Rehabilitation of the Canal Bridge and replacement of spans 1 and 5

InfraMTL Inc., which maintains the infrastructure acquired as part of the development of the REM, must intervene on the Canal Bridge, at the Lachine Canal.

During an inspection conducted in the summer of 2020, several defects were observed. Major repair and replacement work is required to ensure the integrity of the structure and the safety of users.

The project is divided into several phases. The first phase, scheduled for July, consists of removing the out-of-service catenaries, preparing the surface, painting the columns and transfer beam, and finally replacing spans 1 and 5, which are located on the land portion of the bridge only. No work will be done over the Lachine Canal waterway. 

More


Latest update

October 07, 2021 - The assessment decision statement has been issued to the proponent.

Participate

Contacts

Lachine Canal National Historic Site
105, McGill Street, 6th Floor
Montréal, Quebec H2Y 2E7
Telephone: 450-447-4832
Email: envuvnq-qww@pc.gc.ca


  • Location

    • Lachine Canal National Historic Site (Quebec)
  • Nature of Activity

    • Bridges
  • Assessment Status

    Completed
  • Start Date

    2021-05-26
  • Proponent

    External Proponent
  • Authorities

    • Parks Canada Agency
  • Assessment Type

    Project on federal lands
  • Reference Number

    81651