FORTIS Alberta has proposed a project to construct 2883.31 meters of underground powerline to Matilda Tower. Construction includes trenching, cable laying, cable splicing, installing padmount transformer, and installing padmount metering.


Latest update

July 25, 2023— The Department of National Defence issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination - July 25, 2023
1 Public Comment Period on Intent to Make a Determination - February 27, 2023

Contacts

Sheri McNamara
Department of National Defence
Sheri McNamara, Base Environment Officer
CFB Suffield, Box 6000 St Main
Medicine Hat, Alberta T1A 8K8
Email: Sheri.McNamara@forces.gc.ca


  • Location

    • Canadian Forces Base (CFB) Suffield (Alberta)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2023-02-27
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    84366