Parks Canada Agency Connaught East Waterway Restructure
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Jasper National Park experienced a significant rainfall event in June 2023, resulting in flood conditions in the Cottonwood Creek channel, along the eastern edge of the townsite of Jasper. The high-water event resulted in erosion of the creek bed and bank, causing destabilization and partial failure of the roadbed next to the creek. Flows have since subsided to normal rates and Parks Canada intends to repair the damaged portions of the road bed and bank. The work is proposed in three locations along the impacted portion of the creek.
Area 1: road failure site (previously disturbed and channelized) – Install stream isolation, perform fish salvage, and dewater the worksite. Remove jersey barriers and pavement that collapsed into the creek when the road failed. Remove clean boulders that were placed temporarily during flood event. The eroded base of the end lock blocks from the current wall would be rebuilt as well as the base for new blocks will be built using 3/4" crush with backhoe and compaction device. The block wall will be extended to meet the uneroded bank upstream and the space behind the blocks under the road will be backfilled with clean fill material of 2" minus sourced from inside the park. The creek isolation will be removed once instream work is complete. The damaged road bed will be rebuilt, and asphalt paved.
Area 2: culvert inlet - Class I round rock along backslope of road above culvert will be added where it was washed out. Rock work will be mostly above the high-water mark and will not interfere with the streambed or natural banks.
Area 3: culvert outlet – Install stream isolation, perform fish salvage, and dewater the worksite. Once the area is dewatered, the culvert will be cleared of accumulated sediment, maintaining the midsized cobble bed. This will be done with a back hoe and by hand. Washed rock sourced from within the park will be installed along the sides of the culvert against the road backslope with a back hoe operating from the road surface. Additional rock rip rap will be placed above the ordinary high-water mark across from the outlet, where the bank was previously armoured. Riparian vegetation will be maintained.
This project falls outside of the scope of the Roads and Related Infrastructure PRIA. This PRIA does not apply to projects that require authorization under the Fisheries Act. A request for review will be sent to Fisheries and Oceans Canada's Fish and Fish Habitat Protection Program Office. The BIA pathway is the suitable level of assessment to determine if the project is likely to cause significant residual environmental effects.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
1 | New project being assessed by Parks Canada and Fisheries and Oceans Canada - Public comments invited from September 14, 2023 to October 14, 2023 | - | September 14, 2023 |
Contacts
Jasper National ParkBox 10
Jasper, Alberta T0E 1E0
Telephone: 780-852-6141
Email: evaluationdimpactjasper-jasperimpactassessment@pc.gc.ca
-
Location
- Jasper National Park (Alberta)
-
Nature of Activity
- Highways and Roads
-
Assessment Status
In progress -
Start Date
2023-09-14 -
Proponent
Parks Canada -
Authorities
- Fisheries and Oceans Canada
- Parks Canada Agency
-
Assessment Type
Project on federal lands -
Reference Number
85913
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Pine Bungalows Master Plan 2021
Jasper National Park -
Parks Canada Agency Pyramid Bench Fire Guard Prescribed Burn
Jasper National Park of Canada -
Parks Canada Agency - Trail 8c Re-route in Jasper National Park
Jasper National Park -
JTA - Hochimini Trail Realignment
Jasper National Park -
Trans Mountain Corporation Sleepy Hollow Line Replacement
Jasper National Park -
Biocontrol of Linaria dalmatica (Dalmatian Toadflax) using the agent Mecinus janthiniformis (Stem-boring weevil) in Jasper National Park
Jasper National Park of Canada -
Parks Canada Agency Douglas Fir Slopes Prescribed Burn
Jasper National Park -
Trail 1a Jasper National Park
Jasper National Park -
Jasper House Bungalows Master Plan
Jasper National Park -
Trail 8c Realignment
Jasper National Park of Canada -
Jacques Lake Realignment
Jasper National Park of Canada -
Trans Mountain Fibre Gaps Project
Jasper National Park -
Caribou Conservation Breeding and Augmentation Project in Jasper National Park
Jasper National Park, Detailed Impact Assessment -
Parks Canada Agency Backcountry Meadows Prescribed Burn
Jasper National Park -
Parks Canada Agency Highway Operations Unit Marmot Pit Expansion-Winter Abrasives
Jasper National Park -
Parks Canada Agency Highway Operations Unit Marmot Pit Expansion-Winter Abrasives
Jasper National Park -
Trans Mountain Pipeline Site KP387 Bioremediation
Jasper National Park of Canada -
Marmot Basin Knob Chair Lift Line Replacement
Jasper National Park of Canada -
Parks Canada Agency Snaring River Bridge Rehabilitation
Jasper National Park of Canada -
Trans Mountain Derr Creek Bridge Replacement
Jasper National Park of Canada -
Trans-Mountains KP400.2 Derr Creek - TMPL 24" Depth of Cover and Bank Protection Mitigation
Jasper National Park -
Trans Mountain Pipeline ULC KP404 Integrity Dig
Jasper National Park of Canada -
Evelyn Creek trail re-adoption into official trail network
Jasper National Park -
ATCO Miette 5L215 Rebuild
Jasper National Park -
Pyramid Lake Resort Wastewater Treatment Plant and Disposal System
Jasper National Park -
Depth of Cover Mitigation at four sites on the 114.3 mm Jasper Transmission Pipeline in Proximity to the Fiddle River
Jasper National Park -
Parks Canada Agency Prescribed Burns- Southesk, Talbot Lake
Jasper National Park -
Coalspur Vista Coal Mine Phase II Expansion Project
3.5 kilometres east of Hinton -
Vista Coal Underground Mine Project and Vista Mine Phase II Expansion Project
10 kilometres east of Hinton -
Trans Mountain Pipeline Fiddle River Hazard Remediation
Jasper National Park -
Parks Canada Agency Brazeau Lake Bridge Replacement
Jasper National Park of Canada -
Robb Trend Coal Mine Expansion Project
Robb -
Pursuit - Columbia Icefield Adventure Tour Road Maintenance Program
Jasper National Park of Canada -
Highway 93 N 2020 Rip Rap Sourcing Program
Banff National Park -
Alexandra Patrol Cabin Demolition and Removal
Banff National Park -
Cascade Power Plant Project
Yellowhead County -
Highway 947 Extension Project
Edson -
Summit Mine 14 Project
Grande Cache -
Big Horn Reserve Water System
Big Horn Reserve No. 144A -
Stoney Big Horn AORHS and Health Center Project
Stoney Nakoda Nation -
Stoney Big Horn Fire Hall
Big Horn Reserve -
New Fibre Installation
Big Horn 144A - site 2(BH-FSA) -
New Fibre Installation
Big Horn 144A - site 1(BH-POP) -
Stoney Nation Big Horn Wastewater System
Big Horn No. 144A -
Ruddock Creek Mine Project
Avola -
Owen Creek Warden Cabin Decommissioning
Banff National Park -
Edson Mainline Expansion Project
Drayton Valley -
Water Survey Canade Silverhorn Water Meter Station
Banff National Park -
Edson Mainline Expansion Project
Drayton Valley -
Highway 947 Extension Project
-
Lodge at Bow Lake Staff Accommodation, Dining Tent, and Parking Lot
Banff National Park of Canada -
Wildfire Risk Reduction Project 2023-2026- FireSmart work at several facilities in the Lake Louise, Yoho, and Kootenay Field Unit
Banff National Park of Canada -
O'Chiese Culvert 2 Replacement Project
O'Chiese First Nation -
Rogers Communications Inc. Telecommunication Tower Project in Glacier National Park along Highway 1
Rogers Communications Inc. Telecommunication Tower Project in Glacier National Park along Highway 1 -
O'Chiese Culvert 1 Replacement Project
O'Chiese First Nation -
Hazard Spruce Tree Removal
Glacier National Park -
O'Chiese Culvert 3 Replacement Project
O'Chiese First Nation -
Harper Creek Mine Project
Vavenby -
Sunchild 202 Reserve oil and gas development OS-7243
Sunchild Reserve 202 -
Sunchild Culvert 2 Replacement Project
Sunchild First Nation -
New Rogers Communications Inc. Telecommunication Tower Project in Glacier National Park along Highway 1
New Rogers Communications Inc. Telecommunication Tower Project in Glacier National Park along Highway 1 -
O'Chiese Indian Reserve 203 Well pad Expansion
O'Chiese Reserve 203 -
Sunchild Gas Distribution Line
Sunchild -
Sunchild First Nation: Community Wastewater Lagoon and Access Road
Sunchild First Nation -
Sunchild First Nation: Community Roads, Residences, and Service Infrastructure Buildout
Sunchild First Nation -
Sunchild Indian Reserve Pipeline
Sunchild Indian Reserve -
O'Chiese Indian Reserve 203 Well pad Expansion
O'Chiese Reserve -
Margaret Creek Fish Barrier Creation
Banff National Park -
O'Chiese First Nation
O'Chiese First Nation -
O'Chiese Indian Reserve 203
O'Chiese Indian Reserve 203 -
Sunchild Culvert 1 Replacement Project
Sunchild First Nation -
OS-7255 Authorization to Construct and Operate a Surface Lease for a Borrow Pit, a multi-well pad and log deck.
Alexander First Nation 134A -
O'Chiese First Nation Former Landfills Closure and Remediation Plan
O'Chiese First Nation -
RW-4852 and OS-7246 Authorization to Construct and Operate a Right of Way for a natural gas Pipeline and associated riser
Alexander First Nation -
O'Chiese First Nation Powwow Arbor Replacement
O'Chiese First Nation -
Emerald Lake Lodge Water Permit
Yoho National Park of Canada -
OS-5844 oil and gas well site Sunchild IR202
OS-5844 Sunchild IR 202 -
Emerald Canoes Dock Replacement
Yoho National Park of Canada -
Edson Mainline Expansion Project
Rocky Mountain House -
NOVA Gas Transmission Ltd. - 2021 NGTL System Expansion Project
Grande Prairie -
Parks Canada Staff Accommodation 210 Stephen Avenue, Field, BC.
Yoho National Park of Canada -
Wildfire Risk Reduction Maintenance Activities - Yoho, Kootenay, and Banff National Parks (2023-2034)
Yoho National Park of Canada -
New Fibre Installation
Cassimayooks (Mayook) 5, Tobacco Plains 2, Yoho National Park Of Canada - Site 5 -
Mt. Stephen Trail Reroute
Yoho National Park of Canada