Little Pine First Nation Lagoon Upgrade and Bridge over Battle River
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The project will include the construction of a new sewage lagoon , including common excavation, synthetic liner, and transfer piping. The lagoon will be design and constructed to meet the 10 year design horizon, with practical considerations to allow for easy expansion to meet the 20 year design horizon, when appropriate. Lagoon sizing is 3.45ha primary cell; 95,100 cubic meter storage cell. The project will include a 200mm sewage forcemain of approximately 3,300 lin. m. in length. Sewage pumping station upgrades include new sewage pumps, piping and a sewage grinder. The project will include approximately 3,300 lin. m. of access road construction and bridge construction will take place in Section 31, Township 45, Range 21 W3. Road width of 7m with gravel surface.
Lagoon construction will take place in portion of NW6 - TWP46 - Rng 21- W3M.Sewage force main will be in portion of, NW31 - 45 - 21 - W3M, NW31 - 45 - 21 - W3M, SE6 - 46 - 21 - W3M and NW6 - 46 - 21 - W3M. All parcels were previously disturbed by farming activities.
New and permanent infrastructure will include the new sewage force main and sewage treatment lagoon. Activities include feasibility study, design, tender, construction operation and maintenance. Waste generation is expected to be minimal for this project. Waste generation to include typical construction waste. Waste will be collected in transportation bins and hauled to the nearest regional landfill.
Force main crossing to be completed by horizontal directional drilling under Battle River. Fisheries permit is not required for directional drilling, and proponent confirms that all mitigation measures noted here will be followed: http://www.dfo-mpo.gc.ca/pnw-ppe/measures-mesures-eng.html
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
Latest update
.
Participate
Key documents
Document Number | Document Title | File | Date |
---|---|---|---|
3 | Notice of Determination for Little Pine First Nation Lagoon Upgrade and Bridge over Battle River | - | February 17, 2023 |
2 | Public Comment Period on Intent to Make a Determination | - | November 23, 2022 |
1 | Public Comment Period on Intent to Make a Determination | - | July 7, 2022 |
Contacts
ISC-SKENVIndigenous Services Canada
1827 Albert Street
Regina, Saskatchewan S4P 2S9
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
-
Location
- Little Pine IR No. 116 (Saskatchewan)
-
Nature of Activity
- Water Management
- Waste Management
-
Assessment Status
Completed -
Start Date
2022-07-07 -
Proponent
Little Pine First Nation -
Authorities
- Indigenous Services Canada
- Transport Canada
-
Assessment Type
Project on federal lands -
Reference Number
83776
Nearby assessments
...within 200 kilometres-
Great Sandhills Railway Switching Operation at North West Terminal Project - Revised Design
1 kilometre east of Unity, Saskatchewan -
Great Sandhills Railway Switching Operation at North West Terminal Project
1 kilometre east of Unity -
Sweetgrass New School
Sweetgrass IR 113 -
Sweetgrass Daycare and Early Learning Head Start Centre Project
Saskatoon -
Mosquito First Nation Lagoon Upgrades
Mosquito First Nation -
Enbridge Line 3 Replacement Program
Kerrobert -
Moosomin Road Repair and Drainage
Moosomin IR No. 112B -
Saulteaux Fire Hall / Maintenance Facility
Saulteaux IR 159 -
Thunderchild First Nation Lagoon Upgrade
Thunderchild IR115B -
Thunderchild First Nation - Solid Waste Transfer Station
Thunderchild IR115B & 115C -
Thunderchild First Nation - Turtle Lake Site 115C WTP Process Waste Pond
Thunderchild IR 115C -
Thunderchild Wellness Centre
Thunderchild Wellness Centre -
GL7 Phase 1 Transmission Rebuild Project (L007) / Saulteaux and Moosomin First Nations
Saulteaux IR 159G & Moosomin IR 112L -
Building Foundation Removal and Site Restoration in Lost Farm Area at 3CDSB Wainwright
The Range Training Area (RTA) at Detachment Wainwright -
Saulteaux IR159 Timber Harvest Plan 2020-21
Saulteaux IR 159EE -
Saulteaux IR159 Timber Harvest Plan 2021-22
Saulteaux IR 159EE -
Electrical Power Upgrade for Building 650 (B650) at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrade Railhead at Garrison Wainwright
Garrison Wainwright (Denwood) -
New Power Line Installation
CFB Suffield, Medicine Hat -
Reconfigure Power Distribution at the Exercise Control Site
CFB Suffield, Medicine Hat -
Skate Park Design-Build Project - Garrison Wainwright
Garrison Wainwright -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Building 633) -
Demolish Pre-Wash Facility - Garrison Wainwright
Garrison Wainwright -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Bulk parking lot) -
Front Gate Water Loop - Garrison Wainwright
Garrison Wainwright in Denwood -
Upgrade Main Petroleum Oils and Lubricants (POL) Facility at Garrison Wainwright
Garrison Wainwright in Denwood -
Demolition of Tent City, Building 313 and Water Point - Garrison Wainwright
Garrison Wainwright -
Upgrade Water and Sewer Utilities to Building AW22 at Garrison Wainwright
Garrison Wainwright (Denwood) -
Upgrade Range 1 at Garrison Wainwright
Garrison Wainwright in Denwood -
Provide Power to Troop Shelters at Garrison Wainwright
Garrison Wainwright (Denwood) -
Install Cattle Watering Line in the Range and Training Area - Garrison Wainwright
Garrison Wainwright -
Upgrades to Range 8 - Garrison Wainwright
Garrison Wainwright -
Construct Sniper Range at Garrison Wainwright
Garrison Wainwright (Denwood) -
Install New Trailer Complex at P12 at Garrison Wainwright
Garrison Wainwright (near Denwood) -
Onion Lake Cree Nation Aquatic Centre Project
Onion Lake Cree Nation Aquatic Centre Project -
RW-4851 Authorization to Construct and Operate a Right of Way for a gas pipeline
Frog Lake First Nation -
Witchekan Lake Subdivision
Witchekan Lake IR 161 -
Paving project at Garrison Wainwright
Garrison Wainwright in Denwood (Building 750) -
Stabilize Temporary Bridge Abutments - Garrison Wainwright
Garrison Wainwright -
Demolish and Upgrade Vertical Village - Garrison Wainwright
Garrison Wainwright -
Pelican Lake Community Harvest Program Phase 2022-2024
Chitek Lake IR 191 -
Hardisty Rail Terminal Project
10 km southeast of Hardisty -
Pelican Lake First Nation - Quonset Addition
Chitek Lake IR 191 -
Construction of a Royal Canadian Mounted Police Detachment in Vermilion, Alberta
Vermilion -
Potential Regional Assessment of a Western Energy Corridor
near Vermilion -
TransCanada Energy East Pipeline Project
Hardisty -
Enbridge Line 3 Replacement Program
Hardisty -
Pelican Lake First Nation 191 A, B, C, D Gasification Project
Pelican Lake First Nation 191 A, B, C, D -
Pelican Lake Farms - farm site development
Pelican Lake IR 191-B -
Pelican Lake North Sewage Lagoon Expansion and Upgrades
Chitek Lake IR 191 -
Pelican Lake Timber Harvesting Plan 2021-22
Chitek Lake IR 191 & 191A -
Pelican Lake Timber Harvesting Plan
Chitek Lake IR 191 -
Trench Removal and Site Restoration in C1 area at CFB Wainwright
The Range Training Area (RTA) at Detachment Wainwright -
Mistawasis Nêhiyawak Lake - Traditional Lands, Gathering Space
Mistawasis Nêhiyawak Lake -
Mistawasis Nêhiyawak Community Center
Mistawasis -
Kahkewistahaw Landing Infrastructure Construction
Kahkewistahaw IR 72A - 2 -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MAKWA LAKE I.R. 129B (Tower 3) -
Apron III infill
Saskatoon International Airport YXE -
General Aviation Hangars Development
Saskatoon International Airport YXE -
Mistawasis Nehiyawak Rural Transit Solutions
Mistawasis -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MINISTIKWAN I.R. 161 (Tower 2) -
Ahtahkakoop Cree Nation Lagoon and Sewage Pumping Station
Ahtahkakoop IR #104 -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MINISTIKWAN I.R. 161 (Tower 1) -
Waskonaman Hill Gravel Project
Frog Lake First Nation -
Ahtahkakoop Cree Nation Water Treatment Plant
Ahtahkakoop IR 104 -
Muskeg Lake Cree Nation - Construction of commercial/retail building
ASIMAKANISEEKAN ASKIY 102A -
OS-7250 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad
Frog Lake First Nation -
Makwa Lake Resort Development
Makwa Lake Indian Reserve No. 129B -
OS-6825 Authorization to Construct an access road and a Surface Lease Extension and Operate a Multi-well oil pad
OS-6825 -
Lac La Ronge Morin Lake Solid Waste Transfer Station & Decommissioning
Morin Lake IR 217 -
Lac Eauclaire Timber Harvest Program
Pelican Lake IR 191-C -
Regional Psychiatric Centre
Regional Psychiatric Centre -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MINISTIKWAN I.R. 161A -
Big River First Nation Arena Build Project
Big River IR 118 -
Ahtahkakoop Powwow Grounds & Access Road
Ahtahkakoop Cree Nation -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MINISTIKWAN I.R. 161 (Tower 3) -
Mistahi Sipiy CFS and Big River First Nation Prevention Building
Big River First Nation -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
125 Aspen Place Infrastructure & New Building Construction Project
125 Aspen Place, Saskatoon -
Ministikwan Subdivision Development
Ministikwan IR 161 -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Buffalo Berry Culvert Work
Whitecap IR #94 -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Ministikwan Lake Cree Nation - Solid Waste Transfer Station
Ministikwan IR161 -
Dakota Springs Spa
Whitecap IR #94 -
North Creek Trail Realignment
17 Wing Detachment - Dundurn's Range and Training Area -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Frog Lake First Nation Water System Project
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
EAGLES LAKE I.R. 165C -
Frog Lake First Nation Water System Project
Frog Lake First Nation -
Frog Lake Waste Management Transfer Station
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
WATERHEN I.R. 130 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 1 -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MAKWA LAKE I.R. 129B (Tower 2) -
Frog Lake First Nation Landfill Cap Construction
Frog Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Tower
MAKWA LAKE I.R. 129B (Tower 1) -
Flying Dust - New Water Treatment Plant
Flying Dust IR 105 -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Point of presence -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 2 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 3 -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Gas Station Construction Saskatoon
Kahkewistahaw Indian Reserve No. 72A-2 -
Grasswoods Reserve Septage Receiving Station, Retention Pond and Final Disposal to City of Saskatoon Forcemain
Grasswoods IR 192J -
Construction of Ready to Move (RTM) buildings at Willow Cree Healing Lodge
Willow Cree Healing Lodge -
Beardy's & Okemasis Cree Nation Sewage Lagoon and Pumping Station Upgrades
Beardy's and Okemasis IR No. 96 & 97 -
Construction of Two Bridge Files in Saddle Lake Cree Nation
Construction of Two Bridge Files in Saddle Lake Cree Nation -
Batoche Drainage Improvement
Grasslands National Park -
Fuel Reduction Program for Batoche National Historic Site
Batoche National Historic Site