RW-4852 and OS-7246 Authorization to Construct and Operate a Right of Way for a natural gas Pipeline and associated riser
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
A 15 m wide, 4,287 m long right of way easement will provide for the construction and operation of a pipeline riser and a pipeline that will transport natural gas. Construction of this infrastructure and reclamation of the right of way will be completed within the first year of the project. Following decommissioning of the pipeline, the right of way will be surrendered.
The proposed pipeline alignment will follow existing linear disturbances (seismic lines, roads, etc.) wherever possible. Horizontal directional drilling will be used for all small permanent and intermittent creeks as well as the semi-permanent wetland.
The project is located in Alexander First Nation. The proponent is Crescent Point Energy.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Notice of Determination - Indian Oil and Gas Canada | - | March 16, 2023 |
1 | Notice of Intent to Make a Determination - Start of Public Comment Period - Indian Oil and Gas Canada | - | February 8, 2023 |
Contacts
Indian Oil and Gas CanadaJilczy Nelson, Environmental Analyst
9911 Chiila Boulevard Suite 100 Tsuut'ina AB T3T 0E1
Calgary, Alberta T3T 0E1
Telephone: 403-292-5625
Email: jilczy.nelson@sac-isc.gc.ca
-
Location
- Alexander First Nation (Alberta)
-
Nature of Activity
- Oil and Gas
-
Assessment Status
Completed -
Start Date
2023-02-08 -
Proponent
Crescent Point Energy -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
84313
Nearby assessments
...within 200 kilometres-
Highway 947 Extension Project
-
Application for Approval of the 2021 Pipeline Decommission Program
Alexis Nakota Sioux Nation Whitecourt (IR 32) Reserve Lands -
Alexis Nakota Sioux Nation 1993 Spill Remediation Project
Alexis Nakota Sioux Nation -
Moraine Power Generation Project
Whitecourt -
Highway 947 Extension Project
Edson -
Cascade Power Plant Project
Yellowhead County -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 6 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 5 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 4 -
Trans Mountain Pipeline Fiddle River Hazard Remediation
Jasper National Park -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 3 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 1 -
Upgrade (multiple) towers
Sturgeon Lake No.154 (Sturgeon Lake Cree Nation) - Site 2 -
Coalspur Vista Coal Underground Mine and Expansion Activities Project
10 kilometres east of Hinton -
Upgrade (multiple) towers
Sturgeon Lake No.154A (Sturgeon Lake Cree Nation) - Site 7 -
Coalspur Vista Coal Mine Phase II Expansion Project
3.5 kilometres east of Hinton -
DCN 2023 Rapid Housing Project
DCN 2023 Rapid Housing Project -
Driftpile Cree Nation Gas Line Connector Project
Driftpile Cree Nation -
Driftpile Cree Nation New Housing Construction Project
Driftpile, AB -
Driftpile Cree Nation Housing Project
Driftpile Cree Nation -
Driftpile Cree Nation Lift Station No. 1 Replacement Project
Driftpile Cree Nation -
Sucker Creek First Nation Water System Upgrades
Sucker Creek First Nation -
Sucker Creek Housing Project 2020 (4 Units)
Sucker Creek First Nation -
Three Unit Modular Housing Project
Sucker Creek First Nation -
Joussard Harbour Alberta - Routine Maintenance Dredging of the Joussard Harbour at Lesser Slave Lake Alberta - over the next year
Joussard Harbour -
Robb Trend Coal Mine Expansion Project
Robb -
Swan River First Nation Waste Diversion and Recycling Facility
Swan River First Nation -
Swan River First Nation: Wastewater Lagoon Liner Repair & Sub-liner Drainage Upgrade
Swan River First Nation -
Swan River First Nation Lakefront Development Project
Lesser Slave Lake -
Swan River First Nation Housing Project 2019 (5-Units)
Swan River First Nation -
Alexis Nakota Sioux Nation Youth Transitional House Project
Alexis Nakota Sioux Nation -
Kapawe'no First Nation Echo Prairie Waterline Project
Kapawe'no First Nation -
Waheeba Solar Energy Project
Alexis First Nation -
Kapawe'no Adventure Trail Project
Kapawe'no Adventure Trail Project -
Pasa Tibi Village Elder's Living Facility
Alexis Nakota Sioux Nation -
Rapid Housing Initiative 3 - Hill Plain
Alexis Nakota Sioux Nation -
Edson Mainline Expansion Project
Drayton Valley -
Alexis Nakota Sioux Junior and Senior High School - Educational dock
Alexis Nakota Sioux Nation -
Depth of Cover Mitigation at four sites on the 114.3 mm Jasper Transmission Pipeline in Proximity to the Fiddle River
Jasper National Park -
Xplornet Telecommunications Tower Project
Alberta Beach -
ATCO Miette 5L215 Rebuild
Jasper National Park -
Sundance 7 Generating Station Project
Wabamun -
Prairie Lights Power Project
Greenview -
Paul First Nation Gas Station Project
Paul First Nation -
Paul First Nation Culvert Replacement Project
Paul First Nation -
Paul First Nation 2-unit Housing Project
Paul First Nation -
Sawridge Band Solar Farm Project
Sawridge Band -
Alexander First Nation: BF 77352 Replacement and Twp. Rd 562 Improvements
Alexander First Nation -
Replacement of the Carvel Weather Radar
1529 Parkland Hwy, Carvel, Alberta, T0E 0H0 -
O'Chiese Culvert 2 Replacement Project
O'Chiese First Nation -
Alexander Wastewater Treatment Plant
Alexander First Nation -
Alexander First Nation Waste Transfer/Diversion Station Rehabilitation
Alexander First Nation -
Alexander Public Works and Fire hall Building Project
Alexander First Nation -
Summit Mine 14 Project
Grande Cache -
O'Chiese Culvert 1 Replacement Project
O'Chiese First Nation -
Parks Canada Agency Snaring River Bridge Rehabilitation
Jasper National Park of Canada -
O'Chiese Culvert 3 Replacement Project
O'Chiese First Nation -
O'Chiese Indian Reserve 203 Well pad Expansion
O'Chiese Reserve -
2017 NGTL System Expansion Project
Grande Prairie -
O'Chiese Indian Reserve 203
O'Chiese Indian Reserve 203 -
Edson Mainline Expansion Project
Drayton Valley -
Remediation of a Royal Canadian Mounted Police Property in Stony Plain, Alberta
Town of Stony Plain -
O'Chiese Indian Reserve 203 Well pad Expansion
O'Chiese Reserve 203 -
Trail 8c Realignment
Jasper National Park of Canada -
Smoky River Wind Project
Municipal District of Smoky River, between Nampa and Falher -
Alexander First Nation Campground Project
Alexander First Nation -
Whitefish Lake Fire Guard Project
Whitefish Lake First Nation 155 -
Jacques Lake Realignment
Jasper National Park of Canada -
Trans Mountain Fibre Gaps Project
Jasper National Park -
Caribou Conservation Breeding and Augmentation Project in Jasper National Park
Jasper National Park, Detailed Impact Assessment -
Parks Canada Agency Backcountry Meadows Prescribed Burn
Jasper National Park -
Parks Canada Agency Douglas Fir Slopes Prescribed Burn
Jasper National Park -
Genesee Generating Station Expansion Project
Near Warburg -
JTA - Hochimini Trail Realignment
Jasper National Park -
Parks Canada Agency Connaught East Waterway Restructure
Jasper National Park -
Pine Bungalows Master Plan 2021
Jasper National Park -
Sunchild 202 Reserve oil and gas development
Sunchild Reserve 202 -
Atikameg Healing Shelter for Women and Children
Whitefish Lake First Nation -
O'Chiese First Nation
O'Chiese First Nation -
Parks Canada Agency Pyramid Bench Fire Guard Prescribed Burn
Jasper National Park of Canada -
Sunchild Gas Distribution Line
Sunchild -
O'Chiese Indian Reserve Pipeline
Sunchild Indian Reserve -
Trail 1a Jasper National Park
Jasper National Park -
O'Chiese First Nation Powwow Arbor Replacement
O'Chiese First Nation -
Parks Canada Agency Prescribed Burns- Southesk, Talbot Lake
Jasper National Park -
Parks Canada Agency - Trail 8c Re-route in Jasper National Park
Jasper National Park -
Trans Mountain Corporation Sleepy Hollow Line Replacement
Jasper National Park -
Evelyn Creek trail re-adoption into official trail network
Jasper National Park -
Sunchild Culvert 1 Replacement Project
Sunchild First Nation -
Sunchild Culvert 2 Replacement Project
Sunchild First Nation -
OS-5844 oil and gas well site Sunchild IR202
OS-5844 Sunchild IR 202 -
Grande Prairie Very High Frequency Omni-directional Range (VOR) Replacement
Transport Canada Property Number DFRP# 15908: Grande Prairie (VOR/DME) -
Sunchild First Nation Lagoon and Residential Access Road Project
Sunchild First Nation -
Sunchild First Nation Subdivision Planning
Sunchild First Nation -
Enoch Phase 27 Housing Project 2020 (5 Units)
Enoch Cree Nation -
Enoch Cree Nation Housing Development Project
Enoch Cree Nation -
Marmot Basin Knob Chair Lift Line Replacement
Jasper National Park of Canada -
Enoch Cree Nation Wastewater System Upgrades
Enoch Cree Nation -
Enoch Cree Nation Traditional Lands Development Project
Enoch Cree Nation