Removal of Pad-Mount Transformer and Switchgear

Project intent is to remove the redundant pad-mounted transformer and switchgear outside the DND Data Centre. The project area is expected to be about 70m2, and is outside of the building envelope. The building itself has a footprint over 1000m2.
In summary the contractor will:
• Perform locates around work area;
• Lift 15kV transformer from pad and remove from site;
• Remove protective bollards and pad;
• Saw cut section of asphalt and excavate to depth required to remove concrete duct bank and conduit
• Reinstate disturbed areas.
 

The comment period has now ended. 


Latest update

January 11, 2021 - The assessment decision statement has been issued to the proponent.

Participate

Contacts

PSPC
Michelle Fairbrother, Environmental Analyst
Telephone: 613-736-3274
Email: michelle.fairbrother@tpsgc-pwgsc.gc.ca


  • Location

    • DND Data Centre (Ontario)
  • Nature of Activity

    • Other, not otherwise specified
  • Assessment Status

    Completed
  • Start Date

    2020-11-02
  • Proponent

    PSPC
  • Authorities

    • Public Services and Procurement Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    81092
Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Nearby assessments

...within 200 kilometres
Date modified: