Modification of Hydro-Québec facilities, including the construction of a new sectioning post to optimize and integrate energy produced by a forest biomass cogeneration plant in Opitciwan

Project summary: The project involves modifying Hydro-Québec (HQ) facilities in Opitciwan's stand-alone power system to optimize and integrate energy produced by a new 4.8 MW forest biomass cogeneration plant owned by a third party. To enable this integration, HQ must modify and modernize its facilities to increase its capacity to manage more renewable energy. The project includes:

- Clearing 41,600 square meters of forest for the new sectioning post, its access road, and connection lines;
- Construction of a new sectioning post including a building (control/garage), a transit house with septic system, and installation of a 4 MW energy storage system (ESS);
- Modification of an existing road and addition of a new section of road to access the new sectioning post;
- Construction of a new 1.5 m culvert in the new section of road;
- Installation of distribution lines connecting the new sectioning post and the forest biomass cogeneration plant to the existing HQ network;
- Adaptation of existing automation systems to integrate energy produced from biomass;
- Replacement of equipment at the existing thermal power plant to ensure compatibility with the use of an ESS;
- Addition of three oil recovery basins and a prefabricated oil separator well to the existing plant;
- Addition of telecommunications architecture to each facility.


Latest update

[September 15, 2025] – Housing, Infrastructure and Communities Canada and Indigenous Services Canada have issued their Notice of Determination and have determined that the Project is not likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document number Document title File Date
2 Notice of Determination- Housing, Infrastructure and Communities Canada and Indigenous Services Canada - September 15, 2025

Contacts

Environmental Advisor (Qc)
320 St. Joseph St E Q
Québec, Quebec G1K 9J2
Email: qcevalenvenvassessqc@sac-isc.gc.ca


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

  • Location

    • Opitciwan (Quebec)
  • Nature of Activity

    • Building and Property Development
    • Highways and Roads
  • Assessment Status

    Completed
  • Start Date

    2025-07-18
  • Proponent

    Hydro Québec
  • Authorities

    • Indigenous Services Canada
    • Infrastructure Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    89742

Nearby assessments