New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The Rural Municipality of Yellowhead is proposing the construction of a 36.5m telecommunication tower to provide high-speed internet access to the Keeseekoowenin First Nation. Antennas will be mounted at the top of the tower. The antennas will operate in the 24.1 and 5.7 GHz frequency bands. All of the equipment necessary to operate this facility will be housed in a small equipment cabinet located on site. The Rural Municipality of Yellowhead is also proposing the addition of a three sector antennas (594 mm X 157 mm X 110 mm), in the 5.7 GHz frequency band, mounted at the top of an existing 29.3m tower which is located on the Keeseekoowenin First Nation. The antennas will be installed to improve network access to high-speed internet. In the future, the new tower as well as the existing tower may have other antennas and other radiocommunication equipment added or replaced. The project will also install underground approximately 27 km of fiber optic cabling, for Internet purposes, to all residential homes in the Keeseekoowenin First Nation. The cable will run from Oakburn to the Keeseekoowenin region.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 1 | Notice of Determination - New Fibre Installation (Keeseekoowenin First Nation) | - | March 21, 2022 |
Contacts
Connected Canada BranchJames Finch, Program Manager
C.D. Howe Building
235 Queen Street
Ottawa, Ontario K1A 0H5
Telephone: 613-223-5828 or 1-866-694-8389
Email: james.finch@canada.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Keeseekoowenin First Nation (Indian Reserve 61) Project site 1 (Manitoba)
- Keeseekoowenin First Nation (Indian Reserve 61) Project site 2 (Manitoba)
-
Nature of Activity
- Other, not otherwise specified
-
Assessment Status
Completed -
Start Date
2022-01-28 -
Proponent
The Rural Municipality of Yellowhead -
Authorities
- Innovation, Science and Economic Development
-
Assessment Type
Project on federal lands -
Reference Number
83321
Nearby assessments
...within 200 kilometres-
Keeseekoowenin Ojibway First Nation - Water Treatment Plant and Upgraded Lagoon
Keeseekoowenin Ojibway First Nation -
South Lake Prescribed Fire
Riding Mountain National Park of Canada -
Jackfish Creek Bison Pasture Expansion
Riding Mountain National Park -
Extension of Bison Enclosure South onto Plains Rough Fescue Grassland Restoration Area
Riding Mountain National Park -
Ominnik Marsh Trail Accessibility Reroute
Riding Mountain National Park -
Smallmouth Bass Project
Riding Mountain National Park -
Rolling River First Nation - Construction of Three Bridges
Rolling River Reserve 67 -
Ominnik Marsh Trail Anchor System & Boardwalk Replacement
Riding Mountain National Park of Canada -
Westman Communications Fiber Optic Cable
Riding Mountain National Park -
Tiger Salamander Crossing
Riding Mountain National Park -
Research, Monitoring and Management of Invasive Smallmouth Bass in Clear Lake, Riding Mountain National Park
Riding Mountain National Park -
New Cabin 56-4th St. S. Clear Lake Cabin Area
Riding Mountain National Park of Canada -
Westman Communications Fiber - Phase 2 - Clear Lake Cabin Area
Riding Mountain National Park of Canada -
Management of Zebra Mussels in Clear Lake in Riding Mountain National Park
Riding Mountain National Park of Canada -
Northeast end of Clear Lake Cabin area storm water catch basin, drainage pipe and dissipation pool
Riding Mountain National Park -
Seech-Hopper 3 Prescribed Fire
Riding Mountain National Park of Canada -
New Resort Development - 116 TaWaPit Drive, Wasagaming
Riding Mountain National Park -
Clear Lake Pier Repairs
Riding Mountain National Park of Canada -
Lakeshore Trail Re-design
Riding Mountain National Park of Canada -
Mooswa East Water Line
Riding Mountain National Park -
Westman Communications Fibre Optic throughout Wasagaming
Riding Mountain National Park of Canada -
Hydro - North Shore Line Project
Riding Mountain National Park of Canada -
New Fibre Installation
Riding Mountain National Park -
Jackfish Creek Prescribed Fire
Riding Mountain National Park of Canada -
Wasagaming Wildfire Risk Reduction 2023-2026
Riding Mountain National Park -
North Shore Hydro Distribution Line Rebuild
Riding Mountain National Park of Canada -
Clear Lake Golf Course Clubhouse Patio
Riding Mountain National Park of Canada -
Grey Owl Parking Lot Privy and Reroute
Riding Mountain National Park -
Baldy Prescribed Fire
Riding Mountain National Park of Canada -
Highway 19 Urgent Maintenance, Ditch Development and Culvert Replacements
Riding Mountain National Park of Canada -
Menzies Prescribed Fire
Riding Mountain National Park of Canada -
Highway 19 Roadway Rehabilitation Addendum 2 Swanson Creek Culvert
Riding Mountain National Park -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Southeast -
MB Hydro Pole and Arm Replacement
Riding Mountain National Park of Canada -
Utility Service Agreement BELL MTS Inc. Moon Lake Telecommunications Tower
Riding Mountain National Park -
Waywayseecappo First Nation - School Water Treatment Plant Recovery
Waywayseecappo First Nation -
Waywayseecappo - New Water Treatment Plant - 2324
Waywayseecappo WTP -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Northeast -
Escarpment Trailhead Sign Replacement and New vault Privy
Riding Mountain National Park -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Southwest -
Waywayseecappo First Nation - Water Treatment Plant
Waywayseecappo First Nation -
Boreal Trail Reconstruction
Riding Mountain National Park of Canada -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Northwest -
Clear Lake Cabin Area Kayak Launch Site
Riding Mountain National Park -
New Staff Campground for Riding Mountain National Park
Riding Mountain National Park -
Pope National Wildlife Area Spillway Replacement Project
Pope National Wildlife Area -
Pope National Wildlife Area Water Control Structure Renaturalization Project
Pope National Wildlife Area -
Edwards Creek Trail Upgrade Proposal
Riding Mountain National Park of Canada -
East Trails Project - East Gate
Riding Mountain National Park -
PARKS CANADA AGENCY - Riding Mountain National Park (West Side) Addition of New Site Known as Tower Hill
PARKS CANADA AGENCY - Riding Mountain National Park (West Side) -
Tower Hill VHF Tower
Riding Mountain National Park -
Birdtail Sioux Dakota Nation Prevention Centre for the Delivery of FNCFS
Birdtail Sioux Dakota Nation -
Pine Creek and Ebb and Flow - Anishinaabe Aki Petro-Can Gas Bar in Dauphin, MB - 2425
Dauphin -
Birdtail Sioux First Nation Aerated Lagoon Project
Birdtail Lagoon First Nation -
Erosion Control on Hales Creek within the Lake Winnipeg Basin with Sioux Valley Dakota Nation
Sioux Valley Dakota Nation -
Water Retention within the Lake Winnipeg Basin with Sioux Valley Dakota Nation
Sioux Valley Dakota Nation -
Waywayseecappo First Nation Elton Property Gas Bar
Waywayseecappo First Nation -
PADCOM Potash Solution Mining Project
16 kilometres west of Russell -
Energy East Project
Moosomin -
Tootinaowaziibeeng - CHRT 41 - Jordan's Principle - Multiple Buildings - 2324
Tootinaowaziibeeng - CHRT 41 - Jordan's Principle - Multiple Buildings - 2324 -
Tootinaowaziibeeng - CHRT 41 - Wellness Centre
Tootinaowaziibeeng -
Larkhill Avenue Reconstruction - Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Area A Security Fence - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Railway Crossings Upgrade - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Aldershot Road Reconstruction - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Reconstruction of Rifle Range 2 - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Construction of Land Vehicle Crew Training System Building - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
N132 Petroleum, Oils and Lubricants (POL) Revitalization - Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Ortona Road Fireguard Expansion - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Building Construction - Canadian Forces Base Shilo
Canadian Forces Base - Shilo -
Royal Avenue Reconstruction - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Housing Renovations (HAYSL80) - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Construct Transition Centre - Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Installation of Running Trail - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Construction of Land Vehicle Crew Training System Building
Canadian Forces Base/Area Support Unit Shilo -
Construction of New Supply Well- Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Base Refueling Point Tank Replacement
CFB/ASU Shilo -
Demolition of Unnamed Building at Waggle Springs - Canadian Forces Base Shilo
Waggle Springs -
Xplornet Inc. Radiocommunication Antenna Addition on Ebb and Flow First Nation Reserve No. 280
Ebb and Flow First Nation Reserve No. 280 -
CSC97 - Ebb and Flow First Nation Water Supply Line Project
Ebb and Flow First Nation -
Ebb and Flow First Nation - Road and Drainage Upgrades
Ebb and Flow First Nation -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Cromer -
New Fibre Installation - RFNOW
Project site 1: CA12:CARBS-SLFN-23 -
Sandy Bay First Nation CFS Prevention Center Temporary Facilities (10 RTMs)
Sandy Bay First Nation -
New Fibre Installation - Sandy Bay
Project site: Sandy Bay -
Sandy Bay First Nation New Water Treatment Plant
Sandy Bay First Nation -
Saskatchewan Agriculture Drainage Network - Blackbird Creek Drainage Network Project
50 kilometres east of Yorkton, Saskatchewan -
Keeseekoose - Agricultural Permit - K. Martenuik
Keeseekoose - Agricultural Permit - K. Marteniuk -
Launch Ramp Reconstruction - Mossey River, MB - Fall 2021
Mossey River Harbour -
New Broadband Communications North Inc. Telecommunication Tower at Lake Manitoba First Nation on Dog Creek Reserve No. 46
Lake Manitoba First Nation, MB -
New Fibre Installation
Project site: Various parts of Manitoba -
Cote First Nation Solid Waste Transfer Station
Cote IR 64 -
Lake Manitoba First Nation - CHRT41 FNCFS Prevention Centre
Lake Manitoba First Nation -
O-Chi-Chak-Ko-Sipi First Nation Water Treatment Plant Upgrades
O-Chi-Chak-Ko-Sipi First Nation Water Treatment Plant Upgrades -
Lake Manitoba - South Access Road Upgrades - 2324
Lake Manitoba -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Active Transportation for Ochapowace First Nation
Active Transportation for Ochapowace First Nation -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel inlet in Lake Manitoba -
New Fibre Installation
Project Site 5: Ochapowace -
Ochapowace Nation Water Treatment Plant Upgrades
Ochapowace Nation -
Ochapowace Nation Subdivision - Phase I
Ochapowace Nation -
Dakota Women's Lodge (Winyan Tipi)
Portage la Prairie -
Long Plain - CHRT41 - Prevention Centre - P055810 - 2324
Long Plain First Nation -
Long Plain School Renovation & Addition
Long Plain First Nation -
Long Plain First Nation - Water Treatment Plant Upgrades
Long Plain First Nation -
Long Plain FN - Directional Drilling - Water and Sewer Pipeline
Long Plain First Nation -
Zagime Anishinabek First Nation - Section 95 housing project
Sakimay 74-5 -
Dakota Tipi First Nation - New Jordan's Principle Facility
Dakota Tipi First Nation -
Zagime Anishinabek Solid Waste Transfer Station
Sakimay IR 74 -
Kahkewistahaw First Nation Subdivision Development (Phase 23)
Kahkewistahaw IR 72 -
Kahkewistahaw First Nation Water Treatment Plant Upgrade
Kahkewistahaw First Nation -
New Fibre Installation
Project Site 4: Kahkewistahaw -
Kahkewistahaw First Nation Green Links and Teaching Garden: Connecting Elders and Youth
Kahkewistahaw First Nation -
Kahkewistahaw First Nation Operations & Maintenance Building and Fire Hall
Kahkewistahaw First Nation -
Kahkewistahaw First Nation Lagoon Upgrade
Kahkewistahaw IR 72 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-29-20-04-2
Cowessess First Nation -
Kahkewistahaw First Nation Solid Waste Transfer Station
Kahkewistahaw IR 72 -
Zagime Community Center
Zagime IR #74-3 -
Saskatchewan Agriculture Drainage Network - 600 Creek Drainage Network Project
20 kilometers southeast of Storthoaks -
Key Junction Gas Bar & Confectionery
The Key First Nation -
Skownan First Nation Waste Site Closure and Eco-Depot Facility
Skownan First Nation -
Cowessess - Agricultural Permit G. Lerat
Cowessess Indian Reserve 73 -
White Bear First Nation Solid Waste Transfer Station Project
White Bear First Nation -
Pinaymootang First Nation Water Treatment Upgrades
Pinaymootang First Nation -
Pine Creek First Nation - New Access Road (Phase 1 Road and School Area Road)
Road A - Phase I Road -
New Fibre Installation - Central and Southeastern SK
Project site 1: Cote 64 -
Swan Lake First Nation Youth & Prevention Centre
Swan Lake First Nation -
Skownan New Child and Family Services Prevention Building
Skownan First Nation -
White Bear First Nation Community Spray Park
White Bear 70 -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel outlet on Lake St. Martin -
Cote First Nation Main Landfill Decommissioning
Cote IR 64 -
Cote First Nation #64 - Landfill decommissioning at the Main Landfill Site
Badgerville -
Cowessess First Nation Solid Waste Transfer Station
Cowessess First Nation -
Cote First Nation Wood Treatment Remediation Project
Cote IR 64 -
New Fibre Installation
Project Site 1: White Bear -
New Fibre Installation - Central and Southeastern SK
Project site 6: COTE I.R. 64 -
Walkway to support healthy lifestyle for Cote First Nation
Bagerville -
Upgrade Single Tower & New Fibre Installation
Project Site 2: Central East region -Badgerville -
New Fibre Installation
Project Site 2: Cowessess -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation
Cowessess First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SE-08-19a-05-2
Cowessess First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NW-23-14-05-2
Cowessess First Nation -
Crooked Lake Outlet Structure Replacement
Crooked Lake - SW-08-19A-05 W2M -
Vehicle and Equipment Management Agency Radio Services Radiocommunication Antenna Addition on Pine Creek First Nation Reserve No. 66A
Pine Creek First Nation, MB -
New Broadband Communications North Inc. Telecommunication Tower on Pine Creek First Nation Reserve No. 66A
Pine Creek First Nation, MB -
White Bear First Nation Wastewater Upgrade Project
White Bear First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NE-06-17-05-02
Cowessess First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-09-15-05-2
Cowessess First Nation -
Pine Creek First Nation - New Access Road (Phase 1 Road and School Area Road)
Road B - School Area Road -
Keeseekoose Education Center Drainage
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-06-17-05-2
Cowessess First Nation -
Yorkton Tribal Council Child & Family Services Office Building
Kahkewistahaw IR 92 A-1 -
Keeseekoose - Agricultural Permit - S. Marsh
Keeseekoose - Agricultural Permit - S. Marsh -
Boissevaine Port of Entry: Paving Replacement
Boissevain Port of Entry -
Keeseekoose Multi-Purpose Health facility
Keeseekoose IR 66 -
New Fibre Installation - Central and Southeastern SK
Project site 10: KEESEEKOOSE I.R. 66 -
Zagime Anishinabek Youth Safe House
Shesheep Indian Reserve No. 74A -
Blanket Permit - SaskEnergy - Gasification of Sakimay
Sakimay -
Bekevar Wind Energy Project
Cowessess IR No. 73A -
Basadinaa - Crooked Lake Cottage Lots Head Lease #5- Zagime Anishinabek First Nation
Shesheep IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #4- Zagime Anishinabek First Nation
Shesheep IR 74A -
Basadinaa - Crooked Lake Cottage Lots Head Lease #4- Zagime Anishinabek First Nation
Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots
Shesheep IR 74A & Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #5- Zagime Anishinabek First Nation
Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #3- Zagime Anishinabek First Nation
Sakimay IR 74, Shesheep IR 74A -
Zagime Anishinabëk Gasification
Zagime Anishinabëk Indian Reserves 74, 74-2, 74-9, 74-12, 74-16, 74-17 and Shesheep IR 74A -
Little Saskatchewan First Nation - Mino-Aya-Win Centre
Little Saskatchewan First Nation -
Zagime Anishinabek Youth Centre
Sakimay Indian Reserve No. 74 -
New Fibre Installation
Project Site 3: Zagime Anishinabek -
Zagime Anishinabek Water Treatment Plant and Sewage Pumping Station Upgrade
Zagime Anishinabek First Nations -
Zagime Anishinabek School
Sakimay IR 74 -
Lena Port of Entry Redevelopment
Lena Port of Entry -
Zagime Anishinabek New Subdivision Project
Zagime Anishinabek -
Keeseekoose First Nation Well Completions
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Keeseekoose Road to Community Wells
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Zagime Greenhouse
Zagime IR #74-9 / IR #74-2 -
Xplornet Communications Inc. Telecommunication Tower at Canada Border Services Agency - Cartwright Port of Entry, MB
Cartwright, MB -
Cartwright Port of Entry Redevelopment
Cartwright Port of Entry -
New Fibre Installation - Dauphin River
Project site 2: Obushkudayang Indian Reserve -
Vertical Farming and Sustainable Grazing for Food Security and Innovation
near Grenfell -
The Key First Nation Lagoon Upgrade Project
The Key First Nation -
The Key First Nation Firehall
The Key First Nation -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA BAND I.R. 68 (Site #2) -
Lake St. Martin - Water Treatment Plant Zebra Mussels Control
Lake St. Martin -
Vehicle and Equipment Management Agency Radiocommunication Antenna Addition in Manitou, MB
Manitou -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA BAND I.R. 68 (Site #1) -
Pheasant Rump Lagoon Expansion
Pheasant Rump Nakota IR 68D -
WireIE (Canada) Inc. - Radiocommunication Tower - Carievale Border Crossing, Hwy 8, Carievale SK
Carievale Border Crossing -
Pheasant Rump Nakota IR 68D Gasification Project
Pheasant Rump Nakota IR 68D -
Pheasant Rump Nakota Nation Subdivision Expansion
SW 19-08-005 W2M -
Cultural Centre for Women, Girls and Two Spirited Band Members
Kisbey -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA INDIAN RESERVE NO. 68D (Site #3) -
Pheasant Rump Nakota First Nation - Cultural Centre
Pheasant Rump Nakota First Nation - Cultural Centre -
Pheasant Rump Nakota Nation Solid Waste Transfer Station
Pheasant Rump IR 68 -
Saskatchewan Agriculture Drainage Network - Vipond Drainage Network Project
6 kilometres east of Glenavon