Improving the reliability of Obedjiwan's stand-alone power grid by adding the equipment and infrastructure needed to integrate renewable energy from the future forest biomass power plant.

The project involves integrating a new renewable energy source from the 4.8 MW forest biomass power plant. In Order to do so, Hydro-Québec must build a new sectioning post and a control building, as well as a new access road, in addition to extending the distribution lines to the new facilities and converting the network voltage from 4.8 MW to 25 kV.


Latest update

Natural Resources Canada is inviting comments from the public on the proposed Improving the reliability of Obedjiwan's stand-alone power grid by adding the equipment and infrastructure needed to integrate renewable energy from the future forest biomass power plant project to help inform its determination under Section 82 of the Impact Assessment Act..

Participate

Key documents

Key documents
Document number Document title File Date
1 Notice of Intent to Make a Determination—Start of Public Comment Period - February 27, 2026

Contacts

Natural Resources Canada
Geneviève Poitras, Impact Assessment Officer
580 Booth street
Ottawa, Ontario K1A 0E8
Email: genevieve.poitras@nrcan-rncan.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Obedjiwan (Quebec)
  • Nature of Activity

    • Alternative Energy
  • Assessment Status

    In progress
  • Start Date

    2026-02-27
  • Proponent

    Hydro-Québec
  • Authorities

    • Natural Resources Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    90268