In support of the new Impact Assessment Act, the Impact Assessment Agency of Canada has redesigned and implemented a new Canadian Impact Assessment Registry. Learn more about the new Registry.

Registry Search Mobile

Registry Search

Hardrock Gold Mine Project

Greenstone Gold Mines is proposing the construction, operation, decommissioning, and abandonment of an open-pit gold mine and on-site metal mill located approximately five kilometres south of Geraldton, Ontario, at the intersection of Highway 11 (Trans-Canada Highway) and Michael Power Boulevard. As proposed, the gold mine would have an ore production capacity of 30,000 tonnes per day, and the metal mill would have an ore input capacity of 30,000 tonnes per day.

Please note that this project was formerly known as the Hardrock Deposit Project.

Please note that the proponent was formerly known as Premier Gold Mines Hardrock Inc.


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given project.


Latest update

December 13, 2018 - The Minister of Environment and Climate Change issued the Environmental Assessment Decision Statement to the proponent.

List all documents

Contacts

  • Impact Assessment Agency of Canada
  • 22nd Floor, Place Bell
  • Ottawa, ON, K1A 0H3
  • Telephone: 613-957-0700 or 1-866-582-1884
  • Fax: 613-957-0862
  • Email: ceaa.information.acee@canada.ca

  • Location

    • Geraldton (Ontario)
  • Project Type

    • Mines and Minerals
  • Status

    Completed
  • Start Date

    2014-06-13
  • Proponent

    Greenstone Gold Mines (formerly Premier Gold Mines Hardrock Inc.)
  • Authorities

    • Impact Assessment Agency of Canada
  • Assessment Type

    Environmental assessment under CEAA 2012
  • Reference Number

    80068
Date modified: