Sucker Creek Housing Project 2020 (4 Units)
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Rural residential Housing. Supply and install 1400 sq ft prefabricated modular home with Poured concrete foundation piling system. Site servicing comprised of 1500 gal precast concrete water cistern, 2000 gal precast concrete sewage holding tank, 3 phase power, natural gas and driveway.
Rubber tired backhoe, Skidsteer, John Deere 200 Trackhoe, and D5 Cat Crawler Tractor to be used for excavation, driveway construction, backfill and landscaping.
Rural residential Housing. Supply and install 1220 sq ft stickbuilt bi-level house with ICF Poured concrete foundation walls. Site servicing comprised of 1500 gal precast concrete water cistern, 2000 gal precast concrete sewage holding tank, 3 phase power, natural gas and driveway.
Rubber tired backhoe, Skidsteer, John Deere 200 Trackhoe, and D5 Cat Crawler Tractor to be used for excavation, driveway construction, backfill and landscaping.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination for the Sucker Creek Housing Project 2020 (4 Units) | - | December 11, 2020 |
1 | Public Comment Period on Intent to Make a Determination | - | October 26, 2020 |
Contacts
Indigenous Services CanadaStacey LeBlanc, Sr. Environment Officer
630 Canada Place, 9700 Jasper Ave
Edmonton, Alberta T5J 4G2
Telephone: 780-782-8350
Email: stacey.leblanc@canada.ca
-
Location
- Sucker Creek First Nation (Alberta)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
Completed -
Start Date
2020-10-26 -
Proponent
Sucker Creek First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
81100
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Upgrade (Multiple) Tower
Project Site 2: Sucker Creek FN 150A -
Sucker Creek First Nation Water System Upgrades
Sucker Creek First Nation -
2024-3899-00 Sucker Creek Bridge Assessment
Sucker Creek First Nation -
Three Unit Modular Housing Project
Sucker Creek First Nation -
Joussard Harbour Alberta - Routine Maintenance Dredging of the Joussard Harbour at Lesser Slave Lake Alberta - over the next year
Joussard Harbour -
Kapawe'no First Nation Echo Prairie Waterline Project
Kapawe'no First Nation -
Upgrade (Multiple) Tower
Project Site 1: Kapawe'no FN 150B -
Kapawe'no Adventure Trail Project
Kapawe'no Adventure Trail Project -
Driftpile Cree Nation New Housing Construction Project
Driftpile, AB -
Driftpile Cree Nation Housing Project
Driftpile Cree Nation -
Driftpile Cree Nation Lift Station No. 1 Replacement Project
Driftpile Cree Nation -
Driftpile Cree Nation antenna supporting structure located on the Driftpile Cree Nation in the Municipal District of Big Lakes.
Driftpile Cree Nation antenna supporting structure -
Driftpile Cree Nation Gas Line Connector Project
Driftpile Cree Nation -
DCN 2023 Rapid Housing Project
DCN 2023 Rapid Housing Project -
Driftpile Cree Nation Lagoon Reclamation
Driftpile Cree Nation -
Swan River First Nation Lakefront Development Project
Lesser Slave Lake -
Swan River First Nation: Wastewater Lagoon Liner Repair & Sub-liner Drainage Installation
Swan River First Nation -
Swan River 32 Lot West Subdivision Project
Swan River First Nation -
Swan River First Nation Waste Diversion and Recycling Facility
Swan River First Nation -
Swan River First Nation Housing Project 2019 (5-Units)
Swan River First Nation -
New Fibre Installation
Swan River 150E -
Whitefish Lake Fire Guard Project
Whitefish Lake First Nation 155 -
Atikameg Healing Shelter for Women and Children
Whitefish Lake First Nation -
New Fibre Installation - Slave Lake
Project Site 2: Slave Lake -
Smoky River Wind Project
Municipal District of Smoky River, between Nampa and Falher -
New Fibre Installation - Slave Lake
Project Site 1: Slave Lake -
Upgrade (multiple) towers
Sturgeon Lake No.154A (Sturgeon Lake Cree Nation) - Site 7 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 5 -
Sawridge Band Solar Farm Project
Sawridge Band -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 4 -
Sturgeon Lake Cree Nation Child and Family Services Modular Office Complex
Sturgeon Lake Cree Nation -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 2 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 1 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 6 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 3 -
Black Bear Power Plant Project
Swan Hills -
New Fibre Installation
Project Site 1: Little Buffalo -
Wolverine River Lateral Loop (Carmon Creek Section)
Carmon Lake -
Woodland Cree CMHC Co-Investment Housing Project - Marten Lake Subdivision (10-Units)
Cadotte Lake -
OS-7244 Woodland Cree 226
Woodland Cree 226 -
OS-7239 Woodland Cree 226
OS-7239 -
Woodland Cree 226
OS-7238 -
Woodland Cree CMHC Co-Investment Housing Project - Simon Lake Subdivision (21-Units)
Woodland Cree First Nation -
OS-7245 Woodland Cree Reserve 226
Woodland Cree 226 -
RW-4852 and OS-7246 Authorization to Construct and Operate a Right of Way for a natural gas Pipeline and associated riser
Alexander First Nation -
OS-7255 Authorization to Construct and Operate a Surface Lease for a Borrow Pit, a multi-well pad and log deck.
Alexander First Nation 134A -
Application for Approval of the 2021 Pipeline Decommission Program
Alexis Nakota Sioux Nation Whitecourt (IR 32) Reserve Lands -
Loon River First Nation: CU344 Main Access Road Upgrade Project
Loon River First Nation -
Loon River First Nation Wastewater Treatment Facility Upgrade and Expansion
Loon River First Nation -
Loon River First Nation North Central Corridor Loop Temporary Contractor Yard
Loon River First Nation -
Loon River First Nation: Industrial Park Grocery Store
Loon River Cree Nation -
Loon River First: Nation Industrial Park Warehouse
Loon River First Nation -
Loon River Cree Nation Pure Fibre Network Project
Loon River Cree Nation -
Loon River First Nation: CU363 Emergency Wastewater System Repairs
Loon River First Nation -
Loon River First Nation: CU350 BF 78716 Bridge Replacement over Loon River
Loon River First Nation -
Loon River First Nation Water Treatment Plant Upgrades Design Construction
Loon River First Nation -
Alexis Nakota Sioux Nation 1993 Spill Remediation Project
Alexis Nakota Sioux Nation -
Duncan's First Nation New Subdivision - 22 units
Duncan First Nation -
Duncan's First Nation Three Unit Housing Project in Current Sub-Division
Duncan's First Nation -
Moraine Power Generation Project
Whitecourt -
Highway 947 Extension Project
-
Bigstone Cree First Nation Flood Recovery Program: Culvert 166D-08 TSAG ID No. 08 Replacement
Bigstone Cree Nation -
Bigstone Cree Nation Flood Recovery Program: Culvert 166D-27 Replacement
Bigstone Cree Nation -
New Fibre Installation
Project Site 4 - Wabasca No. 166D: -
OS-7241 Wabasca IR 166D | Authorization to Construct and Operate a Surface Lease for an access road and for a multiwell pad
Wabasca IR # 116D -
New Fibre Installation
Project Site 2 - Wabasca No. 166B : -
Rogers Communications Inc., new radiocommunications tower (W6238) on Peerless Trout First Nation land, near Trout Lake, AB.
W6238 - Peerless Trout First Nation Land (near Trout Lake) -
Bigstone Cree Nation High School Waterline Project
Wabasca -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-18 TSAG ID No. 04 Replacement
Bigstone Cree Nation -
New Fibre Installation
Project Site 1 - Bigstone Cree Nation: -
Bigstone B.O.S.S Modular Construction and Fabrication Yard Expansion Project
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-17 TSAG ID No. 03 Replacement
Bigstone Cree Nation -
Bigstone Cree First Nation Flood Recovery Program: Culvert 166A-10 TSAG ID No. 07 Replacement
Bigstone Cree Nation -
Bigstone Cree Nation New High School
Bigstone Cree Nation -
Bigstone Cree Nation Education Authority: CU254 Oksi Pasikoniwew Kakik School Secondary Access Road Project
Bigstone Cree Nation -
Bigstone Cree Nation Oilfield Supply Store
Wabasca #166 -
ATCO Gas and Pipelines Ltd.: 1088866 Wabasca IR No. 166A Gas Distribution Extension
Bigstone Cree Nation Wabasca IR No. 166A -
Rycroft Alternative Water Hub Facility Project
Woking -
Wabasca Water Treatment Plant Upgrades Project
Wabasca -
New Fibre Installation
Project Site 3 - Wabasca No. 166C: -
Wolverine River Lateral Loop (Carmon Creek Section)
Jackpine Lake -
ATCO Gas and Pipelines Ltd.: 1088866 Bigstone Cree Nation & Hamlet of Sandy Lake Gas Feeder and Mains at Wabasca IR No. 166
Bigstone Cree Nation -
North Corridor Expansion Project
Peerless Lake -
Rogers Communications Inc., new radiocommunications tower (W6225) on Peerless Trout First Nation land, near Peerless Lake, AB.
W6225 - Peerless Trout First Nation Land (near Peerless Lake) -
New Fibre Installation
Project Site 5 - Wabasca No. 166: -
ATCO Gas and Pipelines Ltd.: 1098480 Wabasca IR No. 166 Phase 2 Alfred Road Gas Main & Distribution System
Bigstone Cree Nation -
2017 NGTL System Expansion Project
Grande Prairie -
Prairie Lights Power Project
Greenview -
North Corridor Expansion Project
Highway 88 -
Amisk Hydroelectric Project
Peace River -
Grande Prairie Very High Frequency Omni-directional Range (VOR) Replacement
Transport Canada Property Number DFRP# 15908: Grande Prairie (VOR/DME) -
Meanook National Wildlife Area Buildings Demolition
Meanook National Wildlife Area