YUL Montréal-Trudeau International Airport - Demolition of buildings to create parking spaces

The project consists of demolishing four buildings present in parking lots P8 and P9 in order to transform the area into parking spaces. These buildings were used by car rental service centers whose activities have been relocated. Materials from the demolition will be recycled. Asphalting work will also be carried out on the existing parking lots.


Latest update

May 12, 2023 - ADM Aéroports de Montréal issued its Notice of Determination and determined that the project is not likely to cause significant adverse environmental effects by applying the mitigation measures planned for the project.

Participate

Key documents

Key documents
Document Number Document Title File Date
2 Notice of Determination - May 12, 2023
1 Notice of Intent to Make a Determination - Start of Public Comment Period - March 3, 2023

Contacts

Public Affairs
ADM Aéroports de Montréal
800 Place Leigh-Capreol
Office 1000
Dorval, Quebec H4Y 0A5
Email: consultation-projets@admtl.com


  • Location

    • YUL Montreal-Trudeau International Airport (Quebec)
  • Nature of Activity

    • Airport and Airfields
  • Assessment Status

    Completed
  • Start Date

    2023-03-03
  • Proponent

    ADM Aéroports de Montréal
  • Authorities

    • Montreal Airport Authority
  • Assessment Type

    Project on federal lands
  • Reference Number

    84382
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: