conduits, will be installed via trenching activities.

Phase 2: Facility Construction

Commencement of concrete works for building foundations and hatchery infrastructure, above-ground installation of utility services, and underground building utility service tie-ins will take place. Hatchery infrastructure to include building of a staff residence and office, workshop, storage facilities, two indoor hatchery modules, an aeration tower, head tanks, and a series of holding tubs. Other infrastructure requirements will include water delivery and sanitation systems, a backup power generator and effluent channel.

Phase 3: Finishing Works & Commissioning

Anticipated to complete culvert installation, grading of roads, pathways and sidewalks, and the installation of curbs and pathways. Landscaping elements will include planting of trees and vegetation. A fence and gate will be installed surrounding the hatchery facility. Signage and other finishing items will be installed throughout the hatchery facility. Finally, the site will undergo the commissioning phase where final utility connections and systems will be tested and building infrastructure will undergo furnishing.

More


Latest update

December 9, 2024 – The Department of Fisheries and Oceans Canada has issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Contacts

PSSI Projects
Real Property and Environmental Management - Technical Services Team
200 - 401 Burrard Street
Vancouver, British Columbia V6C 3S4
Email: DFO.PSSI.Projects@dfo-mpo.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Prince George (British Columbia)
  • Nature of Activity

    • Aquaculture (aquafarming)
    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2024-09-19
  • Proponent

    Fisheries and Oceans Canada - Real Property, Safety and Security
  • Authorities

    • Fisheries and Oceans Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    88909

Nearby assessments

...within 200 kilometres
Date modified: