Pigeon Lake Recreation Centre Water and Sewer Line Replacement Project

Louis Bull First Nation proposes to replace an approximately 200 meter long waterline and an approximately 200 meter long sewer line connected to the existing Pigeon Lake recreation centre. The proposed project will involve the excavation of the former line in order to replace it with a new one. Anticipated impacts of the proposed project on waterbodies, vegetation, and wildlife are minimal.


Latest update

November 21, 2023 - The assessment decision statement has been issued to the proponent.

Participate

Key documents

Key documents
Document Number Document Title File Date
1 Notice of Intent to make a Determination - May 24, 2023

Contacts

Lands and Economic Development
Joël Gervais, P.Biol., Environment Officer
630 Canada Place, 9700 Jasper Avenue
Edmonton, Alberta T5J 4G2
Telephone: 780-224-5395
Email: joel.gervais@sac-isc.gc.ca


  • Location

    • Pigeon Lake (Alberta)
  • Nature of Activity

    • Water Management
  • Assessment Status

    Completed
  • Start Date

    2023-05-24
  • Proponent

    Louis Bull First Nation
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    84627
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: