In support of the new Impact Assessment Act, the Impact Assessment Agency of Canada has redesigned and implemented a new Canadian Impact Assessment Registry. Learn more about the new Registry.

Registry Search Mobile

Registry Search

Roberts Bank Terminal 2 Project

The Vancouver Fraser Port Authority proposes the construction and operation of a new three-berth marine container terminal located at Roberts Bank in Delta, British Columbia, approximately 35 km south of Vancouver. The proposed project, to be located next to the existing Deltaport and Westshore Terminals, would provide an additional 2.4 million twenty-foot equivalent units of container capacity per year at Roberts Bank.

Please note that the proponent was formerly known as Port Metro Vancouver.



Latest update

June 27, 2019 - The Review Panel completed the Public Hearing sessions on June 24, 2019. The public registry remains open to accept undertakings until June 28, 2019. After that date, only closing remarks will be accepted and posted to the public registry. Closing remarks should be submitted by August 26, 2019, as outlined in the Procedures for Submitting Closing Remarks for the Public Hearing.

Participate

List all documents

Contacts

  • Review Panel, Roberts Bank Terminal 2 Project
  • Impact Assessment Agency of Canada
  • 22nd Floor, 160 Elgin Street
  • Ottawa, ON, K1A 0H3
  • Telephone: 866-582-1884
  • Fax: 613-957-0941
  • Email: ceaa.panelrbt2-commissionrbt2.acee@canada.ca

  • Location

    • Delta (British Columbia)
  • Project Type

    • Water Projects (excluding hydroelectric generation)
    • Transportation
  • Status

    In progress
  • Start Date

    2013-11-08
  • Proponent

    The Vancouver Fraser Port Authority
  • Authorities

    • Impact Assessment Agency of Canada
  • Assessment Type

    Environmental assessment by Review Panel under CEAA 2012
Date modified: