L150 Anchor Inspection and Repair
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
NTPC is currently planning an anchor degradation study for L150 transmission line. The initial inspection phase of the project will be conducted outside of the migratory bird nesting period from late July to the end of August, 2023. Excavation work will take place during the fall months. The L-150 is a 115 kV transmission line that forms the South Slave Power Grid, it comprises of approximately 800 Guyed-Y aluminum transmission towers. The length of the transmission line spans 285 km and is strung with single 3/0 ACSR Pigeon conductor. The tower line was constructed in the 1960s and is currently experiencing widespread issues with its anchors. The anchors are fastened to the ground with anchor rods that are buried 2-3m below ground surface (bgs). Additional geotechnical information is required to complete Engineering of the anchor solution, and ground level assessments of all the anchor structures is required to prioritize structure rehabilitation. A drilling program is planned to take place starting September 2023 between Fort Smith and Pine Point. A desktop study will be carried out in August to determine the location of the boreholes (estimating 20-30 boreholes within the Park). Based on the results of the borehole logs, recommendations will be made for 8 excavations at Towers along the distribution line to extract the anchors for corrosion assessment. Extracted anchors will be sent for testing, and new anchors will be installed in their place. Excavation depths are expected to be 8-10 feet, and carried out using small tracked excavator. NTPC is planning to investigate the anchors and identify the main cause(s) of anchor degradation along the Transmission Line (Corrosion, End of Life, etc.) and the extent of the degradation during the summer of 2023. Anchors deemed to be in unsuitable condition throughout the SSES system will be dug up using an excavator (bobcat style equipment with rubber tracks to minimize ground disturbance). Anchors removed will be replaced. Minor travel and transportation of equipment between spans will occur. Repairs and upgrades may be undertaken as necessary. The scope of work involves shallow subsurface excavation (0.6 m bgs) as well as deep subsurface excavation (2-3 m) to determine extent of surface & subsurface corrosion, for one anchor at several tower sites. Exact dates and locations will be submitted in project information updates. July 7, 2022 A detailed sediment and erosion control plan will be delivered prior to work commencement.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
1 | New project being assessed by Parks Canada - Public comments invited from January 25 to February 24, 2023 | - | January 25, 2023 |
Contacts
Wood Buffalo National Park149 McDougal Rd
Box 750
Fort Smith, Northwest Territories X0E 0P0
Telephone: 867-872-7960
Email: rescon-ftsmith@pc.gc.ca
-
Location
- Wood Buffalo National Park of Canada (Northwest Territories)
-
Nature of Activity
- Maintenance activities (fences, walls)
-
Assessment Status
In progress -
Start Date
2023-01-25 -
Proponent
Northwest Territories Power Corp -
Authorities
- Parks Canada Agency
-
Assessment Type
Project on federal lands -
Reference Number
84265
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Smith's Landing First Nation Phase 1A Housing Development (Part 2)
Smiths Landing First Nation -
Smith's Landing First Nation Phase 1(a) Housing Development
Smiths Landing First Nation -
NTPC L-150 Anchor Inspection and Rehabilitation Project, Highway 5
Wood Buffalo National Park of Canada -
New Fibre Installation
Project site 1: Thabacha Náre 196A & Thebathi 196 -
Hay Camp Road (km 20) Culvert Replacement, Wood Buffalo National Park
Wood Buffalo National Park -
Culvert Replacement and Repair at km 41 Hay Camp Road
Wood Buffalo National Park of Canada -
Berry Plant Clearing in Pine Lake Campground, Wood Buffalo National Park
Wood Buffalo National Park -
Wood Buffalo National Park Highway Asphalt Surface Treatment
Wood Buffalo National Park -
Sandhills Substation Generator Upgrade
Wood Buffalo National Park of Canada -
Sass River / Prebble Creek Embankment Repair and Gabion Installation by the Government of the Northwest Territories
Wood Buffalo National Park of Canada -
Mikisew Peace Point Power Plant Solar Addition
Mikisew Cree First Nation -
Peace Point Water Survey of Canada Hydrometric Station Shelter Replacement, Wood Buffalo National Park
Wood Buffalo National Park -
Culvert Replacement Along Carlson's Road km 136.1 Wood Buffalo National Park (Alberta)
Wood Buffalo National Park -
Winter Road creation, maintenance, and breakdown
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Establish Water Survey of Canada river depth station on north branch of Quatre Fourches
Wood Buffalo National Park -
Peace-Athabasca Delta Field Station
Detailed Impact Assessment, Wood Buffalo National Park -
Dog Camp Water Control Structure
Wood Buffalo National Park of Canada -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Re-establish Former Water Level and Flow monitoring stations at four sites within the Peace Athabasca Delta of Wood Buffalo National Park
Wood Buffalo National Park -
Big Egg Lake Water Control Structure
Athabasca Chipewyan First Nation Jackfish Reserve (I.R. 201) -
Former Gunnar Mine Site Rehabilitation Project
Gunnar