SaskPower - 2E-33 Mullingar Rural Rebuild
This is a non-designated project on federal lands or outside Canada. The listed authorities are responsible for the project assessment.
The purpose of the Project is for SaskPower to replace aging overhead powerline infrastructure in order to maintain the integrity of power service for existing and future customers. The Project scope includes building approximately 51 km and salvaging approximately 36 km of overhead power lines within existing SaskPower right-of-ways (ROW) and within road allowance adjacent to existing roads. A portion of the project traverses eight quarter sections of Mosquito Grizzly Bear's Head Lean Man TLE Indian Reserve land, located approximately 55 km NE of North Battleford, Saskatchewan.
The Project is located on or near eight quarter sections of Mosquito Grizzly Bear's Head Lean Man TLE Indian Reserve land with legal land descriptions as follows:
SW 30-47-11-W3M (construction in the developed road ROW to the south, salvage on the southern portion of the quarter section)
SE 25-47-12-W3M (construction in the developed road ROW to the south, salvage on the southern portion of the quarter section)
NW 23-47-12-W3M (construction in the developed road ROW on the west portion of the quarter section)
SE 22-47-12-W3M (construction and salvage on the north portion of the quarter section)
SE 26-47-12-W3M (construction in the developed road ROW to the south, salvage on the southern portion of the quarter section)
NE 31-47-11-W3M (construction in the developed road ROW on the south portion of the quarter section)
SW 15-47-12-W3M (~30 m salvage in the northwest corner of the quarter section)
The project includes vegetation clearing, the salvage of existing wood poles with associated hardware and overhead conductor, and the installation of wood poles with associated hardware and overhead conductors. The Project will be accessed from locations within road allowances and SaskPower ROW. The removal of trees and shrubs is required for safe equipment access and tree-fall clearance to reduce the risk of damage to the overhead powerline and the potential for fire due to tree contact with the overhead conductor.
A portion of the underground cable installation will require approximately 20 m of directional boring underneath a small drainage ditch, within SE 22-47-12 W3M, with the use of a back-hoe and directional boring equipment. The back-hoe will excavate two approximately 2 m deep, 2 m wide, and 2 m long bell holes at the terminal ends of the bore path, and the directional borer will drill an approximately 5 cm diameter bore path to accommodate the underground cable. The underground cable will then be pulled through to the other end, leaving the cable exposed at the end points. At these locations, topsoil stripping will be employed prior to the excavation of parent material to minimize admixing of soil horizons. The excavated soil will be placed back in order into the bell holes and compacted immediately after the underground cable has been installed.
The proposed project footprint is also within 30 meters of multiple Class I to Class IV wetlands. SaskPower proposes to span the wetlands with an overhead line.
A permanent residence located in SE 22-47-12-W3M is located along the Project route. The Project will connect to this residence directly as this is distribution power that is required to be upgraded.
Latest update
Participate
Key documents
| Document number | Document title | File | Date |
|---|---|---|---|
| 2 | Notice of Determination for the SaskPower 2E-33 Mullingar Rural Rebuild | - | July 2, 2025 |
| 1 | Notice of Intent to Make a Determination - Start of Public Comment Period | - | June 2, 2025 |
Contacts
ISC-SKENVIndigenous Services Canada
Alvin Hamilton Building, 1783 Hamilton Street
Regina, Saskatchewan S4P 2B6
Telephone: 306-581-3134
Email: isc-skenv@sac-isc.gc.ca
Disclaimer
This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.
-
Location
- Mosquito Grizzly Bear's Head Lean Man TLE Indian Reserve (Saskatchewan)
-
Nature of Activity
- Other, not otherwise specified
-
Assessment Status
Completed -
Start Date
2025-06-02 -
Proponent
SaskPower -
Authorities
- Indigenous Services Canada
-
Assessment Type
Project on federal lands -
Reference Number
89590
Nearby assessments
...within 200 kilometres-
Lucky Man Cree Nation Community Access Road
LUCKY MAN RESERVE -
Lucky Man Cree Nation Access Road Design and Construction
Lucky Man Reserve -
Witchekan Lake Subdivision
Witchekan Lake IR 161 -
Big River First Nation Reserve Drainage Re-Establishment
Big River First Nation -
Witchekan Lake First Nation Solid Waste Transfer Station
Witchekan Lake First Nation -
New Fibre Installation - Central and Southeastern SK
Project site 5: MUSKEG LAKE I.R. 102 -
Moosomin Road Repair and Drainage
Moosomin IR No. 112B -
Witchekan Lake First Nation Cultural Centre
Witchekan Lake Indian Reserve No. 117 -
Saulteaux First Nation Subdivision Development
Saulteaux Indian Reserve No. 159 -
Witchekan Lake First Nation Sweat Lodge
Witchekan Lake Indian Reserve No. 117 -
Saulteaux First Nation Firehall and Vehicle Storage Facility
Saulteaux Indian Reserve Number 159 -
Saulteaux Fire Hall / Maintenance Facility
Saulteaux IR 159 -
GL7 Phase 1 Transmission Rebuild Project (L007) / Saulteaux and Moosomin First Nations
Saulteaux IR 159G & Moosomin IR 112L -
Mistawasis Nêhiyawak Lake - Traditional Lands, Gathering Space
Mistawasis Nêhiyawak Lake -
Upgrade Single Tower & New Fibre Installation
Project site 5: North East region - Mistawasis -
Mistawasis Nêhiyawak Community Center
Mistawasis -
Ahtahkakoop Cree Nation New School
AHTAHKAKOOP INDIAN RESERVE NO. 104 -
Mistawasis Nehiyawak Rural Transit Solutions
Mistawasis -
Ahtahkakoop Cree Nation Lagoon and Sewage Pumping Station
Ahtahkakoop IR #104 -
New Fibre Installation - Central and Southeastern SK
Project site 7: AHTAHKAKOOP I.R. 104 -
Cree Nation Treatment Haven Replacement
Ahtakakoop First Nation -
Ahtahkakoop Cree Nation Water Treatment Plant
Ahtahkakoop IR 104 -
Red Pheasant Cree Nation - Eagle Landing Development
Red Pheasant Reserve No. 108 -
Mistawasis Nehiyawak Lagoon Upgrades
Mistawasis Nêhiyawak -
Ahtahkakoop Powwow Grounds & Access Road
Ahtahkakoop Cree Nation -
Lac La Ronge Morin Lake Solid Waste Transfer Station & Decommissioning
Morin Lake IR 217 -
Thunderchild First Nation - Turtle Lake Site 115C WTP Process Waste Pond
Thunderchild IR 115C -
Ahtahkakoop Cree Nation Debden Road Upgrades
AHTAHKAKOOP INDIAN RESERVE NO. 104 -
New Fibre Installation - Central and Southeastern SK
Project site 4: Big River 118 -
Mistahi Sipiy Child and Family Service and Big River First Nation Prevention Building
Big River First Nation -
Big River First Nation Arena Build Project
Big River IR 118 -
Thunderchild First Nation Lagoon Upgrade
Thunderchild IR115B -
Thunderchild First Nation - Solid Waste Transfer Station
Thunderchild IR115B & 115C -
Big River First Nation Drainage Reestablishment Phase 1B
BIG RIVER INDIAN RESERVE NO. 118 -
Pelican Lake Bioenergy Project
Pelican Lake First Nation -
Pelican Lake Farms - farm site development
Pelican Lake IR 191-B -
Pelican Lake First Nation 191 A, B, C, D Gasification Project
Pelican Lake First Nation 191 A, B, C, D -
Food Sovereignty Project- Bison and Elk Farms, and Community Gardens
Pelican Lake First Nation, near Leoville -
Pelican Lake Child and Family Services Facility
Pelican Lake First Nation -
Pelican Lake Timber Harvesting Plan
Chitek Lake IR 191 -
Pelican Lake Timber Harvesting Plan 2021-22
Chitek Lake IR 191 & 191A -
Pelican Lake First Nation - Quonset Addition
Chitek Lake IR 191 -
Pelican Lake Community Harvest Program Phase 2022-2024
Chitek Lake IR 191 -
Pelican Lake First Nation Subdivision
CHITEK LAKE INDIAN RESERVE NO. 191 -
Pelican Lake North Sewage Lagoon Expansion and Upgrades
Chitek Lake IR 191 -
Saulteaux IR159 Timber Harvest Plan 2021-22
Saulteaux IR 159EE -
Saulteaux IR159 Timber Harvest Plan 2020-21
Saulteaux IR 159EE -
Walk Into History
Chitek Lake -
Upgrade Single Tower & New Fibre Installation
Project site 2: North East region - Chamakese Resort (Chitek Lake) -
Ahtahkakoop South Subdivision Phase 1
Ahtakakoop Cree Nation -
Mosquito Grizzly Bear's Head Lean Man First Nation - Core Area Subdivision
Mosquito Grizzly Bear's Head Lean Man First Nation -
Mosquito First Nation Lagoon Upgrades
Mosquito First Nation -
Sweetgrass First Nation Wastewater System Upgrades
Sweetgrass First Nation -
Witchekan Lake First Nation Youth Lodge
Witchekan Lake Indian Reserve No. 117 -
Sweetgrass Daycare and Early Learning Head Start Centre Project
Saskatoon -
Sweetgrass New School
Sweetgrass IR 113 -
Beaver dam and lodge removal
Prince Albert National Park -
Lac Eauclaire Timber Harvest Program
Pelican Lake IR 191-C -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 1: West Central region - Sweetgrass -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 1 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Point of presence -
Beardy's and Okemasis Cree Nation Water Treatment Plant Upgrades Project
Beardy's and Okemasis Cree Nation -
Beardy's and Okemasis Cree Nation Solid Waste Removal and Landfill Decommissioning
Beardy's and Okemasis Cree Nation -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 2 -
New (Multiple) Tower Construction, Upgrade (Single) Tower, New Fibre Installation
Tower 3 -
New Fibre Installation, Upgrade (Single) Tower
Moonlight bay -
Beardy's & Okemasis Cree Nation Stage 4 Subdivision
Beardy's & Okemasis Cree Nation -
Thunderchild First Nation - Turtle Lake Site 115C Sewage Lagoon Operations
Thunderchild First Nation -
Poundmaker Cree Nation New Bridge Construction
Poundmaker Indian Reserve No. 114 -
Poundmaker Cree Nation Lagoon Upgrades
Poundmaker Indian Reserve No. 114 -
SaskPower Pole Mount Transformer Replacement for Hawood
Prince Albert National Park -
Thunderchild Community Walking Trail
Thunderchild First Nation -
Thunderchild First Nation Powwow Arbor
THUNDERCHILD FIRST NATION 115B -
Thunderchild First Nation Firehall
Thunderchild First Nation Indian Reserve No. 115B -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 3: West Central region - Thunderchild -
Thunderchild First Nation Water Treatment Plant and Well Upgrades
THUNDERCHILD FIRST NATION 115B -
Thunderchild Wellness Centre
Thunderchild Wellness Centre -
Willow Cree Healing Lodge - Construction of Ready to Move (RTM) Buildings
Willow Cree Healing Lodge -
Thunderchild First Nation New Subdivision
THUNDERCHILD FIRST NATION INDIAN RESERVE NO. 115B -
Little Pine First Nation Health Clinic
Little Pine Indian Reserve No. 116 -
Zagime Anishinabëk RV Trailer Park
Sakimay IR 74 -
On Hold - Aggregate Business Development Plan - Phase 2, Sturgeon Lake First Nation I.R. 101
Sturgeon Lake IR 101 -
Sturgeon Lake First Nation Child and Family Service Centre
STURGEON LAKE INDIAN RESERVE NO. 101 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 1 -
Batoche Drainage Improvement
Grasslands National Park -
Fuel Reduction Program for Batoche National Historic Site
Batoche National Historic Site -
Kapasiwin Bungalows Installation of Deep Water and Sewer Infrastructure
Prince Albert National Park -
Oskâyak Miyoayâwin Youth Learning Centre
STURGEON LAKE INDIAN RESERVE NO. 101 -
Sturgeon Lake First Nation Children's Playgrounds
Park location 2 -
Phase 2 - Sturgeon Lake First Nation Active Transportation Network
Phase 2 - Sturgeon Lake First Nation Active Transportation Network -
Blanket Permit - SaskEnergy - Gasification of Sturgeon Lake Indian Reserve No. 101
Sturgeon Lake Indian Reserve No. 101 -
Remediation of One Arrow First Nation River Lot 62
One Arrow IR 95 -
New Fibre Installation - Central and Southeastern SK
Project site 3: One Arrow 95-1A -
Hunters Lake Trail Rehabilitation
Prince Albert National Park -
Upgrade Single Tower & New Fibre Installation
Project site 3: North East region - One Arrow -
Little Pine First Nation Lagoon Upgrade and Bridge over Battle River
Little Pine IR No. 116 -
Sturgeon Lake First Nation - East Lagoon Expansion
Sturgeon Lake IR 101 -
Sturgeon Lake First Nation Subdivision
Sturgeon Lake IR 101A -
Sturgeon Lake First Nation Children's Playgrounds
Park location 3 -
Upgrade Single Tower & New Fibre Installation
Project site 6: North East region - Sturgeon Lake -
Sturgeon River Pedestrian Bridge
Sturgeon Lake Indian Reservation No.101 -
Biocontrol of Yellow Toadflax using Rhinusa pilosa, in Prince Albert National Park
Prince Albert National Park -
Wahpeton Roads Upgrades
Wahpeton Dakota Nation -
SaskPower Transformer Salvage
Prince Albert National Park -
Beardy's & Okemasis Cree Nation Sewage Lagoon and Pumping Station Upgrades
Beardy's and Okemasis IR No. 96 & 97 -
New Fibre Installation - Central and Southeastern SK
Project site 2: Wahpaton 94A -
Wahpeton Dakota Nation New School
Wahpeton Dakota Nation -
New Fibre Installation - Central and Southeastern SK
Project site 8: WAHPATON I.R. 94A -
Wahpeton Dakota Nation Sewage Lagoon Expansion
WAHPATON INDIAN RESERVE NO. 94A -
SaskPower Ground Mount Transformer Installation Red Deer Campground
Prince Albert National Park of Canada -
Montreal Lake IR 106B Gasification
Montreal Lake IR 106B -
Saskatoon Airport Solar - 1MW Project
1MW Ground Mounted Solar Facility -
Apron III infill
Saskatoon International Airport YXE -
General Aviation Hangars Development
Saskatoon International Airport YXE -
Upgrade Single Tower & New Fibre Installation
Project site 4: North East region - Montreal Lake -
Montreal Lake Cree Nation Little Red River Water Treatment Plant Upgrade Project
Montreal Lake Cree Nation -
Saskatchewan Indian Institute of Technologies Hangar Expansion
Saskatchewan Indian Institute of Technologies -
Nutrien Aviation Hangar Expansion
STARS Saskatoon Base -
45th & Airport Holdings Ltd. Restaurant and Gas Station Commercial Development
Restaurant/Gas Station Commercial Development -
SaskPower Ground Grid Replacement near MacKenzie Creek
Prince Albert National Park -
Kahkewistahaw Landing Infrastructure Construction
Kahkewistahaw IR 72A - 2 -
Kahkewistahaw First Nation - Mamawi Business Center
Kahkewistahaw No. 72A -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 2) -
Montreal Lake Cree Nation & Little Red River Solid Waste Transfer Station & Decommissioning
Montreal Lake IR 106B -
SaskPower Poles Replacement in Prince Albert National Park near south west boundary.
Prince Albert National Park -
Flying Dust Commercial Project
Meadow Lake -
SaskPower Pole Replacement near Halkett (Sandy) Lake
Prince Albert National Park -
New Fibre Installation - Central and Southeastern SK
Project site 9: LITTLE RED RIVER I.R. 106C -
Flying Dust - New Water Treatment Plant
Flying Dust IR 105 -
SaskPower Pole Replacement in Prince Albert National Park - east of Sandy Lake
Prince Albert National Park -
Muskeg Lake Cree Nation - Construction of commercial/retail building
ASIMAKANISEEKAN ASKIY 102A -
Regional Psychiatric Centre - Removal of an Underground Storage Tank
Regional Psychiatric Centre -
Peter Ballantyne Cree Nation Parcel E Development
CHIEF JOSEPH CUSTER RESERVE -
Parcel E Sublease - Eagle Ridge Residential Building
Parcel E of Chief Joseph Custer Reserve -
Prince Albert Administration Office Addition
Chief Joseph Custer Reserve -
Peter Ballantyne Child and Family Services Inc. Central Office Extension
Chief Joseph Custer Reserve -
Sturgeon Lake First Nation - Renovation for gas bar and convenience store
Sturgeon Lake First Nation - Prince Albert Strip Mall -
Peter Ballantyne Child and Family Services Facility
Kistapinin IR 211 -
Kistaphinanihk Office Building
Kistaphinanihk IR No. 231 -
Northern Lights Casino Expansion and Renovation
Northern Lights Indian Reserve No.220 -
Fenceline Replacement - Prince Albert Training Area, Saskatchewan
DND Prince Albert Training Area -
Blanket Permit - SaskEnergy - Northern Lights Indian Reserve No. 220
Northern Lights Indian Reserve No. 220 -
Blanket Permit - SaskPower - Kistapinan Indian Reserve No.211
Kistapinan Indian Reserve No. 211 -
Potential Regional Assessment of a Western Energy Corridor from Alberta to Manitoba
Prince Albert -
Potential Regional Assessment of a Western Energy Corridor
near Prince Albert -
SaskPower Trenching at Anglin Lake Dam (MPE Engineering)
Prince Albert National Park -
Great Sandhills Railway Switching Operation at North West Terminal Project - Revised Design
1 kilometre east of Unity, Saskatchewan -
Great Sandhills Railway Switching Operation at North West Terminal Project
1 kilometre east of Unity -
The Lac La Ronge Indian Band Little Red River Water Upgrades
LITTLE RED RIVER 106C -
Little Red River Wellbeing Centre
Little Red River IR #106c -
125 Aspen Place Infrastructure & New Building Construction Project
125 Aspen Place, Saskatoon -
Flying Dust First Nation Regional Landfill
Flying Dust IR 105 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 1) -
Yuasni Tipi Lodge Lease
Wahpeton Dakota Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
EAGLES LAKE I.R. 165C -
Flying Dust First Nation Railway Infrastructure Development Project
Flying Dust First Nation Indian Reserve No. 105 -
Flying Dust First Nation Residential Subdivision Development
Flying Dust First Nation Indian Reserve No. 105 -
SaskPower Pole Replacement near Rec Hall
Prince Albert National Park -
Rabbit Creek Wildfire Reclamation
Prince Albert National Park -
SaskPower replacement of 8 power poles in Prince Albert National Park
Prince Albert National Park -
SaskPower Line Trenching at Operations Compound
Prince Albert National Park -
SaskPower Stabilization of 3 Power Poles in Waskesiu
Prince Albert National Park -
Muskoday First Nation Booster Station Upgrades
Muskoday First Nation -
Parks Canada ski trail reconfiguration in Waskesiu Lake, SK
Prince Albert National Park -
SaskPower Hesje Light Pole
Prince Albert National Park -
Outhouse relocation
Prince Albert National Park of Canada -
Red Deer Campground Electrical Upgrades
Prince Albert National Park -
Construction and Installation of a Clear Span Acrow Panel Bridge at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
SaskPower New U/G Cable and Transformer at Kapasawin Bungalows
Prince Albert National Park of Canada -
SaskPower Underground Cable Install at Kapasiwin Bungalows
Prince Albert National Park -
SaskPower Transformer Replacement and line trenching at Kapasiwin Bungalows
Prince Albert National Park -
SaskPower Cable Installation to Kapasiwin Cabins
Prince Albert National Park -
Boundary Bog Trail Boardwalk Project
Prince Albert National Park -
North Creek Trail Realignment
17 Wing Detachment - Dundurn's Range and Training Area -
Muskoday First Nation Subdivision Development
Muskoday First Nation I.R. 99 -
Muskoday First Nation - Construct Cultural Centre
Muskoday First Nation - Construct Cultural Centre -
Repair of the Waskesiu River riffle weir
Prince Albert National Park of Canada -
Woods Trail Bridge Replacement and Water Course Alteration – 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Muskoday First Nation - Drainage Improvements Phase 1
Muskoday First Nation Reserve -
Grasswoods Reserve Septage Receiving Station, Retention Pond and Final Disposal to City of Saskatoon Forcemain
Grasswoods IR 192J -
Gas Station Construction Saskatoon
Kahkewistahaw Indian Reserve No. 72A-2 -
Muskoday First Nation - Community Access Road
Muskoday First Nation Reserve -
Muskoday First Nation Sewage Lagoon Upgrade
Muskoday First Nation -
Whitecap Dakota First Nation Community Drainage
Whitecap Dakota First Nation No 94 -
Piapot First Nation Prince Albert Urban Gas Bar & Convenience Store
Piapot IR 75 -
Buffalo Berry Culvert Work
Whitecap IR #94 -
Whitecap Dakota First Nation Sewage Pumping Station 3
Whitecap Dakota First Nation No 94 -
Whitecap Dakota First Nation Subdivision Stage 4
NE 35-33-6 W3M -
Whitecap Dakota First Nation Multi-Use Trails
Whitecap Dakota First Nation Multi-Use Trails -
Dakota Springs Spa
Whitecap IR #94 -
Whitecap Dakota Nation Virtual Health Hub
Whitecap Dakota First Nation No 94 -
Whitecap Dakota Nation Water Treatment Plant Upgrade & Wells Project
Whitecap Dakota First Nation No 94 -
Whitecap Dakota Nation Wellbeing Centre
Whitecap No. 94 -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 2) -
Upgrade Woods Trail - 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
Makwa Sahgaiehcan First Nation Well Completion
Makwa Sahgaiehcan First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MAKWA LAKE I.R. 129B (Tower 3) -
Crean Channel Modification
Prince Albert National Park -
Makwa Sahgaiehcan First Nation Transfer Station
Makwa Sahgaiehcan First Nation -
Makwa Lake Resort Development
Makwa Lake Indian Reserve No. 129B -
Tway National Wildlife Area Water Control Structure Re-naturalization Project.
Tway National Wildlife Area -
Fishing Lake First Nation Sewage Pumping Station Upgrades
Fishing Lake First Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 1) -
SaskPower HR-01033 - RPD-511 PQ Rural Rebuild (Makwa Rebuild)
Makwa First Nation -
Magazine Area Recapitalization Canadian Forces Ammunition Depot (CFAD) - 17 Wing Detachment Dundurn
Canadian Forces Ammunition Depot Dundurn,17 Wing Detachment Dundurn -
Woods Trail Intersection Realignment
17 Wing Detachment Dundurn's Range and Training Area -
Replacement of the Fuel Transfer Station and Fuel Tank Systems
17 Wing Detachment Dundurn -
Install Security Fence along Pryor Road at 17 Wing Detachment Dundurn
17 Wing Detachment Dundurn -
MEDA 324 kW Solar Farm
Muskoday IR 99 -
Muskoday Convenience Store Remediation
Muskoday First Nation -
Montreal Lake RCMP New Detachment
Montreal Lake -
Prince Albert Grand Council (PAGC) Women's Shelter
Montreal Lake -
MLCN Montreal LK East Lagoon
Montreal Lake IR 106 -
Enbridge Pipelines Inc. - Line 3 Replacement Program
Kerrobert -
Onion Lake Cree Nation Aquatic Centre Project
Onion Lake Cree Nation Aquatic Centre Project -
Fixed Point-to-Point Link from Dorintosh, SK to Waterhen Lake, SK
Waterhen 130 Reserve -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161A -
Onion Lake Family Services Inc. Child and Family Services Building
Onion Lake First Nation -
Lloydminster Region Abandonment Project
Makaoo Indian Reserve 120 (Onion Lake Cree Nation) -
Dore Lake Wharf Removal
Dore Lake -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
MINISTIKWAN I.R. 161 (Tower 3) -
Ministikwan Subdivision Development
Ministikwan IR 161 -
Ministikwan Lake Cree Nation - Solid Waste Transfer Station
Ministikwan IR161 -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 7: West Central region - Thunderchild Fixed Wireless Tower -
Onion Lake 3D 2026 Seismic Program
Onion Lake 3D 2026 Seismic Program -
James Smith Cree Nation Peonan Creek Crossing
James Smith Cree Nation -
James Smith Miyo-Pimatisiwin Wellness Centre
JAMES SMITH INDIAN RESERVE NO. 100 -
James Smith Cree Nation Solid Waste Transfer Station
James Smith Cree Nation -
Tower Alteration for James Smith Cree Nation Justice & Policing communication system on James Smith Reserve No. 100
James Smith Cree Nation -
Upgrade Single Tower & New Fibre Installation
Project site 8: Central East region - James Smith -
James Smith Cree Nation Headstart and Daycare
JAMES SMITH INDIAN RESERVE NO. 100 -
James Smith Cree Nation Subdivision Stage 4
James Smith Cree Nation -
New (Multiple) Tower Construction, Upgrade (Multiple) Towers
WATERHEN I.R. 130 -
Ministikwan Community Road Repairs
Ministikwan Lake Cree Nation -
RW-4851 Authorization to Construct and Operate a Right of Way for a gas pipeline
Frog Lake First Nation -
Star-Orion South Diamond Mine Project
Fort à la Corne Provincial Forest -
OS-7250 Authorization to Construct and Operate a Surface Lease for an access road and a multi-well pad
Frog Lake First Nation -
OS-7262 Authorization to Construct and Operate a Surface Lease for a multiwell oil pad
Frog Lake First Nation -
OS-7257 Authorization to construct and operate a surface lease for an access road and for a multi-well oil pad
Frog Lake First Nation -
Frog Lake Waskonaman Hill Gravel Project (Amendment)
Frog Lake First Nation -
Powwow Arbour Construction
Pierceland -
New Towers Construction, Upgrade single tower & New Fibre Installation
Project Site 2: West Central region - Big Island Lake -
Big Island Lake Cree Nation Child and Family Service Centre
Big Island Lake Cree Territory