Provide Power to Troop Shelters at Garrison Wainwright

This project involves the provision of power to the Troop Shelters at various locations within the Range and Training Area of Garrison Wainwright. Specifically:
· Gas Hut - trenching cable below-ground 42m in a new corridor (the original power was overhead)
· Range 1 - installing 3-phase power to intersection (underground) and single phase power to Range 1 troop shelter
· Range 3 - trenching 30m of cable underground
· Range 6 and 8 - extend overhead from Building 457; create new utility right-of-way to bring power to Range 6 and Range 8; tree removal is required


Latest update

May 21, 2020 – The public comment period on the project is closed. The Department of National Defence is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.

Participate

Contacts

Project Manager, Real Property Operations Unit (West) Detachment Wainwright
Department of National Defence
Caroline Paquin, Project Manager, Real Property Operations Unit (West) Detachment Wainwright
Real Property Operations Unit (West) Detachment Wainwright
Denwood, Alberta T0B 1B0
Telephone: 780-842-1363 ext. 1361
Email: caroline.paquin@forces.gc.ca


  • Location

    • Garrison Wainwright (Denwood) (Alberta)
  • Nature of Activity

    • Building and Property Development
  • Assessment Status

    In progress
  • Start Date

    2020-04-30
  • Proponent

    Department of National Defence
  • Authorities

    • Department of National Defence
  • Assessment Type

    Project on federal lands
  • Reference Number

    80636