Winter Road Bridge Crossing Construction on Nibinamik First Nation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Proposed Project
Nibinamik First Nation is proposing the installation of a pre-purchased bridge at winter road Crossing #1, approximately 1.7 km south of the community. This project would improve early access to opening and construction of the winter road since it is the first water crossing. This crossing has proven difficult to maintain as small culverts and fill were used in its initial construction. Overland flooding occurs regularly as the creek exceeds the culvert capacity. Installing a portable bridge would alleviate these challenges and extend the winter road season.
Latest update
Winter Road Bridge Crossing Construction on Nibinamik First Nation – Public Comments Invited
January 28, 2026 – Indigenous Services Canada must determine whether the proposed Winter Road Bridge Crossing Construction on Nibinamik First Nation, located in Nibinamik First Nation is likely to cause significant adverse environmental effects. To help inform this determination, Indigenous Services Canada is inviting comments from the public respecting that determination.
Written comments must be submitted by February 26, 2026 to:
Hannah Silvaggio
101-100 Anemki Place
Fort William First Nation, ON P7J 1A5
hannah.silvaggio@sac-isc.gc.ca.
Participate
Contacts
Indigenous Services CanadaHannah Silvaggio, Environment Officer
100 Anemki Place, Suite 101
Fort William First Nation, Ontario P7J 1A5
Telephone: 807-624-5921
Email: hannah.silvaggio@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Nibinamik First Nation (Ontario)
-
Nature of Activity
- Bridges
-
Assessment Status
In progress -
Start Date
2026-01-28 -
Proponent
Nibinamik First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
90188
Nearby assessments
...within 200 kilometres-
New Fibre Installation
Project Site 5 -
Wunnumin H1RCI Compound Construction
Wunnumin Lake -
New Fibre Installation / Upgrade Multiple Towers
Sandy Lake PoP -
Wunnumin Lake First Nation Teacherages Project
Wunnumin Lake First Nation -
New Fibre Installation
Project Site 4 -
New Fibre Installation / Upgrade Multiple Towers
Slate Falls PoP -
New Fibre Installation / Upgrade Multiple Towers
Bearskin Lake PoP -
Neskantaga First Nation New Construction of an 8-plex teachers residence
Neskantaga First Nation -
Neskantaga Community Recreation Centre
Neskantaga First Nation Reserve -
New Fibre Installation / Upgrade Multiple Towers
Poplar Hill PoP -
Webequie Supply Road Project
Webequie First Nation - Western limit -
Construction of Four Modular Teacherages on Webequie First Nation
Webequie First Nation -
Webequie First Nation - Nursing Station Bulk Fuel Storage Upgrades
Webequie First Nation -
Kasabonika Lake New 7 - 12 school
Kasabonika Lake First Nation -
Kasabonika Lake First Nation Band Representative Facility
Kasabonika Lake First Nation -
Kasabonika Lake First Nation - Nursing Station Fuel System Upgrade
Kasabonika Lake First Nation -
New Fibre Installation / Upgrade Multiple Towers
Pikangikum Fibre Cabinet -
New Fibre Installation / Upgrade Multiple Towers
Cat Lake PoP -
New Fibre Installation / Upgrade Multiple Towers
Wawakepewin PoP -
Kingfisher Lake First Nation K4-10 School
Kingfisher Lake First Nation/Reserve No. 1 -
Kingfisher Lake First Nation Subdivision Phase 2
Kingfisher Lake First Nation -
Replacement of Bridge for Winter Road Crossing - Eabametoong First Nation
Eabametoong First Nation -
Kinonjeoshtegon - CHRT 41 - CFS CENTER AND ASSOCIATED BUIDLINGS - P048401 - 2425
Kitechuhmaykoosib Inninuwug First Nation -
Development of 10 Lot Residential Subdivision on Eabametoong First Nation
Eabametoong First Nation -
East End Subdivision Development - Eabametoong First Nation
Eabametoong First Nation -
New Fibre Installation / Upgrade Multiple Towers
Pikangikum PoP -
Wapekeka Office Building Construction Project
Wapekeka First Nation -
Wapekeka First Nation Bulk Fuel Storage Upgrades Project
Wapekeka First Nation -
Wapekeka First Nation New School Project
Wapekeka First Nation -
Eagle's Nest Project
Ring of Fire -
Webequie Supply Road Project
McFaulds Lake area - Eastern limit -
Eagle's Nest Mine Project
Ring of Fire -
Northern Road Link Project
McFaulds Lake area - Northern Limit -
Regional Assessment in the Ring of Fire Area
Ring of Fire -
Kitchenuhmaykoosib Inninuwug Wastewater System Upgrades & Expansion
Kitchenuhmaykoosib Inninuwug First Nation -
Cliffs Chromite Project
McFaulds Lake -
Kinonjeoshtegon - CHRT 41 - CFS CENTER AND ASSOCIATED BUIDLINGS - P048401 - 2425
Kitechuhmaykoosib Inninuwug First Nation - Main site -
Northern Road Link Project
150km north of the Municipality of Greenstone -
North Caribou Lake First Nation - Lot Servicing for Housing Development
North Caribou Lake First Nation -
North Caribou Lake First Nation - Backup Power Decommissioning Project
North Caribou Lake First Nation -
North Caribou Lake First Nation School
North Caribou Lake First Nation -
North Caribou Lake First Nation - Teacherages Project
North Caribou Lake -
North Caribou Lake First Nation - Immediate Housing - Lot Servicing
North Caribou Lake First Nation - Weagamow Lake -
New Fibre Installation / Upgrade Multiple Towers
Sachigo Lake PoP -
North Caribou Lake First Nation Water Treatment System Upgrades
North Caribou Lake First Nation