Plumbing System Replacement - CCHM - S5-8

The septic tanks at Locks 5 and 8 of the Chambly Canal are at the end of their life cycle and show signs of advanced deterioration, with the potential for soil contamination. The metal tanks are extremely corroded, which suggests that the contents of the tanks have percolated into the surrounding soil. A soil characterization is required to determine the degree of soil contamination, if any. The metal pits will be replaced with concrete pits. 


Latest update

January 20, 2023 – The public comment period on the project is closed. Parks Canada is considering comments received to help inform its determination on whether the carrying out of the project is likely to cause significant adverse environmental effects.

Participate

Key documents

Key documents
Document Number Document Title File Date
1 New project being assessed by Parks Canada - Public comments invited from December 21, 2022 to January 20, 2023 - December 21, 2022

Contacts

Chambly Canal National Historic Site
1899, boulevard De Périgny
Chambly, Quebec J3L 4C3
Telephone: 450-447-4832
Email: envuvnq-qww@pc.gc.ca


  • Location

    • Chambly Canal National Historic Site of Canada (Quebec)
  • Nature of Activity

    • Building and Property Development
    • Waste Management
    • Maintenance activities (fences, walls)
  • Assessment Status

    In progress
  • Start Date

    2022-12-21
  • Proponent

    Parks Canada
  • Authorities

    • Parks Canada Agency
  • Assessment Type

    Project on federal lands
  • Reference Number

    84194