The proposed location for the new WTP is in Waywayseecappo First Nation, Manitoba, approximately 3.7 km south of Provincial Road 45 at approximate UTM Coordinates 14 U 5617604 m N, 365349 m E.
The Site is within the Hamiota Ecodistrict in the Aspen Parkland Ecoregion of Manitoba (Smith et al., 1998). Soils in this ecodistrict are dominantly organic-rich soils derived from glacial till (Smith et al., 1998). Typical vegetation in the ecodistrict includes slough grass (pasture grass, grama grass, sage grass, spear grass), sedges and rushes, willow, and trembling aspen, along with shrubs such as prairie rose, silverberry and snowberry. (Smith et al., 1998). This ecoregion contains habitat for white-tailed deer, coyote, red fox, ground squirrel, cottontail rabbit, redback vole, and deer mice. (Smith et al., 1998).
The Site consists of land to accommodate a new WTP, truck garage, new raw water pumphouse and raw water intake structure/ intake line, a process waste structure/line, and watermain connection to the existing school (Appendix A, Figure 1-1 &1-2). New WTP Building, Truck Garage and Watermain The location for the new WTP (the Site) is an undeveloped, unoccupied, grassy area with low-lying marsh approximately 30 m to the east, an occupied residential house approximately 80 m north, and a gravel community road and right of way approximately 200 m east (Appendix B, Photo ID 1 &2). The Site will also include a detached, 6-bay truck garage located approximately 32 m north of the proposed WTP building. A proposed watermain will run along the existing community road right of ways from the WTP location approximately 200 m east, 1.4 km south,1.6 km east, and 400 m south to provide potable water to the existing community school. Raw Water Intake and Pumphouse The location of the raw water pumphouse is on the shore of Berney Lake on undisturbed land at approximate UTM coordinates 14U 5616806 m N 363941 m E. The location for the pumphouse and the alignment for the intake line was largely cleared for geotechnical investigations and is surrounded by undisturbed forest consisting primarily of trembling aspen, white birch and poplar (Appendix B, Photo ID 3 and 4). The proposed raw water intake line runs from Berney Lake approximately 1.6 km northeast to the new WTP, going through the recently cleared right of way in the forested area and through agricultural cropland (Appendix A, Figure 1-1). Process Waste Line and Concentrate Holding Pond For the new WTP, a process waste line will run below ground at a depth of approximately 2.4 m from the new WTP building approximately 500 m westward through the agricultural cropland to a proposed concentrate holding pond at approximate UTM coordinates 14 U 5617391 m N 364841 m E, where it will be discharged seasonally via a concentrate discharge line running approximately 260 m north to an unnamed tributary creek to the Birdtail River.
List of all Easements and Rights of Way Affecting Properties: A gravel community road, overhead powerline, and right-of-way are located approximately 200 m east of the new WTP location. A potable water line is proposed to run from the new WTP to the existing community school, along the existing gravel road right of way.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | April 2, 2024 |
Contacts
Tebesi MosalaIndigenous Services Canada
Tebesi Mosala, Senior Environmental Specialist
200-365 Hargrave Street
Winnipeg, Manitoba R3C 4H4
Telephone: 204-984-0711
Fax: 204-983-2936
Email: tebesi.mosala@canada.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Waywayseecappo WTP (Manitoba)
-
Nature of Activity
- Water Management
-
Assessment Status
In progress -
Start Date
2024-04-02 -
Proponent
Waywayseecappo First Nation -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
88462
Nearby assessments
...within 200 kilometres-
Waywayseecappo First Nation - School Water Treatment Plant Recovery
Waywayseecappo First Nation -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Northeast -
Waywayseecappo First Nation - Water Treatment Plant
Waywayseecappo First Nation -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Northwest -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Southwest -
New Telecommunication Towers on the Waywayseecappo First Nation Reserve
Waywayseecappo First Nation Southeast -
Baldy Prescribed Fire
Riding Mountain National Park of Canada -
PARKS CANADA AGENCY - Riding Mountain National Park (West Side) Addition of New Site Known as Tower Hill
PARKS CANADA AGENCY - Riding Mountain National Park (West Side) -
Tower Hill VHF Tower
Riding Mountain National Park -
Menzies Prescribed Fire
Riding Mountain National Park of Canada -
PADCOM Potash Solution Mining Project
16 kilometres west of Russell -
Seech-Hopper 3 Prescribed Fire
Riding Mountain National Park of Canada -
Keeseekoowenin Ojibway First Nation - Water Treatment Plant and Upgraded Lagoon
Keeseekoowenin Ojibway First Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Keeseekoowenin First Nation (Indian Reserve 61) Project site 2 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Keeseekoowenin First Nation (Indian Reserve 61) Project site 1 -
Jackfish Creek Bison Pasture Expansion
Riding Mountain National Park -
Extension of Bison Enclosure South onto Plains Rough Fescue Grassland Restoration Area
Riding Mountain National Park -
Jackfish Creek Prescribed Fire
Riding Mountain National Park of Canada -
Birdtail Sioux Dakota Nation Prevention Centre for the Delivery of FNCFS
Birdtail Sioux Dakota Nation -
Birdtail Sioux First Nation Aerated Lagoon Project
Birdtail Lagoon First Nation -
Tootinaowaziibeeng - CHRT 41 - Jordan's Principle - Multiple Buildings - 2324
Tootinaowaziibeeng - CHRT 41 - Jordan's Principle - Multiple Buildings - 2324 -
Tootinaowaziibeeng - CHRT 41 - Wellness Centre
Tootinaowaziibeeng -
Smallmouth Bass Project
Riding Mountain National Park -
South Lake Prescribed Fire
Riding Mountain National Park of Canada -
Utility Service Agreement BELL MTS Inc. Moon Lake Telecommunications Tower
Riding Mountain National Park -
MB Hydro Pole and Arm Replacement
Riding Mountain National Park of Canada -
Ominnik Marsh Trail Accessibility Reroute
Riding Mountain National Park -
Research, Monitoring and Management of Invasive Smallmouth Bass in Clear Lake, Riding Mountain National Park
Riding Mountain National Park -
Management of Zebra Mussels in Clear Lake in Riding Mountain National Park
Riding Mountain National Park of Canada -
Ominnik Marsh Trail Anchor System & Boardwalk Replacement
Riding Mountain National Park of Canada -
New Cabin 56-4th St. S. Clear Lake Cabin Area
Riding Mountain National Park of Canada -
Northeast end of Clear Lake Cabin area storm water catch basin, drainage pipe and dissipation pool
Riding Mountain National Park -
Westman Communications Fiber - Phase 2 - Clear Lake Cabin Area
Riding Mountain National Park of Canada -
Tiger Salamander Crossing
Riding Mountain National Park -
Westman Communications Fiber Optic Cable
Riding Mountain National Park -
Clear Lake Pier Repairs
Riding Mountain National Park of Canada -
New Resort Development - 116 TaWaPit Drive, Wasagaming
Riding Mountain National Park -
Lakeshore Trail Re-design
Riding Mountain National Park of Canada -
Energy East Project
Moosomin -
Mooswa East Water Line
Riding Mountain National Park -
Westman Communications Fibre Optic throughout Wasagaming
Riding Mountain National Park of Canada -
Hydro - North Shore Line Project
Riding Mountain National Park of Canada -
Boreal Trail Reconstruction
Riding Mountain National Park of Canada -
Pope National Wildlife Area Water Control Structure Renaturalization Project
Pope National Wildlife Area -
Pope National Wildlife Area Spillway Replacement Project
Pope National Wildlife Area -
New Fibre Installation
Riding Mountain National Park -
Edwards Creek Trail Upgrade Proposal
Riding Mountain National Park of Canada -
Wasagaming Wildfire Risk Reduction 2023-2026
Riding Mountain National Park -
Clear Lake Golf Course Clubhouse Patio
Riding Mountain National Park of Canada -
North Shore Hydro Distribution Line Rebuild
Riding Mountain National Park of Canada -
Grey Owl Parking Lot Privy and Reroute
Riding Mountain National Park -
Saskatchewan Agriculture Drainage Network - Blackbird Creek Drainage Network Project
50 kilometres east of Yorkton, Saskatchewan -
Rolling River First Nation - Construction of Three Bridges
Rolling River Reserve 67 -
Keeseekoose - Agricultural Permit - K. Martenuik
Keeseekoose - Agricultural Permit - K. Marteniuk -
Highway 19 Urgent Maintenance, Ditch Development and Culvert Replacements
Riding Mountain National Park of Canada -
Pine Creek and Ebb and Flow - Anishinaabe Aki Petro-Can Gas Bar in Dauphin, MB - 2425
Dauphin -
Highway 19 Roadway Rehabilitation Addendum 2 Swanson Creek Culvert
Riding Mountain National Park -
Cote First Nation Solid Waste Transfer Station
Cote IR 64 -
Escarpment Trailhead Sign Replacement and New vault Privy
Riding Mountain National Park -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
East Trails Project - East Gate
Riding Mountain National Park -
Water Retention within the Lake Winnipeg Basin with Sioux Valley Dakota Nation
Sioux Valley Dakota Nation -
Erosion Control on Hales Creek within the Lake Winnipeg Basin with Sioux Valley Dakota Nation
Sioux Valley Dakota Nation -
Saskatchewan Agriculture Drainage Network - Atwater Drainage Network Project
60 kilometres southeast of Yorkton -
Clear Lake Cabin Area Kayak Launch Site
Riding Mountain National Park -
New Staff Campground for Riding Mountain National Park
Riding Mountain National Park -
Active Transportation for Ochapowace First Nation
Active Transportation for Ochapowace First Nation -
Zagime Anishinabek First Nation - Section 95 housing project
Sakimay 74-5 -
Ochapowace Nation Water Treatment Plant Upgrades
Ochapowace Nation -
New Fibre Installation
Project Site 5: Ochapowace -
Ochapowace Nation Subdivision - Phase I
Ochapowace Nation -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Cromer -
Waywayseecappo First Nation Elton Property Gas Bar
Waywayseecappo First Nation -
Zagime Community Center
Zagime IR #74-3 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-29-20-04-2
Cowessess First Nation -
Kahkewistahaw First Nation Subdivision Development (Phase 23)
Kahkewistahaw IR 72 -
Kahkewistahaw First Nation Water Treatment Plant Upgrade
Kahkewistahaw First Nation -
New Fibre Installation
Project Site 4: Kahkewistahaw -
Kahkewistahaw First Nation Green Links and Teaching Garden: Connecting Elders and Youth
Kahkewistahaw First Nation -
Kahkewistahaw First Nation Operations & Maintenance Building and Fire Hall
Kahkewistahaw First Nation -
Kahkewistahaw First Nation Lagoon Upgrade
Kahkewistahaw IR 72 -
Zagime Anishinabek Solid Waste Transfer Station
Sakimay IR 74 -
Key Junction Gas Bar & Confectionery
The Key First Nation -
Kahkewistahaw First Nation Solid Waste Transfer Station
Kahkewistahaw IR 72 -
Cowessess - Agricultural Permit G. Lerat
Cowessess Indian Reserve 73 -
New Fibre Installation - Central and Southeastern SK
Project site 1: Cote 64 -
Cote First Nation Main Landfill Decommissioning
Cote IR 64 -
Cowessess First Nation Solid Waste Transfer Station
Cowessess First Nation -
Cote First Nation #64 - Landfill decommissioning at the Main Landfill Site
Badgerville -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SE-08-19a-05-2
Cowessess First Nation -
Crooked Lake Outlet Structure Replacement
Crooked Lake - SW-08-19A-05 W2M -
Yorkton Tribal Council Child & Family Services Office Building
Kahkewistahaw IR 92 A-1 -
Cote First Nation Wood Treatment Remediation Project
Cote IR 64 -
New Fibre Installation
Project Site 2: Cowessess -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation
Cowessess First Nation -
New Fibre Installation - Central and Southeastern SK
Project site 6: COTE I.R. 64 -
Walkway to support healthy lifestyle for Cote First Nation
Bagerville -
Launch Ramp Reconstruction - Mossey River, MB - Fall 2021
Mossey River Harbour -
Upgrade Single Tower & New Fibre Installation
Project Site 2: Central East region -Badgerville -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NE-06-17-05-02
Cowessess First Nation -
Keeseekoose Education Center Drainage
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-06-17-05-2
Cowessess First Nation -
Zagime Anishinabek Youth Safe House
Shesheep Indian Reserve No. 74A -
Basadinaa - Crooked Lake Cottage Lots Head Lease #3- Zagime Anishinabek First Nation
Sakimay IR 74, Shesheep IR 74A -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NW-23-14-05-2
Cowessess First Nation -
Basadinaa - Crooked Lake Cottage Lots Head Lease #5- Zagime Anishinabek First Nation
Shesheep IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #5- Zagime Anishinabek First Nation
Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #4- Zagime Anishinabek First Nation
Shesheep IR 74A -
Basadinaa - Crooked Lake Cottage Lots
Shesheep IR 74A & Sakimay IR 74 -
Basadinaa - Crooked Lake Cottage Lots Head Lease #4- Zagime Anishinabek First Nation
Sakimay IR 74 -
Keeseekoose - Agricultural Permit - S. Marsh
Keeseekoose - Agricultural Permit - S. Marsh -
Blanket Permit - SaskEnergy - Gasification of Sakimay
Sakimay -
Zagime Anishinabëk Gasification
Zagime Anishinabëk Indian Reserves 74, 74-2, 74-9, 74-12, 74-16, 74-17 and Shesheep IR 74A -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-09-15-05-2
Cowessess First Nation -
Keeseekoose Multi-Purpose Health facility
Keeseekoose IR 66 -
New Fibre Installation - Central and Southeastern SK
Project site 10: KEESEEKOOSE I.R. 66 -
Installation of Running Trail - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Construct Transition Centre - Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Housing Renovations (HAYSL80) - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Construction of Land Vehicle Crew Training System Building
Canadian Forces Base/Area Support Unit Shilo -
Construction of New Supply Well- Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Demolition of Unnamed Building at Waggle Springs - Canadian Forces Base Shilo
Waggle Springs -
Area A Security Fence - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Royal Avenue Reconstruction - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Aldershot Road Reconstruction - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Ortona Road Fireguard Expansion - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Railway Crossings Upgrade - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Construction of Land Vehicle Crew Training System Building - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Building Construction - Canadian Forces Base Shilo
Canadian Forces Base - Shilo -
Larkhill Avenue Reconstruction - Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
N132 Petroleum, Oils and Lubricants (POL) Revitalization - Canadian Forces Base (CFB) Shilo
Canadian Forces Base (CFB) Shilo -
Reconstruction of Rifle Range 2 - Canadian Forces Base Shilo
Canadian Forces Base Shilo -
Zagime Anishinabek Youth Centre
Sakimay Indian Reserve No. 74 -
Base Refueling Point Tank Replacement
CFB/ASU Shilo -
New Fibre Installation
Project Site 3: Zagime Anishinabek -
Zagime Anishinabek Water Treatment Plant and Sewage Pumping Station Upgrade
Zagime Anishinabek First Nations -
Zagime Anishinabek School
Sakimay IR 74 -
Zagime Anishinabek New Subdivision Project
Zagime Anishinabek -
CSC97 - Ebb and Flow First Nation Water Supply Line Project
Ebb and Flow First Nation -
Xplornet Inc. Radiocommunication Antenna Addition on Ebb and Flow First Nation Reserve No. 280
Ebb and Flow First Nation Reserve No. 280 -
Zagime Greenhouse
Zagime IR #74-9 / IR #74-2 -
Ebb and Flow First Nation - Road and Drainage Upgrades
Ebb and Flow First Nation -
Keeseekoose First Nation Well Completions
KEESEEKOOSE INDIAN RESERVE NO. 66 -
Keeseekoose Road to Community Wells
KEESEEKOOSE INDIAN RESERVE NO. 66 -
White Bear First Nation Solid Waste Transfer Station Project
White Bear First Nation -
Bekevar Wind Energy Project
Cowessess IR No. 73A -
White Bear First Nation Community Spray Park
White Bear 70 -
New Fibre Installation
Project Site 1: White Bear -
White Bear First Nation Wastewater Upgrade Project
White Bear First Nation -
Vertical Farming and Sustainable Grazing for Food Security and Innovation
near Grenfell -
The Key First Nation Lagoon Upgrade Project
The Key First Nation -
O-Chi-Chak-Ko-Sipi First Nation Water Treatment Plant Upgrades
O-Chi-Chak-Ko-Sipi First Nation Water Treatment Plant Upgrades -
The Key First Nation Firehall
The Key First Nation -
Pine Creek First Nation - New Access Road (Phase 1 Road and School Area Road)
Road A - Phase I Road -
New Fibre Installation - RFNOW
Project site 1: CA12:CARBS-SLFN-23 -
SaskPower Rural Rebuild - 2D-41 Birmingham Southwest
Star Blanket Indian Reserve No. 83-D -
Sandy Bay First Nation CFS Prevention Center Temporary Facilities (10 RTMs)
Sandy Bay First Nation -
Vehicle and Equipment Management Agency Radio Services Radiocommunication Antenna Addition on Pine Creek First Nation Reserve No. 66A
Pine Creek First Nation, MB -
New Broadband Communications North Inc. Telecommunication Tower on Pine Creek First Nation Reserve No. 66A
Pine Creek First Nation, MB -
New Fibre Installation - Sandy Bay
Project site: Sandy Bay -
Sandy Bay First Nation New Water Treatment Plant
Sandy Bay First Nation -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA BAND I.R. 68 (Site #2) -
Pine Creek First Nation - New Access Road (Phase 1 Road and School Area Road)
Road B - School Area Road -
Saskatchewan Agriculture Drainage Network - 600 Creek Drainage Network Project
20 kilometers southeast of Storthoaks -
Saskatchewan Agriculture Drainage Network - Vipond Drainage Network Project
6 kilometres east of Glenavon -
New Broadband Communications North Inc. Telecommunication Tower at Lake Manitoba First Nation on Dog Creek Reserve No. 46
Lake Manitoba First Nation, MB -
New Fibre Installation
Project site: Various parts of Manitoba -
Skownan First Nation Waste Site Closure and Eco-Depot Facility
Skownan First Nation -
Lake Manitoba First Nation - CHRT41 FNCFS Prevention Centre
Lake Manitoba First Nation -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA BAND I.R. 68 (Site #1) -
Skownan New Child and Family Services Prevention Building
Skownan First Nation -
Peepeekisis Community Centre Gas Bar
Peepeekisis IR #81 -
Ocean Man First Nation 1 MW Solar Project
Ocean Man IR 69I -
Pheasant Rump Lagoon Expansion
Pheasant Rump Nakota IR 68D -
Pheasant Rump Nakota IR 68D Gasification Project
Pheasant Rump Nakota IR 68D -
Cultural Centre for Women, Girls and Two Spirited Band Members
Kisbey -
Pheasant Rump Nakota Nation Subdivision Expansion
SW 19-08-005 W2M -
New (Multiple) Tower Construction
PHEASANT RUMP NAKOTA INDIAN RESERVE NO. 68D (Site #3) -
Pheasant Rump Nakota First Nation - Cultural Centre
Pheasant Rump Nakota First Nation - Cultural Centre -
Lake Manitoba - South Access Road Upgrades - 2324
Lake Manitoba -
Peepeekisis Cree Nation Youth Impact Centre
Peepeekisis Cree Nation -
Ocean Man Indian Reserve 69 Well Pad FS-2023
Ocean Man Indian Reserve 69 -
Ocean Man Indian Reserve 69E Pipeline4
Ocean Man Indian Reserve 69E -
Ocean Man Indian Reserve 69E Pipeline2
Ocean Man Indian Reserve 69E -
Ocean Man Indian Reserve 69E Pipeline3
Ocean Man Indian Reserve 69E -
Ocean Man Indian Reserve 69E Well pad
Ocean Man Indian Reserve 69E -
Peepeekisis Community Centre
Peepeekisis IR #81 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NE-32-17-10-2
Cowessess First Nation -
Okanese First Nation Head Start Building Construction
Okanese First Nation -
Okanese Cree Nation - Water Treatment Plant Upgrade
Okanese IR 82 -
Okanese Lagoon Access Road Upgrades
Okanese First Nation -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel inlet in Lake Manitoba -
Peepeekisis Cree Nation Community Lagoon Improvements
PEEPEEKISIS INDIAN RESERVE NO. 81 -
Blanket Permit - SaskEnergy - Gasification of Okanese Indian Reserve No. 82
Okanese First Nation -
SaskPower's Power Generation - Ocean Man Solar Interconnect
Ocean Man IR 69I -
Ocean Man Indian Reserve 69E Well pad2
Ocean Man Indian Reserve 69E -
Little Black Bear First Nation Water Treatment Plant Upgrades
LITTLE BLACK BEAR INDIAN RESERVE NO. 84 -
Ocean Man First Nation Headstart and Daycare
Ocean Man Indian Reserve No. 69 -
Peepeekisis Cree Nation Youth Safe House
PEEPEEKISIS INDIAN RESERVE NO. 81 -
Peepeekisis Cree Nation Road Construction
PEEPEEKISIS INDIAN RESERVE NO. 81 -
Pheasant Rump Nakota Nation Solid Waste Transfer Station
Pheasant Rump IR 68 -
Star Blanket Water Treatment Plant Upgrades
Star Blanket First Nation -
Carry The Kettle First Nation Solid Waste Transfer Station
Assiniboine IR 76 -
Pinaymootang First Nation Water Treatment Upgrades
Pinaymootang First Nation -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-23-12-10-2
Cowessess First Nation -
Carry The Kettle First Nation Lagoon Expansion
Assiniboine IR 76 -
Carry the Kettle First Nation - Nakota Junction Gas Station
Assiniboine IR 76 -
Blanket Permit - SaskEnergy - Gasification of Assiniboine Indian Reserve No. 76
Assiniboine Reserve No. 76 -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation NW-16-12-10-2
Cowessess First Nation -
Lake Manitoba and Lake St. Martin Outlet Channels Project
Lake Manitoba Outlet Channel outlet on Lake St. Martin -
Restoring Wetlands Within the Lake Winnipeg Basin with Cowessess First Nation SW-18-12-10-2
Cowessess First Nation -
Kawacatoose First Nation Road Repair Project
Kawacatoose First Nation -
Meadow Lake Tribal Council: Solar Project
NE¼-31-09-09 W2M -
WireIE (Canada) Inc. - Radiocommunication Tower - Carievale Border Crossing, Hwy 8, Carievale SK
Carievale Border Crossing -
Dakota Women's Lodge (Winyan Tipi)
Portage la Prairie -
Little Saskatchewan First Nation - Mino-Aya-Win Centre
Little Saskatchewan First Nation -
Long Plain - CHRT41 - Prevention Centre - P055810 - 2324
Long Plain First Nation -
Long Plain School Renovation & Addition
Long Plain First Nation -
Boissevaine Port of Entry: Paving Replacement
Boissevain Port of Entry -
Long Plain First Nation - Water Treatment Plant Upgrades
Long Plain First Nation -
Long Plain FN - Directional Drilling - Water and Sewer Pipeline
Long Plain First Nation -
Mahikan Housing Development
Wuskwi Sipihk First Nation