Green Island Lightstation - Wind and Solar Renewables Project
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
DFO and CCG are proposing to erect two miniature 9 metre wind turbines, a gravel maintenance pad and install an electrical raceway as a required component of the new wind and solar renewable power system at Green Island Lightstation. Foundations for the wind turbines and solar panels have already been poured. Green Island is currently powered exclusively by diesel fuel. Renewable energy technology has advanced through recent years. Reliability and efficiency have made large improvements since early versions. In efforts to reduce fuel consumption, ease the load on the diesel generators on site, and reduce the carbon footprint of the lightstation, DFO is proposing to install a hybrid renewable power system consisting of solar panels and wind turbines. The completion of this project will allow the lightstation to function on renewable energy and contribute to the Government of Canada's Greening Government Strategy of achieving net-zero operational emissions by 2050. The proposed construction will involve the installation of:
• (2) 4" diameter electrical conduit, (2) 3" diameter electrical conduit, and (1) 1" diameter electrical conduit, at least 0.75m underground and at least 0.5m above ground. The total length of the conduit is 50 m;
• Erection of (2) 9m wind turbine towers onto existing foundations;
• Installation of a gravel installation pad;
• Installation of (2) 200A fused disconnects fused at 40A for (2) wind turbines;
• Installation of type (10) pull boxes;
• Work is anticipated to take 12 days to complete with a crew of 4-5 workers;
• Upgrades to battery room including lighting and ventilation; and,
• Possible modifications to the solar panel foundations. In the event that additional concrete pouring is required, environmental mitigation measures will be implemented.
The project works do require ground disturbance to connect the below ground power cable array from the solar panel and wind turbines to the Engine Room building. There is a potential of disturbing suspected subsurface contamination during the installation of the underground electrical conduit. Environmental mitigation measures will be applied to ensure disturbed soil is contained in the same general area of the site. Equipment will be helicopter slung onsite.
The Green Island lightstation is located in Chatham Sound, about 35km northwest of Prince Rupert. The 2 – 2.5 hectare island consists mainly of rocky and sandy beaches and tall grass. No drinking water wells were identified within 1.5km from the site. The site is under the jurisdiction of DFO and CCG, and as such, is on federal land.
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
Participate
Contacts
Fisheries and Oceans Canada, Pacific RegionEmily Sapsford, Project Engineer
200 - 401 Burrard Street
Vancouver, British Columbia V6C 3S4
Telephone: 250-217-0323
Email: Emily.Sapsford@dfo-mpo.gc.ca
-
Location
- Green Island Lightstation (British Columbia)
-
Nature of Activity
- Building and Property Development
-
Assessment Status
Terminated -
Proponent
Fisheries and Oceans Canada - Real Property, Safety and Security -
Authorities
- Fisheries and Oceans Canada
-
Assessment Type
Project on federal lands -
Reference Number
83096
Nearby assessments
...within 200 kilometres-
New Fibre Installation
Lax Kw' Alaams 1 -
Port Simpson (Lax Kw'alaams) Entrance Channel Dredging
Port Simpson (Lax Kw'alaams) Small Craft Harbour -
Lax Kw'alaams Wastewater Transmission, Treatment and Disposal
Lax Kw'alaams -
Sienna Networks Ltd, New Telecommunications Tower on Lax Kw'alaams No. 1 Reserve, Lax Kw'alaams, BC
Lax Kw'alaams No. 1 Reserve, Lax Kw'alaams, BC -
Grassy Point LNG Project
Grassy Point -
Seafood Offloading Facility
Prince Rupert -
Prince Rupert Yard - New Track Construction
Prince Rupert -
Fairview Bay - CN Main Track Expansion
Prince Rupert, British Columbia -
WCC LNG Project
Tuck Inlet in Prince Rupert -
Canadian Coast Guard Seal Cove Base Mid Shore Patrol Vessel Float Replacement
Seal Cove Base is located on the Northern tip of Kaien Island, approximately 4km Northeast of the city center of Prince Rupert, BC. Seal Cove Base is accessible by road access, helicopter, and boat. -
Fairview CCG SAR - Float and Workshop Reconstruction
Fairview CCG SAR -
Seal Cove Coast Guard Base Helicopter Pad Replacement
Seal Cove Coast Guard Base -
Fairview Container Terminal Stage 1B (North) Expansion Project
Fairview Container Terminal -
Aurora LNG Project
Digby Island -
Fairview Terminal Phase II Expansion Project
Casey Point -
Connected Coast Fibre-Optic Cable Installation Project
Ridley Island -
Installation of a Submarine Fibre Optic Cable
Ridley Island, Prince Rupert -
CN Zanardi Bridge, Causeway, and Corridor Connection
Zanardi Rapids -
Ridley Terminals Expansion Project
Ridley Island -
Vopak Pacific Canada
Ridley Island -
Port Edward Phase 3 Wharf Reconstruction
Port Edward Harbour -
Canpotex Potash Terminal Project
Ridley Island -
Prince Rupert LNG Project
Ridley Island -
Ridley Island Export Logistics Platform
Ridley Island -
Porpoise Harbour - Lelu Island Range Markers
Porpoise Harbour -
Prince Rupert Gas Transmission Project
near Hudson's Hope -
Pacific Northwest LNG Project
Port Edward -
Canadian Coast Guard Holland Rock Helipad Rebuild
Holland Rock is located approximately 16 km south of Prince Rupert, BC, in Chatham Sound. -
Ksi Lisims LNG - Natural Gas Liquefaction and Marine Terminal Project
Wil Milit on Pearse Island -
New Fibre Installation
Dolphin Island -
Old Massett Village Council - Hiellen Longhouse Village Expansion
Old Massett Village Council -
Beverage Antenna Boardwalk - Canadian Forces Station (CFS) Leitrim
Masset -
Old Massett Mobile Eco-Depot and In-Vessel Composting System
Old Masset Village Council -
Kitsault Mine Project
Prince Rupert -
Decommissioning of Ne-Aska-Gila Guaw Creek Dam
Kitsumkalum IR #1 -
Kitimat Clean Refinery Project
Kitimat -
Pacific Future Energy Refinery Project
32 kilometres north of Kitimat -
LNG Canada Export Marine Terminal
District of Kitimat -
Coastal GasLink Pipeline Project
Northern British Columbia -
Kitimat LNG Terminal, Bish Cove, BC - Loading and Disposal at Sea of Excavated Material
Kitimat -
Cedar LNG Project
Kitimat -
Enbridge Northern Gateway Project
Kitimat -
Kitselas Community Recreation Centre
Kitselas -
Mitigation of Risks to Hartley Bay Water Supply Project
Mitigation of Risks to Hartley Bay Water Supply Project -
Kitimat LNG Expansion Project
Bish Cove -
Canadian Coast Guard Hartley Bay Search and Rescue Residence
Hartley Bay -
New Fibre Installation
Kulkayu 4 -
All Spirits Gitga'at
Hartley Bay -
Gitga'at FNWMS Sewage Treatment & Disposal Upgrade
Hartley Bay -
Gitga'at Hartley Bay Lift Station Repair
Hartley Bay -
Canadian Coast Guard Hartley Bay Search and Rescue Float
Hartley Bay -
Skidegate Watermain Extension for Wastewater Treatment Plant
Skidegate -
Nav Canada, Antenna Addition to Radiocommunications Tower on Transport Canada Property Number 19393, Sandspit, BC
Transport Canada Property Number 19393, Sandspit, BC -
Red Mountain Gold Mine Project
Stewart -
Gitga'at Hartley Bay Boardwalk Repair
Hartley Bay -
Canadian Coast Guard Mount Gil Radio Site Upgrade and Radar Installation
Mount Gil, Gil Island -
Gitwangak Community Drainage Project
Gitwangak