Kapasiwin Bungalows Installation of Deep Water and Sewer Infrastructure
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
Kapasiwin LP has permission to operate under a year-round commercial lease, including year-round connection to the Waskesiu townsite's existing water distribution and wastewater collection infrastructure. The plan is to install a deep water main and sewage force main via horizontal directional drilling (HDD). Main lines will be installed via HDD through the approximate center of the existing Kapasiwin resort footprint, with individual cabin connections installed via trenching as the construction of new cabins is completed as per the phased plan for the Kapasiwin Bungalows resort site development (CanNorth 2017; eight new cabins will have trenched in connections to the main lines during Phase I of the development). The remaining length of HDD will be installed from the proposed new lift station location at the southeast corner of the existing resort footprint, travel below ground for approximately 1 km, and exit to connect to existing water and sewage facilities within the Waskesiu townsite. Approximately three to six bell holes may be excavated along the ~1 km HDD route, which follows the Old Waskesiu Drive. A 150 mm diameter high-density polyethylene (HDPE) pipe will be installed for the deep water main and a 50 mm diameter HDPE pipe will be installed for the sewage force main. Trenching and the primary HDD entry and exit locations are located in previously disturbed areas (i.e., the existing Kapasiwin resort footprint and within the Waskesiu townsite) and are expected to create minimal additional disturbance as a result of construction. Minimal brush clearing for equipment access and excavation of additional bell holes may be required along the HDD route between the primary entry and exit locations to accommodate the maximum drill length, bends along the proposed route, and available lengths of HDPE pipe.
The following activities will be conducted as part of the project: Site Preparation/Clearing – Prior to HDD and trenching, as required trees and other vegetation will be removed along the path of the planned route as well as from the vicinity of bell holes required for HDD entry and exit locations and any additional tie-ins necessary along the route. Additional clearing or brush cutting may be required for equipment access along the proposed HDD route; however, the width of clearing will be minimized to the amount necessary for construction. Additionally, the proposed HDD route parallels the Old Waskesiu Drive, reducing the need for vegetation clearing in this area. Excavation – All buried utilities will be located prior to trenching, bell hole excavation, and HDD. Topsoil will be removed from bell holes and trenches prior to excavation and stockpiled for reclamation. Excavated materials will be stockpiled a sufficient distance from the excavation so as not to impair the movement of installation equipment. All excavations will be backfilled using stockpiled materials. Machinery Use – Various types of equipment may be required for the project, including a trencher to complete final connections to cabins, a tracked excavator/track hoe to excavate entry/exit bell holes, a drilling rig to complete the HDD, a hydrovac to expose existing utilities at crossings and tie-in locations, and support vehicles. Transport of Materials/Equipment – The proponent/contractor will be responsible for acquiring all necessary permits/approvals required to transport materials and equipment to and from the project site. Equipment, scrap materials, and stockpiled materials will be removed from the construction area when they are no longer required. Waste Disposal - Waste materials will be removed from the site for salvage, reuse, recycling, or disposal at an approved landfill facility outside of PANP. Maintenance – Water and septic facilities will be maintained in accordance with operating specifications. Use – Water and septic facilities will be operated in accordance with operating specifications.
Latest update
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
2 | Parks Canada has issued a notice of determination and decided that the project is not likely to cause significant adverse environmental effects | - | December 15, 2019 |
1 | New Project Being Assessed by Parks Canada - Public Comments Invited 19 November to 19 December, 2019 | - | November 19, 2019 |
Contacts
Prince Albert National ParkBox 100
Waskesiu Lake, Saskatchewan S0J 2Y0
Telephone: 306-663-4522 or 1-888-773-8883
Email: npfuimpactassessment@pc.gc.ca
-
Location
- Prince Albert National Park (Saskatchewan)
-
Nature of Activity
- Building and Property Development
- Water Management
- Recreation and Tourism
- Waste Management
-
Assessment Status
Completed -
Start Date
2019-11-19 -
Proponent
Kapasiwin Bungalows -
Authorities
- Parks Canada Agency
-
Assessment Type
Project on federal lands -
Reference Number
80319
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Nearby assessments
...within 200 kilometres-
Sturgeon Lake First Nation Children's Playgrounds
Park location 2 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 1 -
On Hold - Aggregate Business Development Plan - Phase 2, Sturgeon Lake First Nation I.R. 101
Sturgeon Lake IR 101 -
Blanket Permit - SaskEnergy - Gasification of Sturgeon Lake Indian Reserve No. 101
Sturgeon Lake Indian Reserve No. 101 -
Sturgeon Lake First Nation - East Lagoon Expansion
Sturgeon Lake IR 101 -
Sturgeon Lake First Nation Subdivision
Sturgeon Lake IR 101A -
Sturgeon Lake First Nation Children's Playgrounds
Park location 3 -
Sturgeon River Pedestrian Bridge
Sturgeon Lake Indian Reservation No.101 -
Montreal Lake Cree Nation Little Red River Water Treatment Plant Upgrade Project
Montreal Lake Cree Nation -
Montreal Lake IR 106B Gasification
Montreal Lake IR 106B -
Montreal Lake Cree Nation & Little Red River Solid Waste Transfer Station & Decommissioning
Montreal Lake IR 106B -
Biocontrol of Yellow Toadflax using Rhinusa pilosa, in Prince Albert National Park
Prince Albert National Park -
Wahpeton Dakota Nation Sewage Lagoon Expansion
WAHPATON INDIAN RESERVE NO. 94A -
SaskPower Ground Mount Transformer Installation Red Deer Campground
Prince Albert National Park of Canada -
SaskPower Poles Replacement in Prince Albert National Park near south west boundary.
Prince Albert National Park -
Zagime Anishinabëk RV Trailer Park
Sakimay IR 74 -
SaskPower Ground Grid Replacement near MacKenzie Creek
Prince Albert National Park -
Beaver dam and lodge removal
Prince Albert National Park -
SaskPower Pole Mount Transformer Replacement for Hawood
Prince Albert National Park -
Fenceline Replacement - Prince Albert Training Area, Saskatchewan
DND Prince Albert Training Area -
SaskPower Pole Replacement near Halkett (Sandy) Lake
Prince Albert National Park -
SaskPower Transformer Salvage
Prince Albert National Park -
Sturgeon Lake First Nation - Renovation for gas bar and convenience store
Sturgeon Lake First Nation - Prince Albert Strip Mall -
Peter Ballantyne Child and Family Services Inc. Central Office Extension
Chief Joseph Custer Reserve -
Potential Regional Assessment of a Western Energy Corridor from Alberta to Manitoba
Prince Albert -
Potential Regional Assessment of a Western Energy Corridor
near Prince Albert -
SaskPower Pole Replacement in Prince Albert National Park - east of Sandy Lake
Prince Albert National Park -
SaskPower Trenching at Anglin Lake Dam (MPE Engineering)
Prince Albert National Park -
Peter Ballantyne Child and Family Services Facility
Kistapinin IR 211 -
Hunters Lake Trail Rehabilitation
Prince Albert National Park -
Mistawasis Nehiyawak Lagoon Upgrades
Mistawasis Nêhiyawak -
Muskoday First Nation Sewage Lagoon Upgrade
Muskoday First Nation -
Muskoday First Nation - Construct Cultural Centre
Muskoday First Nation - Construct Cultural Centre -
Muskoday Convenience Store Remediation
Muskoday First Nation -
Ahtahkakoop Powwow Grounds & Access Road
Ahtahkakoop Cree Nation -
Muskoday First Nation - Drainage Improvements Phase 1
Muskoday First Nation Reserve -
Muskoday First Nation - Community Access Road
Muskoday First Nation Reserve -
Mistawasis Nehiyawak Rural Transit Solutions
Mistawasis -
Piapot First Nation Prince Albert Urban Gas Bar & Convenience Store
Piapot IR 75 -
Mistawasis Nêhiyawak Community Center
Mistawasis -
Mistawasis Nêhiyawak Lake - Traditional Lands, Gathering Space
Mistawasis Nêhiyawak Lake -
Ahtahkakoop Cree Nation Water Treatment Plant
Ahtahkakoop IR 104 -
Cree Nation Treatment Haven Replacement
Ahtakakoop First Nation -
Ahtahkakoop Cree Nation Lagoon and Sewage Pumping Station
Ahtahkakoop IR #104 -
Boundary Bog Trail Boardwalk Project
Prince Albert National Park -
SaskPower Line Trenching at Operations Compound
Prince Albert National Park -
SaskPower Pole Replacement near Rec Hall
Prince Albert National Park -
Rabbit Creek Wildfire Reclamation
Prince Albert National Park -
SaskPower replacement of 8 power poles in Prince Albert National Park
Prince Albert National Park -
SaskPower Stabilization of 3 Power Poles in Waskesiu
Prince Albert National Park -
SaskPower Hesje Light Pole
Prince Albert National Park -
Ahtahkakoop South Subdivision Phase 1
Ahtakakoop Cree Nation -
SaskPower Underground Cable Install at Kapasiwin Bungalows
Prince Albert National Park -
SaskPower Cable Installation to Kapasiwin Cabins
Prince Albert National Park -
SaskPower Transformer Replacement and line trenching at Kapasiwin Bungalows
Prince Albert National Park -
SaskPower New U/G Cable and Transformer at Kapasawin Bungalows
Prince Albert National Park of Canada -
Beardy's & Okemasis Cree Nation Stage 4 Subdivision
Beardy's & Okemasis Cree Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Point of presence -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 3 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 2 -
Beardy's and Okemasis Cree Nation Water Treatment Plant Upgrades Project
Beardy's and Okemasis Cree Nation -
Willow Cree Healing Lodge - Construction of Ready to Move (RTM) Buildings
Willow Cree Healing Lodge -
Lac La Ronge Morin Lake Solid Waste Transfer Station & Decommissioning
Morin Lake IR 217 -
Big River First Nation Reserve Drainage Re-Establishment
Big River First Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 1 -
MEDA 324 kW Solar Farm
Muskoday IR 99 -
Big River First Nation Arena Build Project
Big River IR 118 -
Mistahi Sipiy Child and Family Service and Big River First Nation Prevention Building
Big River First Nation -
Fuel Reduction Program for Batoche National Historic Site
Batoche National Historic Site -
Batoche Drainage Improvement
Grasslands National Park -
Remediation of One Arrow First Nation River Lot 62
One Arrow IR 95 -
Prince Albert Grand Council (PAGC) Women's Shelter
Montreal Lake -
MLCN Montreal LK East Lagoon
Montreal Lake IR 106 -
Outhouse relocation
Prince Albert National Park of Canada -
Crean Channel Modification
Prince Albert National Park -
Tway National Wildlife Area Water Control Structure Re-naturalization Project.
Tway National Wildlife Area -
James Smith Cree Nation Peonan Creek Crossing
James Smith Cree Nation -
Tower Alteration for James Smith Cree Nation Justice & Policing communication system on James Smith Reserve No. 100
James Smith Cree Nation -
James Smith Cree Nation Solid Waste Transfer Station
James Smith Cree Nation -
James Smith Cree Nation Subdivision Stage 4
James Smith Cree Nation -
Star-Orion South Diamond Mine Project
Fort à la Corne Provincial Forest -
Witchekan Lake Subdivision
Witchekan Lake IR 161 -
Beardy's & Okemasis Cree Nation Sewage Lagoon and Pumping Station Upgrades
Beardy's and Okemasis IR No. 96 & 97 -
Witchekan Lake First Nation Solid Waste Transfer Station
Witchekan Lake First Nation -
Pelican Lake Bioenergy Project
Pelican Lake First Nation -
Pelican Lake Timber Harvesting Plan
Chitek Lake IR 191 -
Pelican Lake Timber Harvesting Plan 2021-22
Chitek Lake IR 191 & 191A -
Pelican Lake Farms - farm site development
Pelican Lake IR 191-B -
Pelican Lake First Nation 191 A, B, C, D Gasification Project
Pelican Lake First Nation 191 A, B, C, D -
Montreal Lake Cree Nation Bittern Lake Subdivision - Phase II
Montreal Lake IR 106B -
Pelican Lake North Sewage Lagoon Expansion and Upgrades
Chitek Lake IR 191 -
Pelican Lake First Nation - Quonset Addition
Chitek Lake IR 191 -
Lac Eauclaire Timber Harvest Program
Pelican Lake IR 191-C -
Pelican Lake Community Harvest Program Phase 2022-2024
Chitek Lake IR 191 -
Saskatchewan Agriculture Drainage Network - Brooksby Drainage Network Project
30 kilometres northeast of Melfort -
GL7 Phase 1 Transmission Rebuild Project (L007) / Saulteaux and Moosomin First Nations
Saulteaux IR 159G & Moosomin IR 112L -
Regional Psychiatric Centre
Regional Psychiatric Centre -
Apron III infill
Saskatoon International Airport YXE -
General Aviation Hangars Development
Saskatoon International Airport YXE -
Saskatchewan Indian Institute of Technologies Hangar Expansion
Saskatchewan Indian Institute of Technologies -
Nutrien Aviation Hangar Expansion
STARS Saskatoon Base -
Kahkewistahaw First Nation - Mamawi Business Center
Kahkewistahaw No. 72A -
Kahkewistahaw Landing Infrastructure Construction
Kahkewistahaw IR 72A - 2 -
Muskeg Lake Cree Nation - Construction of commercial/retail building
ASIMAKANISEEKAN ASKIY 102A -
125 Aspen Place Infrastructure & New Building Construction Project
125 Aspen Place, Saskatoon -
Saulteaux IR159 Timber Harvest Plan 2021-22
Saulteaux IR 159EE -
Carry the Kettle First Nation - Ag Permit - D. Gorniak -2019-2021
Carry The Kettle Indian Reserve 76-9 & 79-42 -
Saulteaux IR159 Timber Harvest Plan 2020-21
Saulteaux IR 159EE -
Moosomin Road Repair and Drainage
Moosomin IR No. 112B -
Thunderchild First Nation - Turtle Lake Site 115C WTP Process Waste Pond
Thunderchild IR 115C -
Gas Station Construction Saskatoon
Kahkewistahaw Indian Reserve No. 72A-2 -
Grasswoods Reserve Septage Receiving Station, Retention Pond and Final Disposal to City of Saskatoon Forcemain
Grasswoods IR 192J -
Kawacatoose First Nation Subdivision
Kawacatoose IR 88 -
Saulteaux Fire Hall / Maintenance Facility
Saulteaux IR 159 -
Kinistin Saulteaux Nation Barrier River Bridge Replacement
Kinistin Saulteaux Nation -
Kinistin Saulteaux Nation Sewage Lagoon Expansion
Kinistin IR No. 91 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 2) -
Flying Dust - New Water Treatment Plant
Flying Dust IR 105 -
Thunderchild First Nation - Solid Waste Transfer Station
Thunderchild IR115B & 115C -
Thunderchild First Nation Lagoon Upgrade
Thunderchild IR115B -
Flying Dust Commercial Project
Meadow Lake -
Dore Lake Wharf Removal
Dore Lake -
North Creek Trail Realignment
17 Wing Detachment - Dundurn's Range and Training Area -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Flying Dust First Nation Regional Landfill
Flying Dust IR 105 -
La Ronge Area Peat Harvesting Project
La Ronge -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 1) -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Thunderchild First Nation - Turtle Lake Site 115C Sewage Lagoon Operations
Thunderchild First Nation -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
Dakota Springs Spa
Whitecap IR #94 -
Buffalo Berry Culvert Work
Whitecap IR #94 -
New Fibre Installation, Upgrade (Single) Tower
Moonlight bay -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Whitecap Dakota Nation Virtual Health Hub
Whitecap Dakota First Nation No 94 -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
EAGLES LAKE I.R. 165C -
Magazine Area Recapitalization Canadian Forces Ammunition Depot (CFAD) - 17 Wing Detachment Dundurn
Canadian Forces Ammunition Depot Dundurn,17 Wing Detachment Dundurn -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
Fishing Lake First Nation Sewage Pumping Station Upgrades
Fishing Lake First Nation -
Mosquito Grizzly Bear's Head Lean Man First Nation - Core Area Subdivision
Mosquito Grizzly Bear's Head Lean Man First Nation -
Aspen Power Station Project
Lanigan -
Mosquito First Nation Lagoon Upgrades
Mosquito First Nation -
Thunderchild First Nation Powwow Arbor
THUNDERCHILD FIRST NATION 115B -
Thunderchild Wellness Centre
Thunderchild Wellness Centre -
Thunderchild First Nation Water Treatment Plant and Well Upgrades
THUNDERCHILD FIRST NATION 115B -
Sweetgrass First Nation Wastewater System Upgrades
Sweetgrass First Nation -
Hall Lake Stage 3 Subdivision
Morin Lake I.R. No. 217 -
Lac La Ronge Indian Band Morin Lake Lagoon and Sewage Pumping Station Upgrade
SE-33-70-26-2 and SW-34-70-26-2 -
Sweetgrass New School
Sweetgrass IR 113 -
Sweetgrass Daycare and Early Learning Head Start Centre Project
Saskatoon -
Lac La Ronge Indian Band - Lac La Ronge 156 Lagoon Expansion
Lac La Ronge Indian Band -
Lac La Ronge Indian Band Clean-up of Solid Waste Disposal Sites
Sucker River IR 156C, Stanley IR 157, Morin Lake IR 217, Little Red River IR 106C, Lac La Ronge IR 156 and Grandmother's Bay IR 219 -
Lac La Ronge Indian Band Wellness Healing and Recovery Center
Lac La Ronge IR No. 156 -
Fixed Point-to-Point Link from Dorintosh, SK to Waterhen Lake, SK
Waterhen 130 Reserve -
Yellow Quill First Nation Subdivision Stage 2
Yellow Quill IR 90