Sunchild Culvert 2 Replacement Project
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Sunchild First Nation plans to upgrade a watercourse crossing located on an unnamed tributary to the Baptiste River. The proposed project includes the replacement of four existing multiplate culverts (2700mm Ø x 50m length) with a single open-bottom arch culvert (11023mm x 2448mm x 31040mm). The roadway in the vicinity of the culvert will also be upgraded.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
6 | Notice of Determination for the the Sunchild Culvert 2 Replacement Project | - | August 31, 2022 |
5 | Sunchild Culvert 2 Replacement Project | - | April 21, 2022 |
3 | Sunchild Culvert 2 Replacement Project- Public Comments Invited | - | March 3, 2022 |
2 | Notice of Determination for the Sunchild Culvert 2 Replacement Project | - | July 15, 2021 |
1 | Sunchild Culvert 2 Replacement Project- Public Comments Invited | - | February 23, 2021 |
Contacts
Transport CanadaHolly Poklitar, Regional Environmental Officer
Winnipeg, Manitoba
Telephone: 204-688-3872
Email: holly.poklitar@tc.gc.ca
-
Location
- Sunchild First Nation (Alberta)
-
Nature of Activity
- Water Management
-
Assessment Status
Completed -
Start Date
2021-03-03 -
Proponent
Sunchild First Nation -
Authorities
- Indigenous Services Canada
- Transport Canada
-
Assessment Type
Project on federal lands -
Reference Number
81395
Nearby assessments
..within 200 kilometres-
Sunchild First Nation Lagoon and Residential Access Road Project
Sunchild First Nation -
Sunchild First Nation Subdivision Planning
Sunchild First Nation -
Sunchild Culvert 1 Replacement Project
Sunchild First Nation -
Sunchild Gas Distribution Line
Sunchild -
O'Chiese Indian Reserve Pipeline
Sunchild Indian Reserve -
Sunchild 202 Reserve oil and gas development
Sunchild Reserve 202 -
O'Chiese Indian Reserve 203 Well pad Expansion
O'Chiese Reserve 203 -
O'Chiese Culvert 3 Replacement Project
O'Chiese First Nation -
O'Chiese Indian Reserve 203
O'Chiese Indian Reserve 203 -
O'Chiese Culvert 1 Replacement Project
O'Chiese First Nation -
O'Chiese Indian Reserve 203 Well pad Expansion
O'Chiese Reserve -
O'Chiese Culvert 2 Replacement Project
O'Chiese First Nation -
Edson Mainline Expansion Project
Drayton Valley -
Edson Mainline Expansion Project
Rocky Mountain House -
NOVA Gas Transmission Ltd. - 2021 NGTL System Expansion Project
Grande Prairie -
Edson Mainline Expansion Project
Drayton Valley -
Stoney Nation Big Horn Wastewater System
Big Horn No. 144A -
New Fibre Installation
Big Horn 144A - site 2(BH-FSA) -
New Fibre Installation
Big Horn 144A - site 1(BH-POP) -
Big Horn Reserve Water System
Big Horn Reserve No. 144A -
Big Horn Fire Hall
Big Horn Reserve -
Clearwater Peat Harvesting Project
Caroline -
Edson Mainline Expansion Project
Rocky Mountain House -
Genesee Generating Station Expansion Project
Near Warburg -
Sundance 7 Generating Station Project
Wabamun -
Ya Ha Tinda Ranch Solar Array
Banff National Park -
Robb Trend Coal Mine Expansion Project
Robb -
Paul First Nation Culvert Replacement Project
Paul First Nation -
Storage Tank Decommissioning and Relocation at Multiple Locations - 3rd Canadian Division Support Base, Southern Alberta
Cormack Armoury - Red Deer -
Samson Menaik Road Commercial Development Project
Samson Cree Nation -
Owen Creek Warden Cabin Decommissioning
Banff National Park -
Parks Canada Agency Prescribed Burns- Southesk, Talbot Lake
Jasper National Park -
Louis Bull Kikinow Housing Project
Louis Bull Tribe -
Louis Bull Tribe Water System Project/Water Treatment Plant and Reservoir
Louis Bull Tribe -
Louis Bull Tribe - 2020 Septic System Improvements
Louis Bull Tribe -
Cascade Power Plant Project
Yellowhead County -
Alexander First Nation Campground Project
Alexander First Nation -
Ermineskin Waste Transfer Station
Ermineskin Cree Nation -
Replacement of the Carvel Weather Radar
1529 Parkland Hwy, Carvel, Alberta, T0E 0H0 -
Ermineskin Solar Project
Ermineskin Cree Nation No. 138 -
Highway 947 Extension Project
Edson -
Alexis Nakota Sioux Nation Youth Transitional House Project
Alexis Nakota Sioux Nation -
Samson Cree Nation Water Infrastructure Replacement
Samson Cree Nation -
Ermineskin Sundancer Solar Project 2MWdc
Ermineskin Cree Nation -
Montana First Nation Emergency Road Repairs
Montana First Nation -
Water Survey Canade Silverhorn Water Meter Station
Banff National Park -
Highway 93 N 2020 Rip Rap Sourcing Program
Banff National Park -
Alexis Nakota Sioux Junior and Senior High School - Educational dock
Alexis Nakota Sioux Nation -
Xplornet Telecommunications Tower Project
Alberta Beach -
Remediation of a Royal Canadian Mounted Police Property in Stony Plain, Alberta
Town of Stony Plain -
Samson Cree Nation 3 Mile Lagoon Drainage Improvements
Samson Cree Nation -
AIRPORT CITY SOLAR PROJECT at Edmonton International Airport
Edmonton International Airport -
Lodge at Bow Lake Staff Accommodation, Dining Tent, and Parking Lot
Banff National Park of Canada -
GroHERE at Edmonton International Airport
Edmonton International Airport -
Airport Perimeter Road South Extension at Edmonton International Airport
Edmonton International Airport -
Cargo and Apron Development at Edmonton International Airport
Edmonton International Airport -
Runway End Safety Areas at Edmonton International Airport
Edmonton International Airport -
Runway End Safety Areas at Edmonton International Airport
Edmonton International Airport -
Cargo and Apron Development at Edmonton International Airport
Edmonton International Airport (Alberta) -
Alberta Zero Emissions Truck Electrification Collaboration Fueling Station
Edmonton International Airport -
PCA Clearwater Prescribe Burn
Banff National Park of Canada -
Enoch Phase 27 Housing Project 2020 (5 Units)
Enoch Cree Nation -
Enoch Cree Nation Wastewater System Upgrades
Enoch Cree Nation -
Alexandra Patrol Cabin Demolition and Removal
Banff National Park -
Margaret Creek Fish Barrier Creation
Banff National Park -
Enoch Cree Nation Housing Development Project
Enoch Cree Nation -
Badger Lake Non-Native Trout Removal
Banff National Park -
Fortis Line Rebuild at Lake Louise Ski Area
Banff National Park -
Lake Louise Heliport
Kootenay/Yoho/Lake Louise National Parks -
Lake Louise Community Fire Guard
Banff National Park -
Lake Louise Inn Generator and Exit Stairs
Banff National Park -
Mountaineer Lodge Staff Accommodation - 221 Hector Road
Banff National Park -
Village of Lake Louise Utilities Selected System Upgrades
Banff National Park -
Fairmont Chateau Lake Louise Cooling Unit Installation
Banff National Park -
Chateau Lake Louise New Parking Lot Construction
Banff National Park of Canada -
Deer Lodge Redevelopment
Banff National Park -
Fairmont Chateau Lake Louise Pool Demolition
Banff National Park -
Chateau Lake Louise Pool Rebuild
Banff National Park -
Depth of Cover Mitigation at four sites on the 114.3 mm Jasper Transmission Pipeline in Proximity to the Fiddle River
Jasper National Park -
Alexander Wastewater Treatment Plant
Alexander First Nation -
Coalspur Vista Coal Underground Mine and Expansion Activities Project
10 kilometres east of Hinton -
Small-scale habitat enhancement for bears near Lake Louise, Alberta
Banff National Park -
Alexander Public Works and Fire hall Building Project
Alexander First Nation -
Trans Mountain Expansion Project
Edmonton -
Parking Lot Resurfacing for the Entire Complex along with Line Painting at the RCMP K Division
Edmonton -
Fortis Line Install at CP Mile 108
Banff National Park -
Stoney Morley Broadband Tower Installation (Tower 12)
Stoney Nakoda Nation -
Protection Mountain Fire Guard
Banff National Park -
Evelyn Creek trail re-adoption into official trail network
Jasper National Park -
Alexander First Nation Waste Transfer/Diversion Station Rehabilitation
Alexander First Nation -
Coalspur Vista Coal Mine Phase II Expansion Project
3.5 kilometres east of Hinton -
Xplore Inc. Radiocommunication New Tower Proposals on the Stony No. 142-143-144 Reserve, Morley, AB 6318 Forestry Trunk Road
Morley, AB 6318 Forestry Trunk Road -
Abbot Pass Hut National Historic Site Removal
Yoko National Park, Detailed Impact Assessment -
Moraine Lake Lodge Duplex Cabins
Banff National Park -
Mannix Pit 10 Year Gravel Extraction and Reclamation Expansion
Banff National Park of Canada -
Xplore Inc. Radiocommunication New Tower Proposals on the Stony No. 142-143-144 Reserve,
Morley, AB -
PCA Castle Mountain Campground Utilities Upgrade
Banff National Park -
Town of Banff Affordable Housing Apartments, 338-342 Banff Avenue
Banff National Park -
Base Line Terminal Project
Edmonton -
Fortis Alberta 610013030 Castle Junction 551L Rebuild
Banff National Park of Canada -
Cascade Pit Gravel Crushing
Banff National Park -
Johnston Canyon Railing Extension
Banff National Park -
PCA Forty Mile Prescribe Fire
Banff National Park -
Fairholme II Prescribed Fire
Banff National Park -
Banff Air Strip Structure Removal
Banff National Park -
FortisAlberta Cascade 177S Substation Maintenance
Banff National Park -
AltaLink 54L Transmission Rebuild
Banff National Park -
Town of Banff Water Withdrawal, Distribution and Treatment System
Banff National Park -
Parks Canada HWY 93S Boom Creek Culvert Replacement
Banff National Park -
100 Falcon Street-New carpentry shop
Banff National Park -
ATCO Gas Installation of 5 Cathode Test Stations in the Town of Banff
Banff National Park -
Eagle Crescent Mountain View BBQ Housing
Banff National Park -
Tunnel Mountain Campground Winter Use
Banff National Park -
1 Combat Engineer Regiment (CER) Compound Expansion - 3rd Canadian Division Support Base Edmonton
3rd Canadian Division Support Base Edmonton -
Town of Banff 36 Unit Apartment, 418-420 Cougar Street
Banff National Park of Canada -
BC Hydro Field Energy Storage Facility Temporary Generator
Yoko National Park -
Otter Hotel Development (Inns of Banff)
Banff National Park of Canada -
Town of Banff 435 Squirrel Street Shaw Cable
Banff National Park -
Stoney Phase 17 Housing Project
Wesley First Nation -
CP Rail Mountain Subdivision, Mile 3.8 Boulder Creek Bridge Rehab and Bedload Removal
Yoko National Park -
435 Squirrel Street CP Rail Transformer Installation
Banff National Park -
Stoney Morley Rapid Housing Project
Morley -
Town of Banff 425 Muskrat St New 8 Unit Residential Dwelling
Banff National Park -
Banff Lodging Company-413 Beaver Street Redevelopment
Banff National Park -
Shaw Cable Installation at 327 Railway Ave
Banff National Park -
Telus Roehampton CP Rail Yard Mobility
Banff National Park -
Town of Banff 311 and 317 Squirrel Street Redevelopment
Banff National Park -
Town of Banff 347 Grizzly Street New Garage and Accessory Dwelling
Banff National Park -
Town of Banff Atco gas valve replacements, Wolf Street
Banff National Park -
Town of Banff Bow River Bridge Old Pump Station Building Demolition
Banff National Park -
19DP86 - 220 Otter Street Demo and New Building
Banff National Park -
Town of Banff Bear Street Reconstruction
Banff National Park -
206 Otter Street Single Detached Dwelling Residential Addition
Banff National Park -
Bow Valley Credit Union- New Mixed Use Building Construction, 212 Banff Ave. Town of Banff
Banff National Park -
Shaw Cable Conduit Installation in Town of Banff
Banff National Park of Canada -
Town of Banff 135 Lynx Street New Accessory Dwelling
Banff National Park -
Fortis Transformer Replacement
Banff National Park -
Town of Banff, New Family home construction, 129 Kootenay Ave
Banff National Park -
514 Buffalo Street, Crandell Peck Cabin Addition, Studio North
Banff National Park of Canada -
Town of Banff Atco gas valve replacement
Banff National Park -
Town of Banff Bow River Sewer Siphon Liner Installation and In-Water Riffle Construction
Banff National Park -
CCI Wireless o/a Corridor Communications Inc. Radiocommunication Antenna Addition on the Stony No. 142-143-144 Reserve, Morley, AB
Morley, Eagle Hill Rd -
Town of Banff Recreation Grounds Redevelopment and New Pedestrian Bridge
Banff National Park -
Town of Banff Bow River Bridge 2023 Rehabilitation Works
Banff National Park of Canada -
115 Spray Avenue Garage with Suite
Banff National Park -
Town of Banff Jasper Way to Cave Ave Commuter Trail
Banff National Park -
Town of Banff - Construction of Single Detached Home with Accessory Dwelling, 119 Spray Avenue
Banff National Park -
Alexis Nakota Sioux Nation 1993 Spill Remediation Project
Alexis Nakota Sioux Nation -
Kootenay National Park (KNP) Avalanche Mitigations, Whymper Remote Avalanche Control Systems (RACS)
Kootenay National Park -
Banff Trail Riders-3 Mile BBQ Redevelopment
Banff National Park -
ATCO Miette 5L215 Rebuild
Jasper National Park -
FortisAlberta Sunshine Cable Replacement - Phase 2
Banff National Park -
Stoney Phase 18 Housing Project
Wesley First Nation -
Stoney Nakoda Nation Broadband Tower installation - Tower 14 Project
Stoney Nakoda Nation -
Xplore Inc. Radiocommunication New Tower Proposals on the Stony No. 142-143-144 Reserve,
Ozada, AB -
Stoney North Morley Sanitary Servicing
Stoney First Nation -
Wesley First Nation Solar Panels Project
Morley and Bighorn -
Trans Mountain Pipeline Fiddle River Hazard Remediation
Jasper National Park -
Pursuit Night Rise Program
Banff National Park of Canada -
CCI Wireless o/a Corridor Communications Inc. Radiocommunication Antenna Addition on the Stony No. 142-143-144 Reserve, Morley, AB
Morley AB, 133X -
CCI Wireless o/a Corridor Communications Inc. Radiocommunication Antenna Addition on the Stony No. 142-143-144 Reserve, Morley, AB
Morley AB, 133X -
CCI Wireless o/a Corridor Communications Inc. Radiocommunication Antenna Addition on the Stony No. 142-143-144 Reserve, Morley, AB
Morley AB, Stoney 142 -
Stoney Phase 18 Housing Project
Chiniki First Nation -
Stoney Nakoda Broadband Tower installation - Repeater Towers
Stoney Nakoda Nation -
Xplore Inc. Radiocommunication New Tower Proposals on the Stony No. 142-143-144 Reserve,
Cochrane, AB -
Xplore Inc. Radiocommunication New Tower Proposals on the Stony No. 142-143-144 Reserve,
Seebe, AB -
Parks Canada Meadow Restoration Prescribe Fire Plan
Banff National Park -
Canalta 530 Banff Ave Redevelopment
Banff National Park -
FortisAlberta Pole Replacement - Town of Banff (610013803)
Banff National Park -
Application for Approval of the 2021 Pipeline Decommission Program
Alexis Nakota Sioux Nation Whitecourt (IR 32) Reserve Lands -
ATCO Gas Cascade Mall Banff
Banff National Park -
Town of Banff 222 Otter Street Redevelopment
Banff National Park -
Town of Banff 217 Otter Street Redevelopment
Banff National Park of Canada -
ToB 22DP57 216-218 Muskrat Street Redevelopment
Banff National Park of Canada -
Town of Banff 525 Buffalo Street Development
Banff National Park -
Parks Canada Agency Backcountry Meadows Prescribed Burn
Jasper National Park -
Private owner build, new duplex within the Town of Banff
Banff National Park -
Caribou Conservation Breeding and Augmentation Project in Jasper National Park
Jasper National Park, Detailed Impact Assessment -
Jacques Lake Realignment
Jasper National Park of Canada -
Trans Mountain Fibre Gaps Project
Jasper National Park -
Sunshine Village Ski Area - Parking Lot Reconfiguration and Improvements
Banff National Park -
Sunshine Village Ski Resort Bourgeau Parking Lot Parkade
Banff National Park -
Trail 8c Realignment
Jasper National Park of Canada -
Highway 93S km 20 Bank Stabilization
Kootenay National Park -
Wesley Band Goodstoney Meadows Development
Morley, AB -
JCLS Church Shaw Cable installation
Banff National Park -
Sunshine Village Ski Resort Ski Out Widening Tree Removals
Banff National Park of Canada -
Sunshine Village Ski Resort Long Range Plan
Detailed Impact Assessment, Banff National Park -
PCA Backcountry Shelter Redevelopment-Bryant and Egypt
Banff National Park -
Parks Canada Agency Douglas Fir Slopes Prescribed Burn
Jasper National Park -
Sunshine Village Ski Resort Angel Chairlift Replacement
Banff National Park of Canada -
Potential Regional Assessment of a Western Energy Corridor from Alberta to Manitoba
Fort Saskatchewan -
Trail 1a Jasper National Park
Jasper National Park -
Highway 947 Extension Project
-
Pyramid Lake Resort Wastewater Treatment Plant and Disposal System
Jasper National Park -
Pine Bungalows Master Plan 2021
Jasper National Park -
Trans Mountain Corporation Sleepy Hollow Line Replacement
Jasper National Park -
Parks Canada Agency Pyramid Bench Fire Guard Prescribed Burn
Jasper National Park of Canada -
Marmot Basin Knob Chair Lift Line Replacement
Jasper National Park of Canada -
JTA - Hochimini Trail Realignment
Jasper National Park -
Parks Canada Agency - Trail 8c Re-route in Jasper National Park
Jasper National Park -
Parks Canada Agency Snaring River Bridge Rehabilitation
Jasper National Park of Canada -
Rooftop Solar Installation at Letter Carrier Depot (LCD) NW Calgary
40 Royal Vista Drive NW, Calgary, Alberta -
Fort Saskatchewan Rail Facility Project
Fort Saskatchewan -
Heartland Petrochemical Complex Rail Yard Project
North of Fort Saskatchewan -
Cando Sturgeon Rail Terminal Project
Sturgeon County -
Simpson 3 Avalanche Path Berm, Kootenay National Park
Kootenay National Park -
RW-4852 and OS-7246 Authorization to Construct and Operate a Right of Way for a natural gas Pipeline and associated riser
Alexander First Nation -
Redwater Facility Rail Yard Project
Near Redwater -
Springbank Off-Stream Reservoir Project
15 kilometres west of Calgary -
Sturgeon Petrochemical Rail Yard Project
Six kilometres north of Fort Saskatchewan -
Culvert Replacement with Larger Diameter
Elk Island National Park -
Simpson River Pit Toilet Installation
Kootenay National Park of Canada -
Alberta Transportation Culvert Installation on Highway 16 near Main Park Entrance EINP
Elk Island National Park -
Heartland Generating Station Project
Fort Saskatchewan, Bruderheim -
ATCO Salt Cavern Storage Expansion Project
14 kilometres northeast of Fort Saskatchewan -
New rooftop radiocommunications antenna for Aero Mag 2000 at the Calgary International Airport
Calgary International Airport -
Bear and Moss Trails Restoration, Elk Island National Park
Elk Island National Park -
Strathcona Salt Cavern Storage Project
near Fort Saskatchewan -
Calgary International Airport West Runway Rehabilitation Project
Calgary -
Enbridge Northern Gateway Project
Bruderheim -
New rooftop radiocommunications antenna for Central Mountain Air at the Calgary International Airport
Calgary International Airport -
Value Chain Solutions - Heartland Complex Expansion Project
18 kilometres north east of Fort Saskatchewan -
Tsuut'ina Nation - Millburn Creek Culvert Replacement and Road Restoration Project
Tsuut'ina Nation -
PCA Backcountry Shelter Redevelopment-Bryant and Egypt
Banff National Park