Upgrade Main Petroleum Oils and Lubricants (POL) Facility at Garrison Wainwright

This project involves improvements to the existing Main POL facility at Garrison Wainwright. Construction is proposed for 2021 and 2022. Project activities include:
· Remove and replace existing concrete roadways, curbs, sidewalks and trench drain.
· Replace connection between oil water separators.
· Remove and replace existing fence.


Latest update

May 17, 2021– The Department of National Defence issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects.

Participate

Contacts

Department of National Defence
Roy Simpson, Project Manager, Real Property Operations Unit (West) Detachment Wainwright
Real Property Operations Unit (West) Detachment Wainwright
Denwood, Alberta T0B 1B0
Telephone: 780-842-1363 ext. 1308
Email: roy.simpson@forces.gc.ca


  • Location

    • Garrison Wainwright in Denwood (Alberta)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    Completed
  • Start Date

    2021-03-10
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    81437