Construction of Four Modular Teacherages on Webequie First Nation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Proposed Project
Webequie First Nation is proposing the installation of 4 modular teacherages (78 sq.m each) to replace 3 existing teacherages that are in poor condition and add 1 additional teacherage. Activities are as follows:
- The demolition of the existing teacherages;
- Site preparation for the modular units to be delivered via winter road to be placed on permanent foundations;
- Leveling and compaction by heavy equipment with aggregate (source 13 km from community) prior to screw pile install;
- New water and sewer connections (1 per site) and electrical connections (unknown if new pole and transformer is required);
- Installation of 4 new fuel day tanks for heating;
- Designated substances surveys to be completed by a professional for existing teacherages and provide disposal plan of demolished teacherages, if required;
- Landscaping for vehicle access and positive drainage grading.
This project will help with teacher retention by improving the living conditions of resident teachers teaching at the community's school, Simon Jacob Memorial Education Centre.
Latest update
Construction of Four Modular Teacherages on Webequie First Nation – Public Comments Invited
April 9, 2026 – Indigenous Services Canada must determine whether the proposed Construction of Four Modular Teacherages on Webequie First Nation, located in Webequie First Nation is likely to cause significant adverse environmental effects. To help inform this determination, Indigenous Services Canada is inviting comments from the public respecting that determination.
Written comments must be submitted by May 10, 2026 to:
Hannah Silvaggio
101-100 Anemki Place
Fort William First Nation, ON P7J 1A5
hannah.silvaggio@sac-isc.gc.ca.
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | April 9, 2026 |
Contacts
Indigenous Services CanadaHannah Silvaggio, Environment Officer
100 Anemki Place, Suite 101
Fort William First Nation, Ontario P7J 1A5
Telephone: 807-624-5921
Email: hannah.silvaggio@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Webequie First Nation (Ontario)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
In progress -
Start Date
2026-04-09 -
Proponent
Webequie First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
90353
Nearby assessments
...within 200 kilometres-
Webequie First Nation - Nursing Station Bulk Fuel Storage Upgrades
Webequie First Nation -
Webequie Supply Road Project
Webequie First Nation - Western limit -
Webequie Supply Road Project
McFaulds Lake area - Eastern limit -
Eagle's Nest Project
Ring of Fire -
New Fibre Installation / Upgrade Multiple Towers
Bearskin Lake PoP -
New Fibre Installation / Upgrade Multiple Towers
Slate Falls PoP -
Eagle's Nest Mine Project
Ring of Fire -
Northern Road Link Project
McFaulds Lake area - Northern Limit -
Cliffs Chromite Project
McFaulds Lake -
Winter Road Bridge Crossing Construction on Nibinamik First Nation
Nibinamik First Nation -
Regional Assessment in the Ring of Fire Area
Ring of Fire -
Neskantaga First Nation New Construction of an 8-plex teachers residence
Neskantaga First Nation -
Neskantaga Community Recreation Centre
Neskantaga First Nation Reserve -
Kasabonika Lake First Nation Band Representative Facility
Kasabonika Lake First Nation -
Kasabonika Lake First Nation - Nursing Station Fuel System Upgrade
Kasabonika Lake First Nation -
Kasabonika Lake New 7 - 12 school
Kasabonika Lake First Nation -
New Fibre Installation
Project Site 5 -
New Fibre Installation / Upgrade Multiple Towers
Poplar Hill PoP -
New Fibre Installation / Upgrade Multiple Towers
Pikangikum Fibre Cabinet -
New Fibre Installation / Upgrade Multiple Towers
Sandy Lake PoP -
Wunnumin H1RCI Compound Construction
Wunnumin Lake -
New Fibre Installation
Project Site 4 -
Wunnumin Lake First Nation Teacherages Project
Wunnumin Lake First Nation -
Replacement of Bridge for Winter Road Crossing - Eabametoong First Nation
Eabametoong First Nation -
East End Subdivision Development - Eabametoong First Nation
Eabametoong First Nation -
Development of 10 Lot Residential Subdivision on Eabametoong First Nation
Eabametoong First Nation -
Northern Road Link Project
150km north of the Municipality of Greenstone -
New Fibre Installation / Upgrade Multiple Towers
Cat Lake PoP -
New Fibre Installation / Upgrade Multiple Towers
Wawakepewin PoP -
Kingfisher Lake First Nation K4-10 School
Kingfisher Lake First Nation/Reserve No. 1 -
Kingfisher Lake First Nation Subdivision Phase 2
Kingfisher Lake First Nation -
New Fibre Installation / Upgrade Multiple Towers
Pikangikum PoP -
Wapekeka Office Building Construction Project
Wapekeka First Nation -
Wapekeka First Nation Bulk Fuel Storage Upgrades Project
Wapekeka First Nation -
Wapekeka First Nation New School Project
Wapekeka First Nation -
Kinonjeoshtegon - CHRT 41 - CFS CENTER AND ASSOCIATED BUIDLINGS - P048401 - 2425
Kitechuhmaykoosib Inninuwug First Nation -
Marten Falls Community Access Road Project
Marten Falls -
Electrical Distribution System Upgrades - Marten Falls First Nation
Marten Falls First Nation -
Kitchenuhmaykoosib Inninuwug Wastewater System Upgrades & Expansion
Kitchenuhmaykoosib Inninuwug First Nation -
Kinonjeoshtegon - CHRT 41 - CFS CENTER AND ASSOCIATED BUIDLINGS - P048401 - 2425
Kitechuhmaykoosib Inninuwug First Nation - Main site